Villages C LOMR-SY 860510
JOB NUMBER 85048
DATE: 5/10/86
A FLOOD INSURANCE STUDY REVISION
OF ELM FORK OF THE TRINITY RIVER
IN COPPELL, TEXAS
FOR
MR. DAVID WETH
VISTA PLEX DEVELOPMENT, INC.
S1Sl BELTLINE ROAD, SUITE 1016
DALLAS, TEXAS 75240
BY
CAFFEY AND MORRISON, INC.
2218 ARLINGTON DOWNS ROAD, SUITE 105
ARLINGTON, TEXAS 76011
&
,, INC.
CAFFEY AND MORRISON, INC.
ENGINEERS -- HYDROLOGISTS
May 10, 1986
Mr. David Heth
Vista Plax Development, Inc.
5t5! Beltline Road, Suite 1016
Dallas, Texas 75840
Re: Flood Insurance Study Revision of Elm Fork of the
Trinity River in Coppell, Texas/Job No, 85048
Dear Mr. Hath:
In late August, 1985, we discussed the flood plain/floodway
on your property in Coppell, Texas. This flood plain
involved Denton Creek and the Elm Fork of the Trinity River.
At that time, we had two options: begin a,study to redefine
the flood plain or wait for the Corps of Engineers to finish
their ongoing study of the area. To help with this
decision, we contacted the Corps and got an estimated
completion date for their study. The Corps told us that
they would be finishing the study by September. Me took
them at their word and recommended that we wait until the
Corps finished this study so that we would have solid data
to use as a baseline.
As you are well aware, the Corps moved their completion
dates from September to October to November to December to
January to February, and finally our last conversation
indicated possibly another two or three more months.
Conversations with the Federal Emergency Management Agency
indicated that they don't expect results for possibly six
months. In light of this schedule slippage by the Corps, we
felt that the only way to obtain a project completion within
a reasonable time frame was to complete the study through
the area ourselves. This was a formidable task since a
number of projects are underway or completed for the area.
We first tried to obtain data regarding completed projects
from the cities in the area, but they could provide very
little help. Finally, with the aid o¢ Mr. Bill Black of the
Fort Worth District Corps, we were able to obtain a11 of the
needed data.
Before we began the modeling procedure, we contacted Mr.
Matt Miller of FEMA and Mr. Mark Headly with FEMA's
technical consultant, Dewberry and Davis, to determine FEMA
requirements. We then completed a flood plain and floodway
model that matched Corps' data; both the present data and
the recently completed Corps' Environmental Impact Statement
(EIS). On May 6, we were ready to present this data to the
2212ARLINGTONDOWNSRD.,SUITE105 · ARLINGTON, TEXAS76011 · (817) 649-8110 · METRO 640-8101
Caffey and Morrison, Inc.
Elm Fork/Trinity River/Coppell, Tx.
Hay 10, 1986
Page -2-
Corps. However, as a last check to verify the data, we
contacted Mr. Bernard Massey of the United States Geological
Survey (USGS), Hr. Hassey told us of data that the USGS had
that indicated the flood stage elevations to be higher than
we had previously believed. This USGS data was based on a
measured gage height in the Flood of November, 19Bt. This
information sent us back to square one. ~e had to develop a
new model which corrected the previous data and correlated
with the results of the USGS gage.
This brings us to our present study. This study shows that
your property is subject to Flooding at an elevation
slightly above ~5 feet NGVD. However, the correct Floodway
delineation is outside the area of your proposed
development. This means that upon FEHA and City of Coppell
approval of this flood study, the area could be developed by
filling to an elevation above the lO0-year flood levels.
Even though the City of Coppell and FEHA may approve this
study, we do not recommend completion of any superstructure
work beyond filling until the Corps of Engineers Finishes
their Flood study. Their work should be speeded some since
we provided a copy of our results to them, coded on Floppy
disks that can interface with their computer systems.
The specific fill work required on your property would
require approximately 30,000 cubic yards of Fill to provide
two to three Feet elevation of the proposed structures above
the lO0-year Flood. Since Denton Creek is under the
backwater influence of the Elm Fork of the Trinity River,
any excavation work in Denton Creek would have no effect on
the lO0-year flood elevations in the area. ~e have had some
preliminary discussions with FEMA concerning this. Our
determination is that fill can be taken from Denton Creek
with no adverse impact on the tOO-year Frequency water
surface elevation.
Our only concern regarding the removal of fill material from
Denton Creek is that this action might involve a
determination by the Corps of Engineers under their ~04
permitting process. It is our understanding that they have
no Jurisdiction unless fill is being discharged into water
ways. This case involves only removal of material.
However, we don't know For sure if any wetlands exist on
your property. That determination must be made by the
Corps. ~e will contact them and obtain their determination
upon your authorization.
CaFFey and Morrison, Inc.
Elm Fork/Trinity River/Coppell, Tx.
May I0, 1986
Page -3-
We appreciate this opportunity to work with you on this
project and look forward to our continued association,
Sincerely,
Caffey and Morrison, Inc.
Ronald W. Morrison, P.E.
Vice President
TABLE OF CONTENTS PAGE NO,
A. Introduction ...........................................
A.1. Scope of Work
A,2, Data Assembly and Coordination
B. Hydrology .............................................. 7
C, Hydraulics ............................................. 8
C.I. Model Configuration
C,2. Cross Sections
0.3. Flood Delineations
C.~. Water Surface Profiles
C.5. Manning's Coefficient
C.6. Floodways and Encroachments
C.7, Structures
C.B. Velocities
D, Conclusions ............................................
Appendices
1. Flood Profiles from the City of Coppell FIS
2. FEMA Floodway Maps/City of Carrollton and Coppell and Corps
Worn Map
3, Comparison Flood Profiles for 1981 and Present Conditions
4. Flood Profiles for Present Conditions
5. Floodway Delineations for Comparison
6. Floodway/Flood Plain Delineations for Present Conditions
7. t981 Conditions Cross Sections
B. Present Conditions Cross Sections
9. USGS Gage Calibration HEC-2 Model
10, Baseline HEC-8 (1981 Conditions) Model
11, Present Conditions HEC-~ Flood Plain and Floodway Model
Reference Models Obtained from Fort North District Corps of
Engineers
A. Introduction
The Elm Fork of the Trinity River Flows From Lake Lewisville, a
Corps of Engineers discharge regulated reservoir, southward. It
Flows through Lewisville, Hebron, Carrollton, Coppell, Farmers
Branch and Dallas, Texas. It Finally joins with the West Fork
of the Trinity River in Dallas, Texas,
VICINITYMAP
~ 0 2 4 6 8 10 12 14 16
me. OF Mlbg~ -------- ,
i o 4 8 12 16 20
The area through this portion of the metroplex is experiencing an
unusually high growth rate. ProJects are projected in a number
of areas along this watershed.
In August of 1985, we were asked to evaluate the Flood plain and
Floodway along the Elm Fork of the Trinity at Sandy Lake Road.
At that time, the Corps of Engineers was under contract to the
Federal Emergency Management Agency (FEMA), completing a Special
Problem Report as part of the Lewisville Flood Insurance Study.
This project would define the Flood plain and Floodway through
the area. The Corps had been working on this project since )ate
1984. Our position at that time was to wait until the Corps
completed this study and define the area based on the Corps'
work. However, we waited nine months and saw no evidence that
the work was close to completion, Conversations with FEMA,
Region 6 and National clearly indicated that the project might
take another six months or more. We Felt that we had taken
reasonable steps to obtain an official study and must now proceed
on our own.
First, we contacted FEMA headquarters to determine their advice
on how to proceed. We were told that in order to obtain an
accurate study, we must determine all the projects that might
affect the study through our area. Our model should include
those 'that have been completed or will be completed shortiy.
Following this line of reasoning, we contacted the Cities
Coppeil and Carrollton in order to obtain this information.
These cities could not provide the data we needed, Me then
contacted the Corps of Engineers and they provided the data we
needed.
Using data on proJects that the Corps agrees should be
considered, we developed a Flood plain and Floodway through the
area. In order to benefit the Corps in their study and to
provide a consistent model, we started our model upstream
Beltline Road-in Dallas and carried the model through Interstate
Highway 35 in Leuisville.
We agreed to provide our model to the Fort Worth District Corps
in the form of 360 K floppy disks that will interface with their
IBM AT computers.
A.I. Scope o¢ Work
The purpoge o¢ thi9 study i9 to obtain conditional approval
of our Floodway determination in order to provide an area
available For development. The general area of our concern
is shown below.
The procedure followed is outlined below:
1, Obtain the models available for the area between
Beltline Road in Dallas and Interstate Highway 35 in
Lewisviile. These models include the Corps-
Engineers Flood Insurance Study, Albert H. Halff and
Associates model, two models by Nathan O. Maiers
Consultant Engineers and a model developed by Freeze
Nichols and Associates.
2. Develop a calibration model for conditions which
existed in 1981 in order to match the latest United
States Geological Survey (USGS) gage data for the flood
which occurred in that year.
3. Input lO0-year discharges into this calibration model
with necessary modifications to develop an appropriate
lO0-year frequency baseline model.
4. Input the changes made by the projects completed
through the area into the baseline model to obtain an
existing condition model.
5. Develop a floodway for this existing condition model.
This floodway matches the floodway alignment
established by the earlier flood insurance study model
everywhere except where the flood plain changes
sufficiently to make this floodway alignment
inappropriate,
A.2, Data Assembly and Coordination
This study involved a substantial effort in the area of
data assembly and coordination. The Corps of Engineers is
in the process of restudying this area under contract to
FEMA. This restudy was a result of the recalibration
the USGS gage at Sandy Lake Road. This recalibration was a
result of a flood that occurred in November of 198t.
