REPORT OF WATER INJECTION OBSERVATION
TradePoint One
Bethel Road and Royal Lane
Coppell, Texas
REPORTED TO: CP-Coppell Industrial, Ltd. REPORT NO. 31
c/o Champion Partners, Ltd. REPORT DATE: 03-27-01
15601 Dallas Parkway, Suite 100 REG PROJECT NO. 7394
Addison, Texas 75001 TECHNICIAN: C. Johnson
ATTN: Mr. Kerry Burden PAGE: 1 of 1
On these dates a representative of Reed Engineering Group, Inc. observed water injection
operations on the referenced project. The injection operations proceeded in accordance
with project specifications unless otherwise noted.
Specification
Injection Depth I Injection Spacing Injection Pressure Injection Intervals
(ft) J (ft) (psi) (in)
10 5 100-200 12-18
Equipment
Number of Number of Probes J Length of Probes Probe Spacing
Rigs (ea) J (ft) (ft)
2, 4 4 12.6 5
Date J Area Injected (sq ft) J Average Pressure (psi) Pass No.
03-16-01 27.600 150 1st. 2nd
03-17-01 27.000 150 2nd
Surfactant added at regular intervals: Yes
Mail Submitted by:
Distribution: (1) Champion Partners, Ltd./
Mr. Kerry Burden REED ENGINEERING GROUP, INC.
(1) C.D.Henderson, Inc./
Mr. Jason Nunley Original Signed By
(1) AECC, Inc./Mr. Fran Carter
(1) Meinhardt & Quintana/ James F. Phipps. P.E.
Mr. David Meinhardt BW/myw
(1) Haynes Whayley Associates Inc./
Mr. Kent Penrod
(1) City of Coppell/Mr. Larry Davis
(1) City of Coppell/Mr. Lee Stone
2424 STUTZ DR. · SUITE 400 · DALLAS, TX 75235 · -:-L [214] -~50 5600 · =-'× [214] 350 00!9
· GEOTECHNICAL AN~ [~i J:::;J I'--1 I I ~
ENVIRONMENTAL CONSULTANTS
REPORT OF WATER INJECTION OBSERVATION
TradePoint One
Bethel Road and Royal Lane
Coppell, Texas
REPORTED TO: CP-Coppell Industrial. Ltd. REPORT NO. 29
cio Champion Partners. Ltd. REPORT DATE: 03-27-01
15601 Dallas Parkway, Suite 100 REG PROJECT NO. 7394
Addison. Texas 75001 TECHNICIAN: C. Johnson
ATTN: Mr. Kerry Burden PAGE: 1 of 1
On these dates a representative of Reed Engineering Group. Inc. observed water injection
operations on the referenced project. The injection operations proceeded in accordance
with project specifications unless otherwise noted.
Specification
Injection Depth Injection Spacing Injection Pressure Injection Intervals
(ft) (ft) (psi) (in)
10 5 100-200 12-18
Equipment
Number of Number of Probes I Length of Probes Probe Spacing
Rigs (ea) ! (fi) (ft)
3 4 12.6 5
Date I Area Injected (sq ft) !,Average Pressure (psi) Pass No.
03-12-01 9.200 150 1 st
03-13-01 18.400 150 1 st
03-14-01 4,600 130 1st
03-15-01 13,800 130 1st
Surfactant added at regular intervals: Yes
Mail Submitted by:
Distribution: (1) Champion Partners. Ltd./
Mr. Kerry Burden REED ENGINEERING GROUP, INC.
(1) C.D.Henderson. Inc./
Mr. Jason Nunley Original Signed By
(1) AECC, Inc./Mr. Fran Carter
(1) Meinhardt & Quintana/ James F. Phipps, P.E.
Mr. David Meinhardt BW/myw
(1) Haynes Whayley Associates Inc./
Mr. Kent Penrod
(1) City of Coppell/Mr. Larry Davis
(1) City of Coppell/Mr. Lee Stone