Villages C P2-CS 870821NATHAN D. MAIER
cONSUL!lNG ENGINEERS, ~NC'.
August 21, 1987
Mr. Jeff Hawkins
Pierce-Lunsford
3109 Carlisle
Suite 206
Dallas, TX 75204
Re: Villages of Coppell, Phase II
NDM No.: 84-10-054
Dear Mr. Hawkins:
This is to advise you that the paving contractor has been slowed down due
to the excessive heat and will not be able to complete by Friday, August 21,
1987. He now projects his date of completion as August 28, 1987·
The paving contractor has completed sufficient streets so that the uti-'
ltty contractor could proceed, but he recommends that the utility contractor's
access ~o the site.be held up until September 2, 1987.
Sincerely,
NATHAN D. MAIER
CONSULTING ENGINEERS, INC.
· Nichols
G~/rdp
cc: Steve Brooks, The Brooks Companies
,~ ~on, C~L'~r o~ Coppell