Because of this new USGS data, the Corps and FEHA agreed
that the present FEHA base flood elevations through this
area are not correct, and they are probably wrong on the
nonconservative side. For this reason, we could not use
the FIS as a baseline model. The following is a short
chronology of our efforts at obtaining data:
Date Action
August 1985 Contracted with Vista Plex to determine
flood plain and floodway boundaries.
August 1985 Contacted the Fort Worth District Corps
Engineers to determine Elm Fork Trinity
(Lewisville FIS) study completion. They
advised their completion would be late
September.
3
October 1985 Contacted the Corps regarding completion
schedule of Elm Fork Trinity study.
They advised their completion would be late
December.
December 11/85 Contacted Matthew Miller, FEMA Project
Officer, regarding the Elm Fork study. Mr.
Hiller was not aware of any projected
completion dates for the Corps' Elm Fork
study. He suggested that FEMA would not
approve any floodway revisions on the
Trinity unless the model incorporates all
FEHA approved revisions and appropriate
conditional revisions. Ne also said that
the latest preliminary Corps discharges
should be used in the model.
December 13/85 Contacted Mr. Bill MayField, Nydraulics
Branch, Fort Morth District Corps, and
obtained latest Corps Elm Fork model,
January 1986 Contacted the Corps regarding completion of
Elm Fork study. They advised their
completion would be late February.
January 14/86 Contacted Hattheu Hiller, FEHA Project
Officer, regarding the Elm Fork study. Ne
had no information about completion dates.
Me discussed the requirements to obtain
FEHA approval of the study if we completed
it ourselves. He suggested the following
approach:
1, Obtain best Corps data regarding the
Elm Fork model.
2. Obtain copies of all revisions and
appropriate conditional revisions that
might affect the project,
3. Put together a model with all of these.
4. Submit the model through Coppell to
FEHA.
5, FEMA will review and issue comments,
If they are favorable, the results will
have to be compared to the Corps' study
when it comes out before Final map
revisions are made.
January 14/86 Contacted Mr. Mark Headly, Director of
Revisions for Dewberry and Davis, FEMA's
technical consultant. We wanted to know
how to obtain data submitted regarding
projects along Elm Fork Trinity, Mr.
Neadly said that we must contact Region 6
and request data. The process would
probably be lengthy. We also discussed the
requirements addressed by Mr. Miller. Mr,
Headly concurred with everything Mr. Miller
had said.
January 22/86 Met with Diane Leatherwood of FEMA Region 6
regarding revisions and conditional
revisions approved by FEMA. She provided
general information about projects
submitted to FEMA, but could not provide
any specific information regarding
hydraulic models.
March 3/86 Contacted Mr. Dell Greer, Director of
Natural and Technological Hazards Division,
regarding the Elm Fork study. He provided
general information. However, we were
unable to obtain any specific information
regarding status of the study or hydraulic
data.
March 26/86 Met with Mr. Bill Black of the Fort Worth
District Corps. Me received needed
information and direction (see copy of
letters at the end of this section).
April 3/86 Sent a letter to Mr. Matthew Miller, 'FEMA
Project Officer, explaining our approach
and asking for guidance if our approach was
not correct (see copy of letter at the end
of this section).
May 7/86 Met with North Texas Council of Governments
and the Fort Worth District Corps of
Engineers in a meeting about the Trinity
River Environmental Impact Study. Obtained
copies of the report to use as comparison
of our results.
May 13/86 Contacted Mr. Bernard Massey and Mr. Walter
Lear of the USGS regarding gage records at
the Sandy Lake gage. They confirmed gage
data and provided a copy of the gage rating
curve. Mr. Lear also said that USGS
observed that the weir at the Carroilton
dam ISandy Lake Roadl was flooded above
12000 ors and had no effect on the water
surface elevation at that discharge.
5
May 21/86 Presented the Elm Fork study results to Mr.
Bill Black, Fort ~orth District Corps. ~e
also provided all data on 360 K floppy
disks that would interface with the Corps'
IBM AT computers.
May 21/86 Appointment made with Mr. Ed Powell, City
Engineer, City of Coppell, Texas, to
explain our report and ask for their
review.
May 23/86 In anticipation of a favorable response
from the City of Coppeli, we sent final
copies of our Elm Fork study to FEMA Region
6, FEMA Headquarters, Corps of Engineers,
the United States Geological Survey and the
North Texas Council of Governments.
6
CAFFEY AND MORRISON, INC.
ENGINEERS -- HYDROLOGISTS
March 31, 1986
U.S. Army Corps of Engineers
Fort Worth District
Flood Plain Management Section
819 Taylor Street
Fort Worth, Texas 76102
Attn: Mr. Bill Black
Dear Mr. Black:
We are writing this letter to thank you for the help you
provided in obtaining data for the Elm Fork of the Trinity
River in the area shown on the attached map. We have been
asked to develop a flood plain and floodway model through
this area. As you are well aware, the Corps is in the
process of developing a flood insurance study (FIS) revision
that covers the area in question. Our objective in this
project is to develop a study that is as close to the final
Corps study as possible.
At our meeting of March 26, it was our intention to
determine the information which you are Using to develop the
Corps model of this area and to follow, as closely as
possible, your modeling procedure. To the best of our
knowledge, we have obtained a base model and all of the
projects that are to be included in the FIS to update that
base model to the current conditions. The updated model
will then match, as closely as possible, the final model
which the Corps will develop for the FIS.
The following is a listing of all the models to be
considered in this project. It should be noted that we are
only concerned with the Elm Fork of the Trinity River
between Beltline Road and Interstate Highway 35. We are
planning to develop a floodway model for an area just
upstream and downstream of Sandy Lake Road:
1. Corps of Engineers Preliminary Flood Insurance Study
Model for Lewisville, Texas. Title:
Executed 6 Feb. 84 7:41:51
DD Elm Gage Q's Low Flows (10 & 50 Yr.)
Elm Fork Between Lewisville Dam and R.M. 23
Elm Fork X Sections Survey Mar 1983 D.R. Gregory
2212 ARLINGTON DOWNS RD., SUITE 105 · ARLINGTON, TEXAS 76011 · (817) 649-8110 ' METRO 640-8101
Caffey and Morrison, Inc.
Elm Fork/Trinity River
March 31, 1986
Pa~e -2-
2. Corps of Engineers Elm Fork FIA Study. Title:
a. "ACOE Ft. Worth" Printer: 9
-D-Gregory 19 Aug. 85 11:23:38
Terminal: 73
Elm Fork FIA Study Natural Conditions
Sta 32.70 To Sta 342.60
X-Section Data: USGS Quads & Surveyed Chan & Valley
Sec
Levees Reflected On "D" Lines
See File EFlVS For Upstream Comps
File Created Jan. 77 -- Mayfield Revised 10-4-79
b. "ACOE Ft. Worth" Printer: 9
D-Gregory 19 Aug. 85 13:45:28
Terminal: 73
Elm Fork FIA Study Natural Conditions
Sta 966.70 To Sta 1090.00
X-Section Data: USGS Quads & Surveyed Chan Sections
This File Based On Revised USGS Gage Data
(Carrollton NP)
See File EF3VS For Downstream Comps
File Created 9/23/83 Mayfield Modified For Regional
EIS Jun. 7 85 D.R. Gregory
Discharges For 10, 50, 100 & 500 Yr. Freq.
c. "ACOE Ft. Worth" Printer: 9
D-Gregory 19 Aug. 85 11:24:42
Terminal: 73
Sections Added Or Modified For Regional EIS --
895.9, 905.3, 908.0, 911.3, 930, 937.8, 952.7,
966.2
See File EF2VS For Downstream Comps
See File EF4VS For Upstream Comps
File Created Jan. 77 -- Mayfield
Caffey and Morrison, Inc.
Elm Fork/Trinity River
March 31, 1986
Paqe -3-
3. FEMA Approved FIS Revision by Albert Halff and
Associates. Title:
a. 21 Jun. 85
Elm Fork Model Prepared By Albert H. Halff and
Associates, Inc. "ELMBLTR"RJ
From X-Sec 680.0 (COE) U.S. Of IH 635 To
Carrollton Dam (968.1) 06-85
Elm Fork Of Trinity River With IFCD Levee No
Floodway 10-Yr. Flood
b. 21 Jun. 85
Elm Fork Model Prepared By Albert H. Halff and
Associates, Inc. "ELMBLFWR"RJ
From X-Sec 680.0 (COE) U.S. Of IH 635 To
Carrollton Dam (968.1) 06-85
Elm Fork Of Trinity River With IFCD Levee No
Floodway 100-Yr. Flood
c. This model has not been approved by FEMA. However,
it was suggested that we incorporate the data.
18 Sep. 85
Elm Fork Model Prepared By Albert H. Halff and
Associates, Inc. "EMBLFWRR"RJ
From X-Sec 680.0 (COE) U.S. Of IH 635 To
Carrollton Dam (968.1) 09-85
Elm Fork Of Trinity River With IFCD Levee No
Floodway 100-Yr. Flood
4. Engineering Report to the Dallas County Commissioners
Court for the Proposed Creation of Dallas County Levee
Improvement District No. 18. October, 1984 by Nathan D.
Maier, Consulting Engineers, Inc.
5. Flood Plain Reclamation Study/Lakes of Coppell/Coppe!l,
Texas. Prepared for Triland Investment Group.
December, 1984 by Nathan D. Maier, Consulting Engineers,
Inc.
Caffey and Morrison, Inc.
