Verizon-LR 981214REPORT OF REINFORCING STEEL INSPECTION IBC 8901 Carpenter Frwy., Suite # 100 Dallas, Texas 75247 Date of Service: 12/14/98 Report No.: Client No.: 08644025 Project No.: Client: The Beck Group Project: Attn: Gillett Berger 1700 Pacific Ave., Suite 3800 Dallas, TX 75201-4619 Services: 9833617 43-2333-98 GTE Shared Services Coppell Road & Corporate Drive Coppell, Texas Observe placement of reinforcing for compliance with furnished drawings. DRAWINGS UTILIZED: LOCATION/ITEMS INSPECTED: PROJECT DATA On site Paving, Placement #3, northwest quadrant TEST METHOD: Visual Observation REPORT OF INSPECTION ITEMS INSPECTED CORRECT INCORRECT ITEMS INSPECTED CORRECT INCORRECT IfF..MS INSPECTED I CORRECT INCORRECT Placing D~awings Approved X Bar Length and Shape X Column Tied Pr(~oedy Ba~ Size X Pm~oer Bar Placement X Ties and Spaces X Bar Grade X Pmdefly Trod X Stirrup Spacing/Type Rebar Clean X Dowel Bars in Place X Welded Splices Fern1 Clean X Proper Bar Supports X Mechanical Splices Number el Ba~s X Lapped Splices X Pn3oer Cover X DISCREPANCIES/COMMENTS: Dowel bars were straightened. Technician: 1VI. edom Report Distribution: (1) The Beck Group (1) Gromatzky Dupree & Assoc. (1) Brockette Davis Drake, Inc. (1) The Beck Group Started: See Reports #9833615 and #983616 (1) Brockette Davis Drake, Inc. (1) N.L. Schutte Foundation Drilling (1) The Beck Group I--BC Engineering, Inc. Eugene Harbour Vice President 309ss This report is exciusivety for tho uso of the client indicated above and shalt not be reproduced except in full wathout the writlen approval of HEtC Engineering. Icc CONCRETE COMPRL 3SIVE STRENGTH TE £ Date of Service: 11/12/1998 Report No.: Client No.: 08644025 Project No.: Client: The Beck Group Project: Attn: Gillett Berger 1700 Pacific Ave., Suite 3800 Dallas TX 75201-4619 8901 Carpenter Frwy., Suite #100 Dallas, Texas 75247 9830806 Report Date 12/14/1998 43-2333-98 GTE Shared Services Coppell Road & Corporate Drive Coppell, Texas Services: Obtain samples of fresh concrete at the placement locations, perform required field test and cast compressive strength samples. CONTRACTOR: BECK CONCRETE SUPPLIER: WXI PLANT: 41 SPECIFICATION REQUIREMENTS STRENGTH: 4000 psi @ 28 Days SLUMP: 3-5" AIR: NA TEST MYTHOD: ASTM C-143 ASTM C-172 ASTM C-39 PROJECT DATA CONCRETE CLASS: 564 PLACEMENT DATE: 11/12/1998 BATCH TIME: l:35pm TIME SAMPLED: 3:00pm BY: Keith Fowler WEATHER CONDITIONS: TEMPERATURE (F) - AIR TRUCK NO: 463 AIR CONTENT (%): N/A PLACEMENT LOCATION: Light rain, cool 50 F CONCRETE: 60 TICKET NO: 1180982 UNIT WEIGHT (pcf): West wing section "B", Grade beam A to C on 8 Line, K9 to 10, & 11E to G SAMPLE LOCATION: K9 to 10 CYLINDER MEASURED MARKED SLUMP DATE SET NO. (inches) TESTED 1 1 6.00 11/19/1998 1 2 6.00 11/19/1998 1 3 6.00 12/10/1998 1 4 6.00 12/10/1998 REPORT OF TESTS ACCU1VIULATIVE YARDS: 20 MAXIMUlVI COMPRESSIVE AGE LOAD STRENGTH (days) (lbs. force) (psi) 7 117450 4150 7 116470 4120 Average 4140 28 186420 6590 28 190270 6730 Average 6660 1 5 