Loading...
ST9601-CS 981202 TEAGUE NALL AND PERKINS INC. ENGINEERS f SURVEYORS · MUNICIPAL CONSUL TANTS December 02, 1998 Mr. Michael Martin, P.E. Engineering Depa~ent Ci~ of Cop~ell ~ ~/~ ' Consuffing Engin~rs Contm~ Dear Mike: ~,~ prepare, ~r y0Ur'~ueSt, in a=rdan~ with the appli~ble provisions offfie Enginering Sewi~s Cont~~ f~r:th~ :~g le~Drive :Re~ns~ib~ :'P~0je~da~:A~t 1 improveen~ along wrangler Ddve, adja~nt to the Coppell Middle School West. A pmlimina~ opinion of probable ~nstm~ion ~st for these addffional improvements is also enclos~ for your info~ation. The subject Modification of the Scope of Se~ices is based upon the following undemtanding:. 1. The alignmentforffie proposed water line m~tionladjustment will be along the south side of Wrangler Drive, from approximately Sta. 8+25 to Sta. 18+00, save and ex~pt a poffion of the existing water approximately 30 feet either side of the ~o (2) water meter vaults to 2. The Ci~ will provide plans for the existing water, sanita~ sewer, paving and drainage improvements within and/or adja~nt to the proje~ area. 3; The Proposed improvements will be inco~orated into 'the 'currant '= ~nstm~ion contract with Tiseo Pa~ng by Change: Order andWill 'not require '~* ': the' prepara~on of a :'Separate Set of bid or do~raCt 915 FLORENCE S1RET FORT WtIRIH. TEXAS 76102 (817) J36-577J FAX (817) J36-281J Mr. Michael Martin, P.E. - City of Coppell December 02, 1998 Page 2 Should you have any questions regarding the proposed Modifications to the Scope of Services, please give me a call. Sincerely,  ~3~GUE NALL AND PERKINS, INC. Michael A. Jones, P.E. Enclosures Q:\proj-rl 4%cp196164\docs\corres~contract.modification.water line adjust. letter. wpd CITY OF COPPELL Consulting Engineer's Contract Modification to the Scope of Services I. ADDITIONAL SCOPE OF SERVICES Design of approximately 900 linear feet of 12-inch water line relocation and other related improvements along Wrangler Drive, adjacent to the Coppell Middle School West. Information from the previous design surveys for Wrangler Drive will be used as the base for the proposed design, therefore no additional design surveys will be performed. II. PROJECT SCHEDULE The additional design will be completed within 20 working days from receipt of written approval/authorization for the Modification to the Scope of Services from the City. III. COMPENSATION The Engineer shall be paid an additional fee for the above described Additional Scope of Services in an amount not to exceed the lump sum of Five Thousand Two Hundred and no/100 Dollars ($5,200.00). This amount includes nothing for design surveys and $5,200 for basic engineering services. APPROVED: AGREED/ACCEPTED: THE CITY OF COPPELL U~~~/~ Date: Date: /~----~/(~"~ / Attest: Attest' 'l ~SAGUE NALL AND PERKINS, INC. !ENGINEER'S PRELIMINARY OPINION OF PROBABLE COST December 02, 1998 City of Coppell, Texas Project Name: 12-Inch Water Line Relocation on Wrangler Drive Proj. No. CPL 96164 (Adjacent to Coppell Middle School West) ITEM DESCRIPTION OF ITEM UNIT TOTAL UNIT COST NO. QUANTITY PRICE Proposed W. L. Improvements I 6-Inch Water Line LF 20 29.00 580.00 2 8-Inch Water Line LF 10 31.50 315.00 3 12-Inch Water Line LF 895 27.00 24,165.00 4 6-Inch Gate Valve Each 2 975.00 1,950.00 5 8-Inch Gate Valve Each I 1,125.00 1,125.00 6 12-Inch Gate Valve Each 2 1,600.00 3,200.00 7 Fittings Tons 0.75 5,250.00 3,937.50 8 Fire Hydrant Each 2 1,800.00 3,600.00 9 Connect to Existing System Each 5 895.00 4,475.00 10 Abandon Existing Water Line LS 1 1,500.00 1,500.00 11 Remove/Replace Concrete Driveway SY 100 31.00 3,100.00 12 Protect/Repair Existing Irrigation System LS 1 1,500.00 1,500.00 13 Trench Safety for W.L. LF 925 1 ~10 1,017.50 PREPARED BY: SUBTOTAL $50,465.00 CONTINGENCY (+5%) $2,535.00 REVIEWED & APPROVED BY: TOTAL $53,000.00 p:~cp196164\engrdata\12-inch.wlcost wb2 Page 1 of 1