ST9801-CS00101110/11/2880 11:33
FAX (214) 352-3201
October 11, 2000
2149533882 PARAGON-HALFF /f'~ · , e.- PAGE 82
V TELEPHONE (214} 35e-858 1
ED BELL CONSTRUCTION COMPANY
p091' OFFICE BOX 540787
DALLAS. TEXAS 75354-0787
The Mansions by The Lake
620 N. Coppell Road
Coppell, Texas 75019
Coppell Road Reconstruction
SH 121 to Sandy Lake Road
Coppell Project #: ST 98-01
S T't,f "o t
10605 HARRY HINES
DALLAS. TEXAS 75220
Dear Sirs:
It is our intent to begin the final phase of the concrete pavement at the entrance to your property
and prosecute the work in accordance with the following sequence:
Phase 1: Pour the street pavement from the midpoint of the existing driveway entrance
toward the south on October f3 2000. The southern portion of the driveway (entry) will be set
up and poured on October 16, 2000. Traffic will be placed on this portion of the driveway on ~
October 20, 2000. The southern portion (enwy) of the driveway will be closed during this phase.
Traffic will enter the property through the current exit portion of the driveway and exit the
property utilizing the emergency exit on the north end of the property.
Phase 2: After switching traffic to the new driveway, the northern portion of the
driveway and remaining roadway will be excavated and the concrete pavement and driveway will
be constructed. This work will commence on October 23, 2000 and be completed by November.,
3, 2000. Traffic will enter and exit the property through the newly constructed driveway ~\~
entrance. ,
This schedule is subject to minor changes due to unfavorable weather conditions. If you have
any questions regarding this informat!on, don't hesitate to contact our office.
Sincerely,
Ed~__C~.~c~on Company
.\
R~bert D. Weber
Project Manager