Verizon-LR 981112IN-PLACE DENSITY IESTING
Date of Service:
Client No.:
Client:
11/03/1998
THE BECK
The Beck Group
Attn: Gillett Berger
1700 Pacific Ave., Suite 3800
Dallas TX 75201-4619
ENGINEERING, INC.
8901 Carpenter Frwy., Suite #100
Dallas, Texas 75247
Report No.: 9829856
Project No.: 43-2333-98
Report Date
11/12/1998
Project:
GTE Shared Services
Coppell Road & Corporate Drive
Coppell, Texas
Services: In-place density testing.
CONTRACTOR: BECK
PROJECT DATA
Laboratory Test Method: ASTM D-698
Field Test Method:
ASTM D-2922
ASTM D-3017
MOISTURE DENSITY RELATIONS:
M/D No.
Maximum
Description Moisture % Density pcf
Project Requirements
Moisture Density
1 Dark reddish brown sitly 10.0 124.5
clayey sand with gravel
FIELD DENSITY TESTS
-1/+3% 95%
TEST MID MOISTURE
NO TEST LOCATION No. (%)
DRY DENSITY DENSITY
(pc0 (% max)
Paving, Placement C, Firelane
237 SE approach, 120'N of centerline, Final Lift 1 11.6
238 SE approach, 300'NE left of centerline, Final Lift 1 11.4
239 SE approach,240'NW right of centerline, Final Lift 1 11.7
West Wing Footing
240 at 8.0-A.5, Final Lift 1 10.9
241 at 1.0-A.5, Final Lift 1 11.0
242 at 1.0-C.6, Final Lift 1 10.8
Test results on this report meet project specification.
120.4 97
120.1 97
120.6 97
121.8 98
121.9 98
121.6 98
Technician: Tex King
Report Distribution:
:'~'.') The Beck Group
"::~:::: ,~ Gromatzky Dupree & Assoc.
(I) Brockette Davis Drake, Inc.
(!) The Beck Group
(!) Brockette Davis Drake, Inc.
(!) Cooper Excavation
(1) The Beck Group
~ En Inc.
Eug~
Vice President
This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written approval of HBO Engineering, Inc.
07TMP Page 1 of I . . ,, .