Elm Fork/Trinity River
March 31, 1986
Page -4-
6. Flood Plain Reclamation Study/Keas Construction Tract/
Coppell and Carrollton, Texas. Prepared for Veenker
Investments, Inc. July, 1985 by Nathan D. Maier,
Consulting Engineers, Inc.
7. Flood Plain Study of Elm Fork, Trinity, at Interstate
Highway 35 by Freese and Nichols, Consulting Engineers.
The title of the run was:
Carrollton, Texas HUN85107 Hunter.Dat;2
100-Yr. Discharge Elm Fork - Trinity River
(109000 To 121540)
F & N Encroachment Run June 24, 1985 - MJD
The discharge values to be used in this final model will
conform to those shown on the attached table, which we have
obtained from the Corps.
Again, we wish to express our gratitude for the help we
received in piecing together this potential model. Without
the CorDs' help, it would be impossible to coordinate all
the considerations for this area.
If we have left out anything which needs to be considered,
or if any additional information becomes available, we would
appreciate it if you would let us know.
Sincerely,
Caffey and Morrison, Inc.
Ronald W. Morrison, P.E.
Vice President
cc: David Heth
CAFFEY AND MORRISON, INC.
"',.1 '~'-,-
13ENERRL LOCRTION i~RP
I
+~
,~-~;~ ~' TABLE 5 (CONT' D)
%~ /~US~E~T Ta . 1 ..... .~'-.:~
Co~D E~OB~ILI~ DISC~GE 0PT~0N ~ "
I~ L0~TION . ' DA-SQ.~ 10 ~ 50 ~ I00 ~ 500 ~
10~ ~0U~ T~ BA~ ~ - 11.59 ~1169. i718~. 20208. 25363. 34150.
S~TING E~. 438.1 FT ~L
103 ~0U~ FROM BAC~ ~ D~ 12.59 ~575. 6897. 8163. ll0~A. 14379.
TO E~ F0~ C0~.
NO~: ~ FO~O~NG ~ ~OP~ DISHES FO~ ~ I~IC~ POI~ 0F I~ST 0N
~ (1) ELH FO~ D. A. BE~ %.Z7 6300.* 9000.* 21000.* 55000.* 62000.*
D~
3 g~ ~0~ BELOW C0~. ~ 7.82 6300.* 9000.* 21000.* 55000.* 62000.*
8 E~H FO~ BEL~ CO~. ~ ' 13.00 7125. 1~300. 21000.* 53000.* 62000.*
S~T C~ (S.H. 121)
13 E~ FO~ B~0W ~ B~ 17.09 6300.* 9000.* 2!~00.* 55000.* 62000.*
C0~.
2Z E~H FO~ B~OW CO~. ~ 36.25 142'02. 20469. 23507. 55000.* 62000.*
26 E~H FO~ ~0~ IH 35 g ~1.50 ~I335. 16055. 21000.* 55000.* 62000.*
33 E~ PO~ B~OW T~ER C~. 66.67 20575. 29687. 3~522. 55000.* 62606.
CO~ (AT IH 35 E
CROSSI~G)
~4 E~H FO~ B~OW C~OLLTON !04.00 2~317. 37075. ~A359. 60394. 84185.
50 E~H FO~ BELO~ H~ON B~CH 118.9~ 23~65. 35916. 42893. 59155, 82321.
~0~ ·
54 E~M FO~ BELOW G~I~ ~32.17 23288. 36571. a4~86. 62061. 861S5.
EXCEED LOC~ FLOWS.
.. ,..:,.~ TABLE, 5 (CONT'D)
'y ' F..'~CU'~D oN 2.5 0C% 85 A~ ~'L:40:14
L EWI SV ILLE
FLOOD INSUP. ANCE STUDY
EL~H FOB~ TKINZT~ KIVEK
LE%TISVILLE FLOOD INSUEANCo- SI~DI
Co~D pKOB~ZLI~ DISC~E OPTION 1
I~ LOCATION DA-SQ.~ 10 ~ 50 ~ 10O ~ ~00 ~ S~F
65 E~H FO~ BELOW CO0~ B~ ~9.08 ~.~3080. 36924. 4~625. 62675. 86760.
' 63716 · 8803~.
80 E~ FO~ ~EL0W F~ S~ 158.06 ~3056. 37382. ~5292.
88 E~ FO~ BELOW ~S~2 ~- ~78.52 2Z123. 36821. 453a9. 66~85. 92754.
CO~ ·
97 ~ EO~ BELOW JOES ~ ~00.78 20253. 34174. 42665. 62076. 87822-
CO~
104 E~O~ BELO~ BA~ B~ 214.93 19867. 34362. 43216. 63477. 897~1-
107 ~OU~ ~0~ E~H FO~ AT 220.00 - 19497. 33838. 42678. 63039- 89367 ·
CM,, INC.
ENGINEERS -- HYDROLOGISTS
April 3, 1986
Mr. Matt Miller
Federal Emergency Management Agency
Federal Insurance Administration
Office of Risk Management
Risk Studies Division
500 C. Street $.W.
Washington, D.C. 20472
Re: FEMA Map Revision for Tract of Land in Coppell, Texas
Adjacent Denton Creek/Job No. 85048
Dear Mr. Miller:
We have been asked to develop a flood plain and floodway
model through the subject property (see attached map). The
Fort Worth District Corps of Engineers is in the process of
developing a flood insurance study (FIS) update of this
area. Our objective in this project is to develop a study
that is as close to the final Corps study as possible.
On March 26, 1986, we met with Mr. Bill Black of the Fort
Worth District Corps Flood Plain Management Services Branch.
At that meeting, it was our intention to determine the
information which was being used to develop the Corps model
of this area and to follow, as closely as possible, the
Corps' modeling procedure. To the best of our knowledge, we
have obtained a base model and all of the projects that are
to be included in the FIS to update that base model to the
current conditions. The updated model will then match, as
closely as possible, the final model which the Corps will
develop for the FIS.
The following is a listing of all the models to be
considered in ~his project. It should be noted that we are
only concerned with the Elm Fork of the Trini=y River
between Beltline Road and Interstate Highway 35. We are
planning to develop a floodway model for an area just
upstream and downstream of Sandy Lake Road:
1. Corps of Engineers Preliminary Flood Insurance Study
Model for Lewisville, Texas. Title:
Executed 6 Feb. 84 7:41:51
DD Elm Gage Q's Low Flows (10 & 50 Yr.)
Elm Fork Between Lewisville Dam and R.M. 23
Elm Fork X Sections Survey Mar 1983 D.R. Gregory
2212 ARLINGTON DOWNS RD., SUITE 105 · ARLINGTON, TEXAS 76011 · (817) 649-8110 · METRO 640-8101
Caffey and Morrison, Inc.
Land Adjacent Denton Creek, Coppell, Texas
April 3, 1986
Page -2-
2. Corps of Engineers Elm Fork FIA Study. Title:
a. "ACOE Ft. Worth" Printer: 9
D-Gregory 19 Aug. 85 11:23:38
Terminal: 73
Elm Fork FIA Study Natural Conditions
Sta 32.70 To Sta 342.60
X-Section Data: USGS Quads & Surveyed Chan & Valley
Sec
Levees Reflected On "D" Lines
See File EF1VS For Upstream Comps
File Created Jan. 77 -- Mayfield Revised 10-4-79
b. "ACOE Ft. Worth" Printer: 9
D-Gregory 19 Aug. 85 13:45:28
Terminal: 73
Elm Fork FIA Study Natural Conditions
Sta 966.70 To Sta 1090.00
X-Section Data: USGS Quads & Surveyed Chan Sections
This File Based On Revised USGS Gage Data
(Carrollton NP)
See File EF3VS For Downstream Comps
File Created 9/23/83 Mayfie!d Modified For Regional
EIS Jun. 7 85 D.R. Gregory
Discharges For 10, 50, 100 & 500 Yr. Freq.
c. "ACOE Ft. Worth" Printer: 9
D-Gregory 19 Aug. 85 11:24:42
Terminal: 73
Sections Added Or Modified For Regional EIS --
895.9, 905.3, 908.0, 911.3, 930, 937.8, 952.7,
966.2
See File EF2VS For Downstream Comps
See File EF4VS For Upstream Comps
File Created Jan. 77 -- Mayfield
Caffey and Morrison, Inc.
'Land Adjacent Denton Creek, Coppell, Texas
April 3, 1986
Page -3-
3. FEMA Approved FIS Revision by Albert Halff and
Associates. Title:
a. 21 Jun. 85
Elm Fork Model Prepared By Albert H. Halff and
Associates, Inc. "ELMBLTR"RJ
From X-Sec 680.0 (COE) U.S. Of IH 635 To
Carrollton Dam (968.1) 06-85
Elm Fork Of Trinity River With IFCD Levee No
Floodway 10-Yr. Flood
b. 21 Jun. 85
Elm Fork Model Prepared By Albert H. Halff and
Associates, Inc. "ELMBLFWR"RJ
From X-Sec 680.0 (COE) U.S. Of IH 635 To
Carrollton Dam (968.1) 06-85
Elm Fork Of Trinity River With IFCD Levee No
Floodway 100-Yr. Flood
c. This model has not been approved by FEMA. However,
it was suggested that we incorporate the data.
18 Sep. 85
Elm Fork Model Prepared By Albert H. Halff and
Associates, Inc. "EMBLFWRR"RJ
From X-Sec 680.0 (COE) U.S. Of IH 635 To
Carrollton Dam (968.1) 09-85
Elm Fork Of Trinity River With IFCD Levee No
Floodway 100-Yr. Flood
4. Engineering Report to the Dallas County Commissioners
Court for the Proposed Creation of Dallas County Levee
Improvement District No. 18. October, 1984 by Nathan D.
