Villages C P3&4-CS 910930 COPPELL PUBLIC WOR.F~L By: ~-nnginee ' g DATE= September 30, 1991 TO= Larry Davis, Construction Inspector~ ~ROW= Rey Gonzales, Street Superintendent Villages of Coppell Phase IIIA Walkthru - Seal approach on to Deforest - Seal all curb joints - Replace.broken buttons on Allen - Bring seal up in alley construction joints - Grind concrete slag off of alley intersection - Finish headwall at Denton Creek * Note - Street termination on east end of phase with nearby alley intersection will need to be removed to facilitate curb drainage - extensive grinding done should suffice currently. Please see to it that these issues are addressed prior to requesting any follow up. RG/mp VILLCOPP . RG