DAILY CONSTRUCTION REPORT
PROJECT: Villages of Cottonwood Creek V LOCATION: Coppell
JOB #: 96-1779 DATE: 02-24-97 DAY: Monday TIME: 2pm-4pm
CLIENT: Grand Land 96, L.P. CONTRACTOR: Site Concrete
ACTIVITIES:
WEATHER: Overcast LOW TEMP: 46F HIGH TEMP: 52F
Travelled to job site, as requested, to make pick up twelve
(12) concrete test cylinders made on 02-17-97 (four (4) of which
were made by contractor). Returned to office.
Chris Quentin
Technician
~lt)-- '-~ CON~.LTING EN~INEER8 IN=
T~O~XQUe ,vironlnenta[ Assess;ants
~1~, SoiLs & Foundations
Construction Nateciats Testing
,'Exce[t~ce~ri~e'" C~rciat & i~ustria[ [ns~ction
PO Box 925&8 * S~thiake, Texas 76~2 · (817) ~29-0281
CONCRETE CYLINDER TEST RESULTS
PROJECT: Villages at Cottonwood Creek V LOCATION: Coppell
JOB ~: 96-1779 DATE OF BREAK: 02-24-97 DAY: Monday
CLIENT: Grand Land 96, L.P. CONTRACTOR: Site Concrete
CYL. SLUMP DATE OF DAYS
I.D. LOCATION (IN.) SAMPLE AGED POUNDS PSI
Bricknell Lane North: 4A @ Station 7+00 2.50" 02-17-97 7 84,000 2971
4B @ Station 7+00 2.50" 02-17-97 7 83,500 2954
6A @ Station 1+50, 02-17-97 7 85,500 3024
6B @ Station 1+50' 02-17-97 7 84,500 2989
Eastwick Dr, S Lane: 5A @ Station 0+80 2.75" 02-17-97 7 82,500 2918
5B @ Station 0+80 2.75~' 02-17-97 7 85,000 3007
* Contractor Made
SPECIFICATIONS: 3600 psi @ 28 days
SUPPLIER: Pioneer
Jeffrey Holden
Technician