Maier, Consulting Engineers, Inc.
5. Flood Plain Reclamation Study/Lakes of Coppell/CoDDell,
Texas. Prepared for Triland Investment Group.
December, 1984 by Nathan D. Maier, Consulting Engineers,
Inc.
Caffey and Morrison, Inc.
Land Adjacent Denton Creek, Coppel!, Texas
April 3, 1986
Page -4-
6. Flood Plain Reclamation Study/Keas Construction Tract/
Coppell and Carrollton, Texas. Prepared for Veenker
Investments, Inc. July, 1985 by Nathan D. Maier,
Consulting Engineers, Inc.
7. Flood Plain Study of Elm Fork, Trinity, at Interstate
Highway 35 by Freese and Nichols, Consulting Engineers.
The title of the run was:
Carrollton, Texas HUN85107 Hunter. Dar; 2
100-Yr. Discharge Elm Fork - Trinity River
(109000 To 121540)
F & N Encroachment Run June 24, 1985 - MJD
The discharge values to be used in this final model will
conform to those shown on the attached table, which we have
obtained from the Corps.
Our purpose in sending this information to FEMA is to
request that any information or assumptions which we have
made that are incorrect or need to be modified, be corrected
early in the game. If any modifications are needed, please
call me at telephone (817) 640-8101 as early as possible.
Your help is greatly appreciated. We will also provide a
copy of our work to the Corps on floppy disk in case they
want to use it in their FIS determination.
Sincerely,
~rrison, Inc.
Ronald W. Morrison, P.E.
Vice President
cc: Mr. R. Dell Greer, Chief
Natural and Technological Hazards Division
Federal Emergency Management Agency, Region VI
800 N. Loop 288, Federal Center
Denton, Texas 76201-3698
Attn: Bert Carr
Mr. David Heth
CAFFEY AND MORRISON, INC.
\
GENERRL LOCRTION
COL~UTED PROBAI~ILIT~ DISCRAI%Gll; OPTION 1. ....
IND~'Y LOCATION . ' DA-iQ.HI 10 TEA~ 50 YEAR I00 ~ 500 TEA~ .S~F
102 ~ T~ BA~ ~ - 12.59 ~1169. 17184. 20208. 25363. 34150.
S~=!NG E~. t38.1 YT ~L
TO E~H FO~ ¢0~.
1 (1) ~ FO~ D. A. BE~ 1.17 6300.* 9000.* ~I000.* 55000.* 62000.*
D~
3 l~ FO~ B~ CO~. ~ 7.82 6300.* 9000.* 21000.* 55000.* 62000.*
8 E~H FO~ B~ CO~. ~ ' 13.00 7~5. l~]O0. 11000.* 55000.* ' 61000.*
13 ~H FO~ B~O~ ~ B~ ~7.0g 6300.* g000.* 2!~00.* 55000.* 62000.*
~1 ELH ~0~ S~0~ CO~. ~ 36.~6 14Z'O~. Z0469. 23507. 55000.* ~1000.*
Z6 E~ FO~ ~O~ IH 35 E &[.50 [~35. ~6055. 21a00.* 55000.*
33 ~H EO~ S~O~ T~E~ Cl. 66.67 20575. 29687. 345Z/. 55000.*
CO~ (AT ~H 35 E
44 ~H FO~ B~O~ C~O~TON 104.00 24317. 37075. 44359. 60394. 84185.
)0 E~ F0~[ B~0W E~OH B~CH 118.94 23165. 35916. 42893. 59155. 82321.
54 E~H FO~ BELO~ G~ 132.L7 23288. 36571. 44L86. 6206~. 86~85.
*DISC~CE - F~q~llCf ~L~ES FROM g~E LE'~ILLE CONS~E~D 'C~TZC,~ FLO'JS' ~ THeY
RICED LOC~ FLOWS*
LE~rls~ILL~ FLOOD INSUI~/~ STUDI
~ LO~O~ DA-SQ.~ 10 ~ 50 ~ 100 ~ 500
65 E~ FO~ B~OW CO0~ B~ L39.08 · 23080- 36924. 446Z5. 62675. 86760.
co~. ' :ii'::; ;;> '
O~
~ 63716
80 ~ ~0~ B~ ?~ S~ L58.06 ~3056. 37382. 45292.
GO~. '.
88 E~ FO~ B~ ~~ ~' 178.52 22123. 36821. ~53&9. 66~85. 9275~.
97 ~ ~O~ B~W JOES ~ 200.78 20~3. 3417t. ~2665. 62076. 87822.
10a ~'FO~ BELOW B~ B~ 2L~.93 19867. 3~362. 43116- 63~77. 8971L.
~07 ~0~ ~H E~ FO~ ~ ilO.00 ~.L9~97. 33838. il678. 63039. 89367.
~0~
B. Hydrology
All discharge values used in this report for the tOO-year
frequency were obtained from the Fort Worth District Corps of
Engineers and represent the latest information available to date.
A copy of the discharge values is shown on the following page.
In addition to these discharge values presented by the Corps, we
also obtained discharge values used in the current Draft
Environmental Impact Statement (see following pages). These
values compare favorably with those presented earlier by the
Corps.
In order to match the USGS gage station at Sandy Lake Road, we
obtained the 198t discharge value of 21100 cfs at a recorded gage
height (plus datum) of ~4~ feet NGMD. We also obtained the' mean
annual flow for the 1981 water year of 4300 cfs, This was used
to determine the normal flow elevation.
f ''[iL "' ""
L~~ ~OOD ~SU~ S~O~ ..-
CO~D PROB~L~ DISC~GE OPTION I ' "
~ LO~TION. DA-MQ.~ 10 ~ 50 ~ I00 ~ 500 ~ .S2F
102 ~OU~ ~U BA~ ~ - 12.59 11169. 17184. 20Z08. 25363. 3~150.
103 RO~ FROM BAC~ ~ D~ 12.59 4575. 6897. 8163. 11044. 14379.
[O~: ~ FO~O~M~ ~ ~O~ DISHES FOR ~ %~%~D POI~ OF I~ST ON ~ E~M FO~
% (1) Z~ YO~ D. A. Bg~N 1.27 6300.* 9000.* Zl000.* 55000.* 62000.*
D~
3 ~ FO~ B~OW CO~. ~ 7.82 $300.* 9000.* 21000.* 55000.* 62000.*
13 E~ ~O~ BELOW ~ B~ 17.09 6300.* 9000.* zl6oo.* 55000.* 62000.*
co~ ·
zl E~M FO~ B~OW CO~. ~ 36.26 142'0~. 20469, 23507. 55000.* 62000.*
2~ E~M FO~ ~0~ IE 35 E ~1.50 11335, 16055. 21000.* 55000.* 62000.*
33 E~M FO~ B~OW TL~E~ C~. 66.67 20~75. 29687. 34~2~. 55000.* 62606.
CO~ (AT IE 35 E
CROSSZMG)
44 E~M F0~ B~0W C~0LLTON 104.00 243~7. 37075. 44359. 60394.
50 g~ FO~ B~OW EU~N B~CE 118.94 23165. 35916. &2893. 5915~. 82321.
C0~ ·
54 E~ FO~ BELOW G~I~ !32.~7 23288. 36571. 44186. 6206~.
· DISC~GZ - F~Q~ICf ~LZASES FROM L~E LE~!LLE CO:[SIDE~D "C~ITIC2~ FLCWS' '~E~ TF~Y
EMCEED LOC~ FLOWS.
E.XiI~UTED ON Z~ OCT 8§ AT 1!:40:i~
LEW"I fig' ILLE
FLOOD I~N-~URANCE $~DY
ET.H FOF, K TtI.-"tlT'~ 11~1
LEWIMVILLE FLOOD INSURANCE STUDY
I~ LO~TION DA-SQ.~ 10 ~ 50 ~ 100 ~ 500 ~ S2F
65 E~ FO~ BELOW COO~ B~ : i39.08 ~ 23080. 3692~. 44625. 62675. 86760.
CO~. '~ .'~:- i~,'. ·
75 EUM Y0= B~OW ~ A SLUICE "';:~i43-~g::::f'~'~1661 37381. 45077. 63089. 86889.
80 E~ EO~ S~OW F~ S~ 158.06 ~056. 37382. 45292. 63715. 88032.
88 ~ ~0~ S[LOW ~~ ~- ~78.5Z 22~. 3682~. ~53~9. 66485. 9275~-
CO~ · - -.
g7 [~ EO~ B~OW JO~S C~ 200.78 20253. 34~74. 42665. 62076. 87822.
C0~
~04 S~'?O~ ~ZLOW BA~ S~ 2~.93 ~9867. 34362. 432~6. 63~77. 897~.
~07 ~0~ ~OM ~ ~0~ A~ 2~0.00~.~9~97. 33838. ~678. 63039. 89367.
' IJ~ TABLE OF CONTENTS
HYDROLOGY AND HYDRAULICS
HYDROLOGY APPENDIX
~'] TRINITY RI~R REGIONAL ElS
I X~ I. Hydrologic Analysis
~ A. Scope of Work - Purpose and Goals
B. Drainage Area
C. Geosraphical Limits of Channel Modification
D. Model Development'
1. Callbrated Model
'"~ 2. Hypothetical Precipitation
~, ~ a.~ Precipitation Source
b. Precipitation Duration
c. Precipitation Distribution
d. Time to Peak
3.Precipitation Losses
4Urbanization Estimates
g. Scenarios Investigated
] A-1 Sub-Area Division of Drainage Area
A-2 Urbanization Curves
4 A-3 Urbanization Cu~es
APPENDIX A - HYDROLOGY AND HYDRAULICS
I. Hydrologic Analysis
A. Scope of Work - Purpose and Goals
The purpose of the Hydrology portion of the Trinity River Regional
Environmental Impact Study (EIS) was to evaluate the magnitude of
flows in the Trinity River above its confluence with Five Mile Creek
and portions of two of its major tributaries, the West Fork and the
Elm Fork. Ultimate general watershed urbanization and alternative
flood, plain development and channelizatlon options were considered.
