Video Update-CS 940818CASE:
P & Z HEARING DATE:
C. C. HEARING DATE:
CITY OF COPPELL
PLANNING DEPARTMENT
STAFF REPORT
VALLEY RANCH CENTER, REPLAT OF LOT
B-R3, LOTS C AND D
August 18, 1994
September 13, 1994
LOCATION:
Southeast corner of MacArthur Blvd. and Belt Line Rd.
SIZE OF AREA: 9.92 acres for commercial uses
CURRENT
ZONING:
REQUEST:
LI, Light Industrial
To move the Lot D property line up against Tom Thumb site (Lot C),
and add land area from Lot B to keep Lot C the original size.
APPLICANT:
HISTORY:
Beltline/MacArthur Ranch, LP
Scott Morway
(Owner)
7001 Preston Road, # 225
Dallas, TX 75205
(214) 526-6262
Brockette Davis Drake
Richard Carson
(Engineer)
4144 North Central Expwy. ,#1100
Dallas, TX 75204
(214) 824-3647
The most recent plating history occurred on the Boston Chicken site,
roughly one year ago
TRANSPORTATION:
MacArthur is a six-lane divided which has been built to
standard, contained within a 110 foot r.o.w. Beltline Road is
proposed to be a six lane thoroughfare similar to MacArthur,
but is currently not improved on the west side of MacArthur.
Item 5
SURROUNDING LAND USE & ZONING:
North -
South -
East -
West
Retail in process of development; R zoning
Floodplain; FP zoning
Light Industrial; LI zoning
Light Industrial; LI zoning
COMPREHENSIVE PLAN:
The Plan shows this area to be utilized for light industrial
uses.
ANALYSIS:
This plat generally conforms to our replatting requirements, and staff
supports this application. As pointed out in the ~Request" section of is
report, the replat will accommodate a slightly larger land area north
and east of the existing Tom Thumb store. To compensate the Tom
Thumb site for the reduction in their area, the replat also adds a
comparable land area at the southwest comer of the Tom Thumb site,
resulting in the Tom Thumb gross square footage remaining as
originally platted. The only recommendation staff has for the applicant
is to include a signature block for the City Secretary on the replat.
Staff recommends approval of the replat subject to the above condition
being met.
ALTERNATIVES:
1) Approve
2) Deny
3) Modify
ATTACHMENTS:
1) Replat document
2) Site Plan
3) Landscape Plan