Villages C P3&4-CS 920701 Federal Emergency Management Agency
Washington, D.C. 20472
CERTIFIED MAIL IN REPLY REFER TO:
RETURN RECEIPT REQUESTED 316-POST/PRE
Mr. Don A. Tipton Date: July 1, 1992
Don A. Tipton, Inc. Case Number: 92-06-037R
6330 Belt Line Road Re: Villages of Coppell-
Suite C Phases 3 and 4
Garland, Texas ?5043 Community: City of Coppell,
Texas
Dear Mr. Tipton:
This is in regard to your recent submission of data in support of your
request for a conditional Letter of Map Revision (LOMR) for the referenced
project. Our review of the data submitted indicates that we do not have the
minimum data we need to continue our evaluation of your request. The
required data are described on the enclosed checklist and must be submitted
before we can continue our review. Unless otherwise directed by you in
writing, the submitted data and fee will not be returned. We will not begin
a detailed review of the submitted data until we receive the requested data.
We have suspended processing of your request pending our receipt of the
requested data. After we receive the requested data, we will continue our
evaluation. If we need additional data to complete our evaluation, we will
inform you in writing.
If the requested data are submitted more than 90 days after the date of this
letter, they will be treated as a new request and will be subject to all
payment procedures, including the initial fee, as described' in Section ?2.4
of the National Flood Insurance Program regulations (copy enclosed).
When you write to us about your request, please include the case number
(shown above) in your letter. If you have any questions about the requested
data, please call Michael Baker Jr., Inc., our Technical Evaluation
Contractor, at (703) 960-8800, and ask for the Revisions Coordinator for your
state.
Sincerely,
William R. Locke
· Chief, Risk Studies Division
Federal Insurance Administration
Enclosures
cc: The Honorable Mark Wolfe
Mayor, City of Coppell
Mr. Kenneth Griffin, P.E.
C'Cl~f-Eng[neer
Mr. Ron Morrison
Morrison Hydrology/Engineering, Inc.
Federal Emergency Management Agency
Washington, D.C. 20472
Case No.: 92-06-037R
Community: City of Coppell,
Texas
Community No.: 480170
Additional Data Required to Support a
Conditional Letter of Map Revision Request
Requestor: Mr. Don A. Tipton Date: July 1, 1992
The items below must be submitted in order to complete the review of the
request for a conditional Letter of Map Revision.
1. The construction plan submitted on June 5, 1992, does not show the
proposed grading of the project area. Please provide us with a
grading plan, certified by a registered professional engineer,
showing the proposed grading.
2. The topographic map submitted on June 5, 1992, does not show how
the 100- and 500-year floodplain and 100-year floodway boundaries
tie into the effective 100- and 500-year floodplain and 100-year
floodway boundaries at both ends upstream and downstream of the
project. Please submit a topographic map that wile show the above.
The required data should be submitted to the following address:
Michael Baker Jr., Inc.
3601Eisenhower Avenue, Suite 600
Alexandria~ Virginia 22304
Attention: Mr. David P. Preusch, P.E.