6.00 01/07/1999 56 FRACTURE TYPE Technician time: See Report #9830749 Technician: Keith Fowler Report Distribution: (1) The Beck Group (I) Gromatzky Dupree & Assoc. (!) Brockette Davis Drake, Inc. (!) The Beck Group Started: (1) The Beck Group (I) Dalcan, Inc. Finished: I-"]~z~~,g r in g, Inc. Eugene Harbour Vice President This report is exclusively for thc use of the client indicated above and shall not be reproduced except in full without the written approval of HBC Engineering, Inc. 0ILL Page I of 1 CONCRETE COMPRESSIVE STRENGTH TE5 £ ENG--, ~C. .. 8901 Carpenter Frwy., Suite #100 Dallas, Texas 75247 Date of Service: 11/12/1998 Client No.: 08644025 Report No.: 9830749 Project No.: 43-2333-98 Report Date 12/14/1998 Client: The Beck Group Attn: Gillett Berger 1700 Pacific Ave., Suite 3800 Dallas TX 75201-4619 Project: GTE Shared Services Coppell Road & Corporate Drive Coppell, Texas Services: Obtain samples of fresh concrete at the placement locations, perform required field test and cast compressive strength samples. CONTRACTOR: BECK CONCRETE SUPPLIER: TXI PLANT: 41 SPECIFICATION REQUIREMENTS STRENGTH: 5000 psi @ 28 Days SLUMP: 3-5" AIR: N/A TEST METHOD: ASTM C-143 ASTM C-172 ASTM C-39 SAMPLE LOCATION: A-3 CYLINDER MARKED SET NO. MEASURED SLUMP (inches) 1 1 6.50 1 2 6.50 I 3 6.50 1 4 6.50 1 5 6.50 PROJECT DATA CONCRETE CLASS: 658 PLACEMENT DATE: 11/12/1998 BATCH TnVm: h27pm TrME SAMPLED: 3:20pm BY: Keith Fowler WEATHER CONDITIONS: Light rain, cool TEMPERATURE (F) - AIR 50 F CONCRETE: 66 F TRUCK NO: 455 TICKET NO: 1180977 AIR CONTENT (%): N/A UNIT WEIGHT (pcp: N/A PLACEMENT LOCATION: West wing, section "A", columns Al thru A6 ' DATE TESTED 11/19/1998 11/19/1998 12/10/1998 12/10/1998 REPORT OF TESTS ACCUMULATIVE YARDS: 10 MAXmm COm'RESSlVZ AGE LOAD STRENGTH (days) (lbs. force) (psi) 7 120180 4250 7 115640 4090 Average 4170 28 172340 6090 28 170910 6040 Average 6070 01/07/1999 56 FRACTURE TYPE Technician: Keith Fowler Report Distribution: (1) The Beck Group (1) Gromatzky Dupree & Assoc. (1) Brockette Davis Drake, Inc. (l) The Beck Group Started: 12:00pm (1) The Beck Group (1) Dalcan, Inc. Finished: 5:30pm Eugene Harbour Vice President This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written approval of HBC Engineering, Inc. OILL Page 1 of 1 CONCRETE COMPRL3SIVE STRENGTH TEf'£ Date of Service: Client No.: Client: 10/15/1998 08644025 The Beck Group Attn: Gillett Berger 1700 Pacific Ave., Suite 3800 Dallas TX 75201-4619 Report No.: Project No.: Project: .. 8901 Carpenter Frwy., Suite #100 Dallas, Texas 75247 9828129 Report Date 12/14/1998 43-2333-98 GTE Shared Services Coppell Road & Corporate Drive Coppell, Texas Services: Obtain samples of fresh concrete at the placement locations, perform required field test and cast compressive strength samples. CONTRACTOR: BECK CONCRETE SUPPLIER: TXI PLANT: 41 SPECIFICATION REQUIREMENTS STRENGTIt: 3000 psi @ 28 Days SLUMP: 5" AIR: N/A TEST METHOD: ASTM C- 143 ASTM C-172 ASTM C-39 SAMPLE LOCATION: Pier A-7 PROJECT DATA