B. Drainage Area
The area modeled in this study consisted of the entire drainage area
of the Trinity River upstream of the point where Five Mile Creek flows
/
into the Trinity River near the intersection of the Trinity River and
Interstate Highway 20 (about 10 miles southeast of downtown-Dallas).
The total drainage area at that point of the Trinity River is'
approximately 6275 square miles. The total drainage area of the
Trinity River above the Dallas gage is 6106 square miles and at the
Confluence of the Elm Fork and the West Fork is 6061 square miles.
The terrain elevation varies from 1200 feet NGVD at the headwaters of
the West Fork of the Trinity River approximately 35 miles
south-southwest of Wichita Falls, Texas to 380 feet NGVD at the
confluence of Five Mile Creek and the Trinity River.
The Trinity River Watershed as described above is located in a region
of temperate mean climatological conditions, experiencing occasional
extremes of temperature and rainfall of relatively short duration.
The National Oceanic and Atmospheric Administration Station at Fort
Worth, Texas shows an average annual rainfall of 32.3 inches during a
recent ten year period. The extreme annual rainfall values since 1887
are a maximum of 51.03 inches occurring in 1932 and a mimimum of 17.91
inches occurring in 1921. The mean relative humidity is 65 percent
and the average temperature is 65.8 degrees.
Generally the major storms experienced in the Trinity River Watershed
above the Five Mile Creek confluence are produced by heavy rainfall
from frontal-type storms which occur in the spring and summer months,
but major flooding can also. be produced by intense rainfall associated
with localized thunderstorms. These thunderstorms may occur at any
time during, the year but are more prevalent in spring and summer
months.
C. Geographical Limits of Channel Modification
The study area of interest extends from the downstream end of the
proposed Dallas Floodway Extension (approx. the confluence of Five
Mile Creek and the Trinity River) upstream on the West Fork of the
Trinity River to Riverside Drive in Fort Worth, and upstream on the
Elm Fork of the Trinity River to Lewisville and Grapevine Lakes. The
river channel between these geographical locations was conceptually
modified to reflect the conditions of each scenario to be evaluated.
D. Model Development
The area modeled was divided into 108 sub-areas in order to be
responsive to the timing of each major tributary's runoff contribution
and also to obtain detailed flow information (flood hydrographs) at
all major points of interest on the West Fork, Elm Fork, and. the
Dallas Floodway and Floodway Extension of the Trinity River. Figure
A-1 shows the sub-area arrangement. The computer program used to
develop the hydrologic model for this study was the HEC-1 Program
723-X6-L2010 developed by the Corps of Engineers' Hydrologic
Engineering Center at Davis, California. This HEC-1 model is designed
to simulate the surface runoff response of a river basin to
precipitation by representing the basin as an interconnected system of
hydrologic and hydraulic components.
1. Calibrated Model
The hydrologic model was first developed for calibration purposes to
reflect the.1985 urbanized conditions of the drainage area without Ray
Roberts and Joe Pool Lakes. The model was calibrated by adjusting
hydrologic parameters such as "time to peak" and "precipitation loss
rates" within reasonable limits in order to match as closely as
possible the peak values of five different frequency-floods at several
streamflow gaging stations. The values of the peak flows of
frequency-floods at any particular gage was determined by performing a
frequency-flow analysis from the record of flows at that gage. The
time period covered by the gage record of flows was selected to start
in 1953, since all major reservoirs were in place by 1952, and to
continue to the latest published flow. This allowed the recorded
flows to generally reflect watershed conditions as they were in 1985.
The only reservoirs that were activated after 1952 were Lake Arlington
in 1957, Lake Amon Carter in 1956, and Lake Weatherford in 1957. Ail
three are small structures with no flood control storage and have a
minor influence on the flow gages downstream. Streamflow gages in the
study area are shown in Figure A-1. As can be seen from Figure A-I,
two stream flow gages were deactivated by the establishment of Ray
Roberts and Joe Pool Lakes were considered existing
Roberts
Lake.
Ray
for 1985 and ultimate development EIS scenario evaluations.
2. Hypothetical Precipitation
ao Precipitation Source
The hypothetical precipitation for each frequency-flood was developed
using data from National Weather Service Technical Paper 40 (TP40),
National Oceanic and Atmospheric Administration Technical Memorandum
NWS Hydro-35, and Corps of Engineers Civil Engineer Bulletin No. 52-8
("Standard Project Flood Determination"). Figure 15 of TP40,
depth-area-duration curves, was used to adjust the rainfall for
watershed size.
b. Precipitation Duration
A 24 hour storm duration was useH for the frequency storms (10 year,
25 year, 50 year, and 100 year storms). The duration of the Standard
Project Storm was adopted as 96 hours.
c. Precipitation Distribution
The rate (or intensity) of precipitation for all storms was assumed to
remain constant throughout any one-hour time interval although it
changes from one time interval to another.
The rate (or intensity) of precipitation for the frequency storms (10
year through 100 year) was assumed to be evenly distributed over the
entire drainage area, but the rate of precipitation for the Standard
Project Storm was assumed to be distributed according to an elliptical
pattern where the rate of precipitation is inversely porportional to
the distance from the elliptical center. Only one elliptical storm
center, which was the estimated critical center for the Dallas gage,
was evaluated. Figure A-1 shows the elliptical pattern.
d. Time to Peak
Time .to peak was developed for each sub-area using methodology
described in "Synthetic Hydrograph Relationships, Trinity River
Tributaries, Fort Worth - Dallas Urban Area" by T. L. Nelson, 1970.
An urbanization curve indicates elapsed time (time to peak) from the
midpoint of a unit duration of rainfall to maximum runoff for a given
sub-area. The geographical characteristics of the sub-area such as
length of major stream (L), the location of the center of gravity
(Lca), percent urbanization, and the overall slope (S) of the major
stream determine the entering arguments for the urbanization curve
from which "time-to-peak" for the sub-area is extracted. The
"time-to-peak" used for each sub-area was generated from the Fort
Worth-Dallas East-West Cross Timbers Curve and Blackland Curve by
interpolating between them, based on the percentage of each soil type
within the sub-area. The percentage of soil type was derived from a
Soil Survey report for each county published by the U.S. Department of
Agriculture. The East-West Cross Timbers and the Blackland
Urbanization Curves are shown in Figures A-2 and A-3.
3. Precipitation Losses
The block loss method of estimating precipitation losses was used in
this study. Two different loss rates were used: (1) the initial loss
which must be satisfied before any runoff occurs and (2) a constant
loss in inches-per-hour which continues after the initial loss has
been satisfied. The values of both losses vary with the return.
frequency of the storm. The standard values of both loss rates were
initially used in the computer model. Comparisons were made between
"frequency analyses peak flows" at the major stream gages in the area
and the "model computed value of peak flow" at the same gages.
Adjustments were made to the loss rates to improve the comparisons of
peak flows at the gages. The adjusted values were used in this study.
This was the method of calibrating the model to produce results that
agreed with peak flow values determined from gage frequency analyses.
4. Urbanization Estimates
Estimates of the amount of urbanization for each sub-area in this study
for 1985 Existing Conditions were made by referring to the most recent~
maps and charts available.
In an effort to be as accurate as possible in estimating "percent
urbanization" expected to exist as ultimate development (Future
Conditions), a request was made by the Corps of Engineers, through the
North Central Texas Council of Governments, for information from the'
major cities in and around the Metroplex as to their projected future
growth rates. Thirty-two cities responded to the request for future
growth estimates in some fashion, and that information was considered
in the estimate of ultimate urbanization percentage ior each sub-area
in the computer model. These urbanization estimates for ultimate
development were used to evaluate all scenarios except the 1985
Existing Conditions scenario.
E. Scenarios Investigated
Ray Roberts and Joe Pool Lakes were considered in Place for 1985 and
ultimate development conditions. Comparative discharge-frequency data
were developed for "Future Without" considering ultimate Watershed
urbanization with storage-discharge data based on 1985 river channel
conditions.
Modified storage-discharge data for routing reaches for other
scenarios and channel and overbank assumptions were. developed based on
backwater computations. These modified storage-discharge data were
input to the data file for the HEC-1 hydrology model and new
discharge-frequency data were computed. Assumptions involved with
each scenario are described in the Hydraulic Analysis portion of this
Appendix. Computed frequency discharges are presented in Tables A-1
to A-21.
F. Application of Results
Frequency discharges generated for this study are comparative (for
comparing impacts of various alternatives) and are not always critical
for each discharge location. The storm center for the standard
project storm and the rainfall area-reduction factors for frequency
storms for this study have been set up to generate critical discharges
for the Trinity River Dallas Floodway. Discharges generated for the
West Fork Trinity River do not supersede the existing Flood Insurance
Studies (FIS) for the West Fork. However, the new HEC-1 one-hour
model does consider storage-discharge changes which have occurred due
to recent projects along the West Fork. If the new HEC-1 model were
used with critical centering and area reduction factors for storms
along the the West Fork, critical frequency discharges could be
generated for an updated FIS. Adopted discharges for the Elm'Fork
were .developed using the NUDALLAS computer program. Reductions in
loss rates (increases in runoff volume) due to increased future
imperviousness were considered in the NUDALLAS analysis. The Elm Fork
discharges are based on critical storm centerings and the peak flows
for existing conditions will be utilized for new Flood Insurance
Studies.
storms for this s~udy have been set up to generate critical discharges
for the Trinity River Dallas Floodway. Discharges generated for the
West Fork Trinity River do no~ supersede the existing Flood Insurance
Studies (FIS) for the Wes~ Fork. However, the new HEC-1 one-hour
model does consider storage-discharge changes which have occurred due
to recent projects along the West Fork. Adopted discharges for the
Elm Fork were developed using the NUDALLAS computer program.
