CF-Coppell Rd SC-LR011112Hooper
Engineering Laboratories,
Construction Materials Testing
Inc.
.CLIENT:
PROJECT:
CONCRETE SUPPLIER:
REPORT OF CONCRETING OPERATIONS
HE JOB NO. 01.1054
Texas Unified Constructors, Inc.
Field Service Offices & Maintenance Facility-
Coppell, TX
Lattimore
LOCATION OF CONCRETE PLACED:
DATE: 12 November 2001
WEATHER: Cloudy/Calm
AIR TEMP: 60°F
7 Piers at Utility Storage Bldg. (.See Pier Report 11/12/01)
Cement:
Brand
m. Ao
I.A.
C.A.
Materials
HolnamType I Source Bin @ Plant #7
Aggregate Type Source
Size
0 #4 Sand Lattimore
1" - #4 Cr. Stone Bridgeport
Actual Batch Computations:
% Free Actual
Moisture Water Batch Wts.
Cement ..414/103
F.A. 5.0 72 1505
C.A. 18 50
Total Free Water
Added at Mixer
Total Water
72 lbs.
170 lbs.
242 lbs.
Design Mix
Mix 54 , 3000 psi
Max. Water-Cement Ratio by weight
Batch Weights - S. S. Dry Basis:
Cement 4.14/10.3 F.A. 1433
I.A. C.A. 1850
Admix Plastocrete _161 @ 15.5 o~/yd
Time Started: ll:20am
Time Finished: ll:50am
Concrete Placed, c.y.: 7.5
Concrete Temp: 75°F
Cyl'inders Made: 49 - 52
Remarks:
Certified Correct ~
Inspector
28~0 Walnut Hill Lane Dallas, Texas 75229 (214) 351-6419 Fax (214) 351-5148
Hooper Engineering Laboratories, Inc.
Construction Materials Testing
BELLED PIER
INSTALLATION OBSERVATION
CLIENT: Texas Unified Constructors, Inc. DATE: 12 November 2001
PROJECT: Field Service Offices & Maint. Fac., Coppell, TX JOB NO.: 01.1054
DRILLER: TIME: 9:30am-1 2:30pm
3.0 hours
PIER
MARK
SHAFT BELL ALIGN/ REQ'D INITIAL FINAL FINAL TOP OF WATER
DIA. SIZE PLUMB DEPTH DEPTH DEPTH POUR CONC. ELEV. IN HOLE
Utility Storage Buildin,q
12-C/6
21 -B/6
22-B/7
23-B/8
24-B/8.9
25-B/10
11 -C/10
18" 48" (2)/ok 13.0' 11.0' 11.2' 11:46 -1.6' None
18" 48" (2)/ok 13.0' 11.5' 11.5' 11:22 -1.6' None
18" 48" (2)/ok 13.0' 11.5' 11.5' 11:26 -1.2' None
18" 48" (2)/ok 13.0' 10.9' 11.0' 11:30 -1.O' None
18" 48" (2)/ok 13.0' 10.6' 10.9' 11:34 -1 .O' None
18" 48" (2)/ok 13.0' 11.5' 11.7' 11:38 -1.4' None
18" 48" (2)/ok 13.0' 10.6' 11.5' 11:43 -1.4' None
REMARKS:
1) Pier reinforcing verified to be correct in accordance with project plans and specifications,
unless noted otherwise.
2) These piers were drilled and belled on 11/9/01, but no concrete was placed due to heavy rain
and muddy site conditions. Holes were covered with plywood. Final depths and bell sizes were
rechecked and verified to be the same as initially drilled. Concrete was placed today, 11/12/01.
3) Required Depth is based upon existing grade at time of geotechnical investigation. Correct
bearing strata achieved, unless noted otherwise.
4) Initial Depth, Final Depth, and Top of Concrete Elevation, are relative to grade at time
piers were drilled. Contractor must furnish actual elevation, if required.
5) Driller found sand to be approximately 11.5' in this area. Per superintendent for Texas Unified,
other piers were stopped at approximately 11.0'.
TECHNICIAN:
DISTRIBUTION:
MFM
(3) City of Coppell
(1) Vidaud & Associates
(1) Doyle Engineering Group
(1) Texas Unified Constructors, Inc.