CONCRETE CLASS: 9506 PLACEMENT DATE: 10/15/1998 BATCH TIME: 10:lDam TIME SAMPLED: 1 l:20am BY: Brian Otis WEATHER CONDITIONS: TEMPERATURE (F) o AIR TRUCK NO: 455 AIR CONTENT (%): N/A PLACEMENT LOCATION: Piers Clear, mild 84 F CONCRETE: 81 F TICKET NO: 1160658 UNIT WEIGHT (pct'): N/A CYLINDER MEASURED MARKED SLUMP SET NO. (inches) 1 1 5.50 1 2 5.50 1 3 5.50 1 4 5.50 1 5 5.50 REPORT OF TESTS ACCtr~rOLAnVE YAMS: MAXIMUM COMPRESSIVE DATE AGE LOAD STRENGTH TESTED (days) (lbs. force) (psi) 10/22/1998 7 92450 3270 10/22/i998 7 87350 3090 Average 3180 11/12/1998 28 124260 4390 11/12/1998 28 114490 4050 Average 4220 12/10/1998 56 133610 4720 10 FRACTURE TYPE Technician Time: See Technician: Brian Otis Report Distribution: (1) The Beck Group (I) Gromatzky Dupree & Assoc. (I) Brockette Davis Drake, Inc. (1) The Beck Group Report #9828128 Started: (1) The Beck Group (1) Dalcan, Inc. Finished: Eugene Harbour Vice President This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written approval of HBC Engineering, Inc. 01SS Page 1 of 1 CONCRETE COMPRi. 3SIVE STRENGTH TE £ ENGINEERING, INC. 8901 Carpenter Frwy., Suite #100 Dallas, Texas 75247 Date of Service: 12/01/1998 Client No.: 08644025 Report No.: 9832456 Project No.: 43-2333-98 Report Date 12/14/1998 Client: The Beck Group Project: Attn: Gillett Berger 1700 Pacific Ave., Suite 3800 Dallas TX 75201-4619 GTE Shared Services Coppell Road & Corporate Drive Coppell, Texas Services: Obtain samples of fresh concrete at the placement locations, perform required field test and cast compressive strength samples. CONTRACTOR: BECK CONCRETE SUPPLIER: TXI PLANT: 41 SPECIFICATION REQUIREMENTS STRENGTH: 5000 psi @ 28 Days SLUMP: 6.0" Max AIR: N/A TEST METHOD: ASTM C-143 ASTM C-172 ASTM C-39 SAMPLE LOCATION: West side pit slab, Area B PROJECT DATA CONCRETE CLASS: N/A PLACEMENT DATE: 12/01/1998 BATCH TIME: 1:3 lpm TIME SAMPLED: 2:10pm BY: Mike Odom WEATHER CONDITIONS: TEMPERATURE (F) - AIR TRUCK NO: 806 AIR CONTENT (%): 1.4% PLACEMENT LOCATION: Partly cloudy 73 r CONCRETE: 76 F TICKET NO: 1191562 UNIT WEIGHT (pet): N/A Building Area (B) @ elevator (passenger) pit slabs/columns @ Building area (B) @ elevator (passenger) pit slabs/columns @ M-5-9.7, Area B Level !-2 columns at G-15/H-14, 15, Area C, Level I-2. CYLINDER MEASURED MARKED SLUMP DATE SET NO. (inches) TESTED 1 1 5.75 12/08/1998 7 1 2 5.75 12/08/1998 7 REPORT OF TESTS ACCUMULATIVE YARDS: 16.5 MAXIMUM COMPRESSIVE AGE LOAD STRENGTH FRACTURE (days) (lbs. force) (psi) TYPE 131030 4630 130O4O 4600 Average 4620 1 3 5.75 12/29/1998 28 1 4 5.75 12/29/1998 28 1 5 5.75 01/26/! 999 56 Pit slabs only require 4000 "but" same 5000 psi mix used. Technician: Mike Odom Report Distribution: (I) The Beck Group (1) Gromatzky Dupree & Assoc. (l) Brockette Davis Drake, Inc. (!) The Beck Group Started: l:30pm (1) The Beck Group (1) Dalcan, Inc. Finished: 3:00pm m~ Engi Vice President This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written approval of HBC Engineering, Inc. 01LL Page 1 of 1