Reductions in loss rates (increases in runoff volume) due ~o increased
future imperviousness were considered in the NUDALLA$ analysis. The
Elm Eork discharges are based on critical storm centerings and the
peak flows for existing conditions will be utilized for new Flood
Insurance Studies.
TABLE A-24
EXISTING CI)NDITIONS DISCHARf~S (cfs)
Station (ft) Station (ft) 10-Yr,, 25-Y~ 50-Y~ 100-Yr SP~
0000* - 3750 19500 26000 33800 42700 89400
3750 - 6850 19500 26600 33800 42700 89400
6850 - 18450 19900 27000 34400 43200 89700
18450 - 34210 20300 27100 34200 42700 87800
34210 - 48700 21000 28000 35000 43500 90000
48700 - 55300 22160 29400 36800 45300 92800
55300 - 67800 23100 30400 37400 45300 88000
67800 - 71150 23200 30500 37400 45100
86900
71150 - 76000 23100 30400 36900 44600 86800
44200 86200
76000 - 86430 23300 30200 36600
86430 - 91130 23200 __
30000
35900
429OO
8230O
~ 91130 - 96620 ~300 31300 37100 44400' 84200
~96620 109000 23000 28000 35000 41000 79000
109000 - 113720 20600 25400 29700 34500 62600
113720 - 116050 11300 13800 16100 21000 62000
116050 - 141000 14200 17600 20500 23500 62000
141000 - 150350 6300 6300 9000 21000 62000
*West Fork/Elm Fork confluence
C. Hydraulics
This study was the most difficult we have encountered to date.
The hydraulics were very complicated and to make matters worse,
the USGS gage data didn't seem to match with the data developed
by the Corps. It was not until we had spent considerable hours
correlating runs that we began to get a clear picture of what was
happening with the hydraulics. We will present a detailed
analysis of our model in the paragraphs that follow,
In order to further evaluate our model, we also reviewed the
results of the Corps' recently released Draft Environmental
Impact Statement (see sheets at the end of this section). Our
final elevations were slightly higher than the results of the
Corps' EIS study,
For example, at Sandy Lake Road the following comparison is made
for the existing condition:
Corps lO0-year Frequency CafFey & Morrison tOO-year
elevation, ft., NGVD frequency elevation, ft., NGVD
4~3.1 444.73
This variation will be discussed in later paragraphs.
0.1. Model Configuration
The HEC-2 computer model was used for this study. The
version used was a release dated November, 1976, updated
May, 1984. Three models were developed for this study.
They were:
1. Calibration model (ELMF.NV). This model matched 1981
condition5 using the discharge value measured in
November of 1981 by the USGS at the Sandy Lake Road
gage station.
2. Mean daily Flow determination (ELMF.NV). This model
was used to determine the elevation of the normal Flow
line. A smoother channel was assumed below elevations
determined in this model. This will be discussed
later.
3. Baseline model (ELMFIOO.EXT). This model matched 19BI
conditions using lO0-year Frequency discharges
developed by the Corps. It represents conditions that
existed before revisions were made and most nearly
approximates FIS conditions if they had been corrected
with the USGS gage data of 1981. The purpose of this
model was to determine the effect of the many changes
to the Elm Fork through the area of our study.
B
4. Improved model (ELMFIOi.IMP). This model is the
existing conditions model, It includes all of the
floodway revisions and appropriate conditional
revisions. We considered "appropriate conditional
revisions" as those which Mr. Bill Black considers
appropriate in his development of the Elm Fork Flood
Insurance Study.
0,2, Cross Sections
Appendix 7 shows the cross sections as they existed in
1981. We attempted to create 1981 conditions by removing
all post 1981 development which affects our project from
these cross sections. We have also plotted the calibration
elevation on the cross sections to demonstrate the shallow
overbank conditions which will be discussed later.
Appendix 8 shows existing condition cross sections. This
represents conditions as they exist with all of the
floodway revisions and appropriate conditional revisions in
place.
0.3. Flood Delineations
Appendix 2 is a copy of the FIS delineation from the Corps'
work map. We have also included copies of applicable
sections of the Carrollton and Coppeil FIS floodway maps.
In order to show the floodway changes, we have included in
Appendix 5, a map which shows the FIS floodway as it
appears on the original FIS maps. Aisc shown are the
floodway changes approved by FEMA by final revision or
conditional revision. We have also delineated a floodway
change at Sandy Lake Road which ue feel is the most
technically accurate floodway through this area.
Finally, we have included in Appendix 6, a flood plain and
floodway delineation that incorporates all of the changes
and represents present conditions.
C.4. Water Surface Profiles
Appendix 1 contains water surface profiles from the
Coppell Flood Insurance Study. These are no longer
appropriate mince the gage at Sandy Lake Road has made
recalibration necessary. They are included for information
and comparison.
9
Me have also included, in Appendix 3, water surface
profiles which show a comparison between 1981 conditions
connected to reflect the Sandy Lake gage and the existing
conditions which include all revisions and conditional
revisions. This profile shows that water surface
elevations below the Sandy Lake gage have increased since
1981 while the elevations at and above the gage are
approximately the same.
Finally, in Appendix 4, we have drawn the present condition
water surface profile for the lO0-year frequency flood.
In order to demonstrate the changes, we have included the
following table.
]O0-YEAR FREQUENCY MATER SURFACE ELEVATIONS
198l Conditions
Considering 1981 Present
Cross Section Coppell FIS* USGS Gage Record Conditions
930 440.9 440.66 440,66
937.8 441,2 441,93 442,19.
950,97 441.~ 442.84 443.09
952.7 441.5 442,95 443.22
966.2 443 444,72 444,76
988,7 443,7 444,77 444,81
967,6 444,1 444,72 444,73
968,1 444,3 445,12 q45.14
1006 445,5 446,28 446,30
1014 446,7 446,45 446,47
1022 445,9 446,87 446,68
1030,2 446,2 446,87 448,88
1090 448,5 448.88 448,86
Measured from flood profiles
10
C.5. Hanning's Ooefficient
The roughness coefficients used in this model hold the key
to describing the hydraulic conditions that exist. Our
first attempt at this model considered roughness values as
they were developed in the Flood Insurance Study and in all
the subsequent revisions since then. We used these values
directly from cup usual source, "Open Channel Hydraulics"
by Ven Te Chow. However, we were unable to match the gage
records at the Sandy Lake gage. We were considerably low
even though we were using the same discharge value measured
at the gage in November o¢ 198] (see following page for
gage record). This was perplexing until ue looked closely
at the cross sections with the gage discharge plotted. The
example cross section below points out a typical situation:
CROSS SECTZON 950.97
EL~4 FORK 'TR];NTY RZVER
DALLAS COUNTY
460
450 '~
44O
430 I I
420 ,
800 o~n~ 3800 5300 6800 8300 9800 11300 12800 14300
BZSTANCE. FEET
11
400 TRINITY RIVER BASlN
08055500 EI.H FORK TRINITY RIVER NF. AR CARROLLTON, TX
LOCATION.--Let 32°57'57'', long 96'56'39", Dallas County, Hydrologic Unit 12030103, near left bank at do~natrea~ side
of bridge on Sandy Lake Road, 40 ft (12 m) upstream from Ca~ollton D~m, 0.3 mi (0.5 ks) do~nstrenm.from Denton
Creek. 1.0 mi (1.6 ks) upstream from .et. Louis Southwestern Railway 1.tnes bridge. 2.3 mi (3.7 k~) northwest of
Cat-rollton, and 18.2 mi (29.3 ks) upstream from mouth.
DRAINAru~' ARKA.--2,459 mis (6,369 lanZ). ·
PERIOD OF RECORD.--Jantmz~ 1907 to current year. Honthly discharge only for some periods, published in WSP 1312. Prior to Hov~ssber 1923, published as "near
REVISED RECORDS.--WSP 788: 1924. WSP 1148: Drainage erea at former site. WSP 1632: 1908(H). ~SP 1922: Drainage
CAGE.--Water-ataHe recorder and concrete control. Datum of sage £s 433.40 ft (132.100 m) National Geodetic Vertical
Da~ of 1929. Prior to November 1923, nonrecord£ng sage at sics 15.5 mi (26.9 k~) dovnstrea~ at different dat~.
Nov. 1. 1923. to ~k~v. 13, 1934. nonrecordinS gage, and Nov. 14, 1936. to July 6. 1938, water-stage recorder at
present site end dates. July 7. 1938. to Apr. 14, 1939, nonrecordtng g~e at site 9.3 mi (15.0 k~) downstream at
datu~ 22.94 ft (6.992 m) lover. Apr. 15. 1939, to Sept. 30, 1955, water-stage recorder at site 8.5 mi (13.7
dovns~rea~ at datum 22.94 ft (6.992 m)
REHAR~S.--Records good. Flow is largely regulated by Levisville Lake (station 08D52800) since November 1954 end by
Grapevine Lake (station 08054500) since July 1952. Records furnished by .the city of Dallas show ~hat during the
year 129.100 acre-ft (159 hms) was diverted from pool at gage and 41,670 acre-it (51.6 hms) vas diverted from rive
channel 16 mi (23 .ks) downstream for unmicipal use. Also, 2,350 acreoft (2.90 hms) vas returned from a water treat-
sent pleat Co tbs river below chis station. Records fut-nished by the Dallas Power end Light Co. show that during
the year 6,510 acze-ft (8.03 hms) was diverted fr~n pool at gage into North Lake for cnol£ng water at electr£c
generatinA plant. Several observations of water temperature were made du~in~ the year. Gage-height telemeters
located at station.
