Villages C P2-CS 870821NATHAN D. MAIER cONSUL!lNG ENGINEERS, ~NC'. August 21, 1987 Mr. Jeff Hawkins Pierce-Lunsford 3109 Carlisle Suite 206 Dallas, TX 75204 Re: Villages of Coppell, Phase II NDM No.: 84-10-054 Dear Mr. Hawkins: This is to advise you that the paving contractor has been slowed down due to the excessive heat and will not be able to complete by Friday, August 21, 1987. He now projects his date of completion as August 28, 1987· The paving contractor has completed sufficient streets so that the uti-' ltty contractor could proceed, but he recommends that the utility contractor's access ~o the site.be held up until September 2, 1987. Sincerely, NATHAN D. MAIER CONSULTING ENGINEERS, INC. · Nichols G~/rdp cc: Steve Brooks, The Brooks Companies ,~ ~on, C~L'~r o~ Coppell Three NorthPark/8800 N. Central £xpw~;./Sulte 300/Dallas, Texas 75231/(214) 739-4741