Coppell Industrial-LR010426 GEOTECHNICAL A.N:) G F=I r-'l I I F=~
ENV RONMENTAL CONSULT'-,.NTS i
REPORT OF WATER INJECTION OBSERVATION
TradePoint One
Bethel Road and Royal Lane
Coppell, Texas
REPORTED TO: CP-Coppell Industrial. Ltd. REPORT NO. 44
c/o Champion Partners. Ltd. REPORT DATE: 04-26-01
15601 Dallas Parkway, Suite 100 REG PROJECT NO. 7394
Addison. Texas 75001 TECHNICIANS: K. Blaylock &
ATTN: Mr. Kerry Burden C. Johnson
PAGE: 1 of 1
On these dates representatives of Reed Engineering Group, Inc. observed water injection
operations on the referenced project. The injection operations proceeded in accordance
with project specifications unless otherwise noted.
Specification
Injection Depth Injection Spacing Injection Pressure Injection Intervals
(ft) (ft) (psi) (in)
10 5 100-200 12-18
Equipment
Number of Number of Probes Length of Probes Probe Spacing
Rigs (ea) (ft) (ft)
7 4 12.0 5
Date Area Injected (sq ft) Average Pressure (psi) Pass No.
04-09-01 55,700 150 1
i04-10-01 73,000 150 1
04-11-01 70,000 150 1
Surfactant added at regular intervals: Yes
Mail Submitted by:
Distribution: (1) Champion Partners, Ltd./
Mr. Kerry Burden REED ENGINEERING GROUP, INC.
(1) C.D.Henderson, Inc./
Mr. Jason Nunley Original Signed By
(1) AECC. Inc./Mr. Fran Carter
(1) Meinhardt & Quintana/ James F. Phipps, P.E.
Mr. David Meinhardt BW/mm
(1) Haynes Whayley Associates Inc./
Mr. Kent Penrod
(1) City of Coppell/Mr. Larry Davis
(1) City of Coppell/Mr. Lee Stone
2424 STUTZ DR · SUITE 400 · DALLAS. TX 75235 o -[_ [214] ]50 5600 · =~,,,, [214] 350 0019
REPORT OF FIELD DENSITY TESTS
TradePoint One
Bethel Road and Royal Lane
Coppell, Texas
REPORTED TO: CP-Coppell Indbstnal. Ltd. REPORT NO. 43
c/o Champion Pa~ners. Ltd. REPORT DATE: 04-26-C'
1560~ Dallas Parkway. Suite 100 REG PROJECT NO. 7'394
Addison. Texas 75001 TECHNICIAN: M Si:va
ATTN: Mr. Kerry Burden PAGE: 1 of
CONTRACTOR: C.D. Henderson. Inc.
Proctor i ASTM:I I Optimum Maximum
No. ' Standard Description Moisture, % Density, PCF
I 1 D-598 Da'k crown clay 23.5 ? 5
2 D-898 B'ow~ & gh: crown clay. 23.0
3 D-698 S'owp and :an clay 17 C "06 C
Depth
Below Field Field
,Test Final S. G. Dens ty Moisturei Proctor Compaction
(feet) '
I: No. i Date I Location i (pcf) (%) ID Level (%)
296 34-09-31 Blda Pad 580 N -~"*' : ' ."', ~ '.-55 C
~ ~, ¥wl ._ 1007 18.8
297 B~cg Pad: 520'K. !30W:', ' C 59.6 25 8 2
298 Bcg Pad: 523'N. 20C'W, '~ ' C '00.6 '8 5 3 24
299 Bdg Pac ~8.. N : 3 8-q - 2 95
300 Bidg Pac 580N 253'W, 1: 3 978 20.3 3 92.2
3.91 BIdG Pad 520 N 3t.d ,-~.1. ~ 89 5 25.5 2 95.
..... ' .. 88 5 26.'
302 BId~c Pad c20 N 4~u vv;1. r, 2 ~4
303 BldgPad 580N 35uW;1, 0 =3.3 25.0 2
~,'~' Bica~ Pad: 520'1',. 530 W: ' , ,'~ ~'--8. ' z~"n ," 3 92
3C5 B'cg Pad: 580'N. 450 N~', t; ~a 3 ~9 9 3
306 ~avi,'g 33'N. 17C'E.1, ' 3 88 ' 2-' 8 95 2
_7 5 25 3
337 Pay ¢g. 80 N '2O'E~', 3 g -
Comments' Where tested, materials were in compl once w'th project specifications anless no;e=
Footnote: : 1'~ Measurements referencec from S E. corner of buildimg
Mai~ Submitted by:
Distribution: ' ~' ..... ' ....~
.' C D He~=erss~. I"~. REED ENGINEERING GROUP, INC.