AV~P~O!~DISCRARGE.--~7 years (vater yea~e 1908-54), prior to regulation by L~via~ille and Grapevi~e Lakes, 818
(23.1~ m~/e). 592,600 acre-fc/~ (731 hm~/y~); 28 years (rater years 1955-82), regulated, tmadJuaced, 769 ft$/s
(21.78 mS/e), 557,100 acre-ft/yr (687
~J~£KEHES FOR PDIOD OF RECORD.--~--~ gage height, about 17 ft (5.2 m) _~, 25. 1908, present site and datum, from
information by local resident, eet4~nated discharge, 145,000 ~tS/s (4.110 m /s), at site 8.5 mi (13.7 'ks) downstream
(from information by Corps of Engineers).; max .t~um ~a.s.e h. eigh_c su. bsequ.e, nt.to 1908_, 14.5 ft (4.12 m) Apr. 26. 1942,
present site and dattm, from obse~V&tiou oy National weather uervLce; a~acnarEe a~ site 8.5 mi (13.7 km) downstream,
90,700 fts/e (2.570 mS/s); no flow et
Flood in 1866 ~eached about ~he $a---e sta~e es flood of Nay 25, 1908.
EXTRD~ES FOR CURRENT ~J~.--Naxi~um discharge, 21,100 fts/s (598 mS/a) Nov. 2 'at 1200 hours, ga~e height;' 10.65 (3.246 u); no flow Oct. 8.
DISCHARGe, ]~q CUBIC FEE~ PER SECOND, WATER YEAR OCTOBER 1981 ~O SEPTEMBER 1982
DAY OCT NOV DEC J~J~ FEB HAR APR HAY ~ JUL AUG SEP
' 1 204 12700. 6980 5350 3150' 33/,..0" 596 250 7530 6580 6580 3950
2 172 20500 ' 7050 5360 3210 4180 596 322 6660 6530 6540 ~020
3 214 19000 7060 5350 3680 4320 580 291 5650 6380 64.90 /,,030
4 176 15700 ' 7050 5300 3550 /,..190 580' 315 4960 6500 64.70 4.040
5 152 12400 7050 5280 3540 3050 564 342 /,,~70 6610 66,90 6010
6 190 10~00 7040 5270 3490 1010 556 691 4.600 6650 6510 3850
7 321, 9000 7010 5260 3550 902 540 5410 7100 6520 3780
8 3.9 8310 7020 5260 3520 646 56..8 455 6200 5630 . 6530 3500
9 79 8700 7010 5250 356,0 161 54-8 4~3 6500 5840 6530 849
10 66 8690 7000 5200 3530 152 629 623 6440 6/+40 6510 151
11 63 8110 6970 5190 3470 136 621 649 6380 2960 6500 289
12 1290 7260 6960 5170 3290 140 629 2250 6510 988 6500 285
13 1550 6~50 6960 5160 3510 152 723 10900 6750 6630 6460 310
14 176.0 6510 6920 5170 3340 185 731 3390 6510 6270 6440 308
15 119 6830 6910 5160 2820 185 723 476 6190 6640 6430 294
16 872 6930 6890 516.0 2980 348 76.8 361 61&0 6720 - 642.0 362
17 3140 6880 6880 5130 3750 355 754 730 1810 6670 6420 301
1 8 6560 6990 6880 5060 3910 368 588 1880 1090 6480 6410 319
19 7&30 6760 6870 &200 3850 ~,57 564 3350 5160 5860 6320 322
20 7910 6730 6860 3750 3820 450 564 4950 6320 5660 5730 238
21 7830 7010 681'0 3790 3800 672 556 5470 6460 5620 '5.590 145
22 8920 7050 6750 4010 3800 4/,,3 4.95 5350 6590 6300 55/,..0 114
23 8090 7030 6740 3750 3800 443 852 5160 6280 6540 5520 · ' ~ 53
26 7230 7010 6690 3720 3780 450 895 5390 7060 6640 5440 199
26
6070
7O00
6680
'3~00
844 6600 6900 6680 5190 215
3910
650
27 600o 700o · 6620 352o3290 588 6~2 6810685067,o.5,6o2o9
28 6230 6990-659o352o3150 .510408 67205380673o5,~0 ,82
29 66~0 6980 6.0 3400 --- 495 328 716o 4950 6650 5, 60 ,76
30 6.,8o 699o 5590 394o --- 495 ~04 77oo 6030 657o 4990 ~70
31 7390 --- 5360 3840 --- 525 --- 7810 --- 6570 4230 ---
TOTAL 110181.9 264910 210350 142790 ~8980 30012 18550 103132 176700 18886,8 186080 36995
~ 3556 8830 6785 4606 3535 968 618 3327 5823 6092 6003 1233
NAX 8920 20500 7060 5360 3950 4320 895 10900 7530 7100 6580 4040
N~N ' 3.9 64.50 5360 3400 2820 136 204 154 1090 988 4.230 11 4
AC-FT 218500 525400 417200 283200 196300 59530 36790 206600 346500 374600 369100 73380
CA1.. YR 1981 TC'TAL 643767.33 NE.AN 1764 I, tAX 20500 l'ilN .00 AC-FT 1277000
rarER YR 1982 TOTAl, 1565528.90 Hr_,AN . 4289 iv, AX 20500 NIN 3.9 AC-ri' 3105000
As can be seen, the majority oF the overbank Flow is very
shallow, often less than one foot. Chow states that, "on
Flood plains, the value oF 'n' usually varies with the
stage of submergence oF the vegetation at low stages."
Chow presented 'n' values in the overbanks oF the
Nishnabotna River in Iowa. Although it would be impossible
to draw definite numbers From this small sample, a range oF
changes in 'n' values might be a good indication. For a
meadow, in Chow's example, the 'n' value doubled when water
surface elevations decreased From Four Feet to one Foot.
The conclusion we drew From this comparison was that 'n'
values in the overbank oF the Elm Fork oF the Trinity might
be considerably higher than expected when low Flood Flow
conditions exist, perhaps on the order oF as much as twice
the expected value.
With this thought in mind, we again modeled the Elm Fork
using higher overbank 'n' values. Even though we were
closer, we still Felt that the 'n' values we had to use
were excessive, so we considered another option.
The main channel o¢ the Elm Fork is relatively smooth under
normal Flow. We used an 'n' value oF 0.06 For this
channel. However, we had set the top oF bank stations
according to the cross section, A closer look at the
channel, as shown below, shows clearly that the area above
the normal Flow level is virtually choaked with trees and
brush.
This heavy growth thins out some after moving some distance
away from the banks. It didn't seem appropriate to model
the channel with a roughness of 0.06 with this heavy growth
in the upper portion. We elected to model the channel with
a roughness of 0.06 up to the elevation of the mean flow
conditions. We took this to be 4300 ors. A run was made
which set the elevations of the mean flow.
The water surface elevations are shown below. These
elevations were used on "NV" cards to model the channel,
and everything in the channel above this elevation was
considered as very heavy trees. In = 0.16}
Cross Sect. lO0-Yr.
No. Q ~ater Surface
930.00 4300,00 419.93
937.80 4300.00 423.97
950.97 4300.00 428.43
952.70 4300.00 428.93
966.20 4300.00 431.66
966.70 4300.00 437.26
967,60 4300.00 438.50
Considering these two approaches, we were able to obtain a
good calibration with the USGS gage. USGS gage records for
a discharge of 21100 cfs yield a reading of 444 feet NGVD.
Our model obtained a water surface of 443.55 feet NGVD for
the same discharge. This range is well within acceptable
limits.
Next, we tried running the' tOO-year discharge in this
calibrated model. The results we got were plotted on the
cross sections and we then discovered that we were no
longer at extreme shallow flow conditions.
Instead, we find that depths have increased substantially.
Considering the same cross section seen earlier with the
lO0-year discharge, this becomes obvious:
t3
CROSS SECTION 950.97
ELM FORK TRINTY RIVER
DALLAS COUNTY
460
450
Z
~-- 440
LL i
Z' 430
I
0
I
~- 420 l
__1
u~ 4~o [
800 2300 3800 5300 8800 8300 9800 11300 12800 ~.4300
DISTANCE, FEET
So, now we had to determine a new 'n' value in order to
obtain an appropriate model. We elected to reduce the 'n'
value based on engineering Judgement and a review of an
aerial photo we obtained for 1981 conditions (see next
sheet).
The resulting baseline model does not match the USGS rating
curve (see next sheet) for the Sandy Lake gage. However,
this USGS rating curve is extrapolated past the 21100 ors
discharge. We firmly believe that this extrapolation is
based on conditions that do not consider variable 'n'
values. Based on good and reasonable backwater analysis
methods, the 'n' values required to reach the USGS
projected water surface elevation at the tOO-year frequency
event are not reasonable. We believe that the method
presented in this report is much more accurate. After all,
both the USGS and we are guessing past the recorded data.
The following table presents the 'n' values used for the
calibration model, baseline model and present conditions
model through the Sandy Lake gage. 'n' values are similar
upstream.