· -la,-es ?:-~-~ ey Asses a:es I-c Roma.d F. Reec. P. E
%1' Ke-t Fe~-:= BW/myw
GEOTECHNICAL AND J
ENVIRONFIENTAL CONSULTANTS
CONCRETE CYLINDER TEST REPORT
TradePoint One
Bethel Road and Royal Lane
Coppell, Texas
REPORTED TO: CP-Coppell Industrial, Ltd. REPORT NO. 56
Ltd. REG PROJECT NO. 7394~
c/o
Champion
Partners,
15601 Dallas Parkway, Suite 100 SAMPLE DATE: 04-26-01 "~
Addison, Texas 75001 TECHNICIAN: Contractor '~
ATTN: Mr. Kerry Burden _\_.
CONTRACTOR: C.D. Henderson, Inc.
Location of Sample
ISet Number I Location I Quantity Represented
1 Unknown Unknown
Design Information
Source of Concrete I Mix Identification I Specified Strength p.s.i.
N/A N/A N/A
Test Results
Set [ CylinderI Age@ I Tote, Load I Compressive [ Average
No. ID Date Tested Test lbs. Strength p.s.i. Strength p.s.i.
1 6776 05-03-01 7 125840 4450
6776 05-24-01 28 149320 5280
6776 05-24-01 28 152010 5380 5330
Cylinder Data
set I Cylinder[ Time ofI I Concrete Air Ticket
No. ID Slump Sample Air Temp. Temp. Entrainment Number
1 6776 N/A N/A N/A N/A N/A N/A
Mail Submitted by:
Distribution: (1) Champion Partners, Ltd./
Mr. Kerry Burden REED ENGINEERING GROUP, INC.
(1) C.D.Henderson, Inc./
Mr. Jason HuRley Original Signed By
(1) AECC, Inc./Mr. Fran Carter
(1) Meinhardt & Quintana/ Keith Atkins
Mr. David Meinhardt KEAJje
(1) Haynes Whayley Associates, Inc./
Mr. Kent Penrod
(1) City of Coppell/Mr. Larry Davis
(1) City of Coppell/Mr. Lee Stone
(1) Potter Concrete/Mr. Brent Cox
2424 STUTZ DR. · SUITE 400 o DALLAS. TX 75235 · ----'- [214] 350 5600 · F^x [214] 350 0019
GEOTECHNICALAND J ~ ~ r"l I I J:~
ENV:RONMENTAL CONSULTANTS
CONCRETE CYLINDER TEST REPORT
TradePoint One
Bethel Road and Royal Lane
Coppell, Texas
REPORTED TO: CP-Coppell Industrial, Ltd. REPORT NO. 56
c/o Champion Partners, Ltd. REG PROJECT NO. 7394
15601 Dallas Parkway, Suite 100 SAMPLE DATE: 04-26-01
Addison, Texas 75001 TECHNICIAN: Contractor
ATTN: Mr. Kerry Burden
CONTRACTOR: C.D. Henderson, Inc.
Location of Sample
Set Number J Location J Quantity Represented
1 Unknown Unknown
Design Information
Source of Concrete J Mix Identification J Specified Strength p.s.i.
N/A N/A N/A
Test Results
Set [ CylinderI Age@ Total Load J Compressive ] Average
No. ID Date Tested . Test lbs. Strength p.s.i. Strength p.s.i.
1 6776 05-03-01 7 125840 4450
6776 05-24-01 28
6776 05-24-01 28
Cylinder Data
Set j Cylinder [ Timeof! I ConcreteI Air J Ticket
No. ID Slump Sample J Air Temp. Temp. Entrainment Number
1 6776 N/A N/A N/A N/A N/A N/A
Mail Submitted by:
Distribution: (1) Champion Partners, Ltd./
Mr. Kerry Burden REED ENGINEERING GROUP, INC.
(1) C.D.Henderson, Inc./
Mr. Jason Nunley Original Signed By
(1) AECC, Inc./Mr. Fran Carter
(1) Meinhardt & Quintana/ Keith Atkins
Mr. David Meinhardt KEA/je
(1) Haynes Whayley Associates, Inc./
Mr. Kent Penrod
(1) City of Coppell/Mr. Larry Davis
(1) City of Coppell/Mr. Lee Stone
(1) Potter Concrete/Mr. Brent Cox