14
VALUES (LEFT/RIGHT/CHANNEL)
Cross Calibration Baseline Present Notes:
Section Model Model Condition L = Le~t, R = Right, C = Channel
930.0 L - 0.13 .095 .095 L - cultivated, gravel pits, construction
R - 0.15 .1 .06 ~ R - cultivated, heavy trees
C - 0.12 .13 .13 C - 0.06 below tree line, 0.16 above
937.8 L - 0.13 .095 .095 L - same
R - 0.15 .1 .06 ~ R - cultivated, heavy trees
C - 0.14 .15 .15 C - same
950.97 L - 0.13 .09 .09 L - trees, brush, gravel pits
R - 0.13 .085 .06 ~ R - cultivated, construction, trees
C - 0.14 .15 .13 C - sa~e
952.7 L - 0.14 .09 .09 L - same
R - 0.13 .085 .06 * R - same
C - 0.15 .13 .13 C - same
966.2 L - 0.14 .07 .07 L - construction, land~ilt, commercial
R - 0.13 .1 .06 * R - construction, trees, brush
C - 0.15 .1~ .13 C - same
966.Z L - 0.13 .07 .07 L - same except includes road
R - 0.1~ .1 .1 R - construction, trees, brush, road
C - 0.06 .06 .06 C - no trees on upper banks
967.6 L - 0.12 .07 .07 L - so~e trees, brush
R - 0.1~ .1 .1 R - brush, trees
C - 0.06 .06 .06 C - n,) trees on upper banks
~ Improved with ~ill and overbank swale
Note: "same" re,ers to same overbank or channel in previous cross section
C.6. Floodways and Encroachments
We used the same encroachment approved by FEMA for projects
considered in the present condition model.
We did not reduce the floodway anywhere e×oept at Sandy
Lake Road. The reason we reduced the floodway at this
location was because we obtained data from field surveys
Isee following pagesl that showed Sandy Lake Road to be
above the lO0-year frequency water surface elevation
calculated at the road. This means that the assumption
previously made that water was overtopping Sandy Lake Road
in the right overbank was not correct. Since the "flood
plain" flow is almost directly south at the road
(perpendicular to the road), it must be assumed that this
flow is ineffective. We modeled it this way.
Further, our understanding is that floodways should not be
defined in ineffective flow areas. Also, the water levels
just upstream of Sandy Lake Road are about one to two feet
in depth, not an area in which we would normally define a
floodway. Because of this, we elected to draw the floodway
along the banks of Denton Creek.
0.7. Structures
An important structure in this model is the Carrollton dam,
just downstream of the Sandy Lake gage station. This dam
is a fast flowing effective structure at Iow to normal
flows.
16
However, at flows in excess of 12000 cfs, this dam is
flooded and has almost no effect on the water surface
elevation. This was confirmed in the 1981 Flood by records
of the USGS (conFirmed by Walter Lear, USGS, Austinl.
Thus, we didn't include an overflow weir computation.
The other bridges along this river are above the tOO-year
flood levels, so they were not modeled as a special bridge.
0.8. Velocities
Channel velocities and overbank velocities are associated
with this massive river and thus are generally slow moving,
even in the lO0-year event. In our field investigations,
we saw no signs oF erosion.
D. Conclusions
We did a comprehensive model for this reach oF the river and
considered projects deemed appropriate by the Corps. There was
some initial concern about the high measurements by the USGS at
the Sandy Lake Road gage. However, when the variables are
considered, we feel that the values found in the HEC-2 backwater
model are consistent with gage readings. Care must be taken in
modeling a river of this magnitude. It contains a tremendous
potential for disaster. Small streams can be modeled
independently without a great potential For concern, but not the
Trinity. Because of this, we have made our model available to
the North Texas Council of Governments. We support their efforts
to coordinate actions taken in regard to this great Texas river.
This flood study was based on conditions shown in this report.
Any changes to these conditions, or any modification oF this
report, would change the results of this report and thereby
nullify it.
17
hYDRAULIC ANALYSIS
TRINITY RIVER REGIONAL ElS
I. Hydraulic Analysis
A. Scope of Work - Purpose and Goals
B. Location of Limit of Study
C. Origin of Data Base
II. Approach - Methodology
A. Development of Models
1. Existing Conditions (1985)
2. Future Without
3. 404 Permits in Floodway Fringe Only
Maximum Development 1 (MD1)
5. Maximum Development 2 (MD2)
B. Computation of Water Surface Elevations With Hydrology
Revised for Each Scenario.
III. Summary
List of Figures
A-4 - A-9 Trinity River Existing Conditions Water Surface Profiles
A-10 - A-15 Elm Fork Existing Conditions Water Surface Profiles
A-16 - A-23 West Fork Existing Conditions Water Surface Profiles
List of Tables
A-1 - A-22 Flood Frequency/Water Surface Elevation for Each Scenario
A-23 Trinity River Existing Conditions Discharges
A-24 West Fork Existing Conditions Discharges
A-25 Elm Fork Existing Conditions Discharges
I. Hydraulic Analysis
A. Scope of Work - Purpose and Goals
The purpose of the hydraulics study is to develop hydraulic models
necessary to assess the immediate and potential impacts of development
and construction along the West Fork and Elm Fork of the Trinity River.
The goal throughout this study has been to provide technical data used
in making an evaluation of these impacts on river hydraulics, flood
protection, fish and wildlife habitats, and water quality.
B. Location and Limits of Study
The hydraulic models developed for this study include a portion of the
Trinity River and portions of its two main tributaries, the West Fork
and Elm Fork. Limits of the Trinity River model are from Malloy Road,
southeast of downtown Dallas in Seagoville, upstream to the
West Fork/Elm Fork confluence. The West Fork model extends from its
confluence with the Elm Fork upstream to Riverside Drive in Fort
Worth. The Elm Fork model extends from its confluence with the West
Fork to Hwy 121 in Lewisville.
C. Origin of Data Base
Hydraulic models developed for the 1978-1981 Dallas and Tarrant County
FEMA studies (Flood Insurance or FIS) were the primary data base used
in the Trinity River Regional EIS. Data files developed for the 1979
study of the Dallas floodway extension were used in modeling scenarios
which included the Dallas floodway extension. The Dallas County FIS
did not include a model of the Elm Fork to the limits defined above,
therefore, a file, 'modeled by the HEC-2 Water Surface Profiles
computer program and developed for the 1982 Lewisville FIS, was needed
to complete the Elm Fork model from river section 1090+00 to
Hwy 121 (section 1503+10). Input data for each scenario are coded in
format for the LRD-1 water surface profiles computer program, except
for the above HEC-2 file and the MD1 and MD2 scenarios described in
paragraphs II.A.4 and II.A.5.
II. Approach-Methodology
A. Development of Models
1. Existing Conditions (1985)
The "existing conditions" hydraulic models are updated versions of the
hydraulic models used in the FEMA studies of Dallas and Tarrant
Counties completed in 1981. The FEMA data files were modified to
reflect recent changes in the conveyance and/or storage properties of
the river system caused by development, landfills, levees and channel
modifications. For purposes of the Trinity River Regional EIS, the
"existing conditions" model includes additions to the 1978-1981 study
in place or permitted prior to July 1985. New cross sections were
added where necessary. Data generated from this model serves as a
basis for comparison with the possible or hypothetical scenarios
addressed later in this report.
2. Future Without
The hydraulic model is the same as the "existing conditions" model
except for a portion of the Elm Fork below Royal Lane. Existing fill
in the area east of Luna Road blocks conveyance and precludes valley
storage. Although a levee has not been built, permit activity in this
area has been high and complete development is anticipated in the near
future. Consequently the area east of Luna Road, from Royal Lane
south to Northwest Highway parallelling the Elm Fork as it bends
eastward to the I.H. 35 embankment, was treated as a nonconveying
nonstorage area. Conveyance and storage were not allowed in the other
portions of the area where levees exist. No changes were made to the
hydraulic models of the Trinity River or the West Fork.
3. 404 Permits in Floodway Fringe Only
Under this scenario all floodway fringe areas defined by the FEMA
study were assumed to be fully developed. The West Fork model was
developed by imposing the FEMA encroachment limits on the "existing
conditions" model. The differences in water surface elevations on the
West Fork produced by this study and the 1982 Tarrant County FIA.
study are caused by the addition of development, such as new bridges
and landfills, which has occurred or has been permitted for
construction inside the floodway fringe combined with increased flood
frequency discharges.
In the Elm Fork hydraulic model, the reaches upstream of Sandy Lake
Road were modeled by blocking flow outside the floodway fringe.
Development and levee construction below Sandy Lake Road closely
agrees with the FEMA floodway alignment; therefore, encroachments were
not made beyond the encroachments in the "existing conditions" model.
Water surface elevations were computed for the Trinity River, West
Fork and Elm Fork with the existing Dallas floodway channel. In
addition four options were studied for the Trinity River utilizing a
100 foot and a 200 foot floodway channel with and without the Dallas
floodway extension (see chapter II, section D). The hydrology for the
West Fork and Elm Fork is the same for the four options, therefore the
water surface elevations in those portions of the model are the same
for each option.
4. Maximum Development 1 (MD1)
The purpose of this scenario is to approximate the impacts of maximum
land useage without control of development in the floodplain. The
analysis assumed a narrowly leveeded floodway with a maximum size
channel, thereby allowing the maximum developable land area within the
West Fork and Elm Fork flood plains (from Sandy Lake Road to the upper
limit of the study area). In the West Fork and Elm Fork models,
artificial cross sections were created using fixed channel depths and
fixed overbank areas while varying the channel width. The depth of
Channel was fixed at 20 feet, which approximates the depth of the
existing channel. The distance from top of channel to toe of levee
was set at 50 feet on each side, which is the minimum distance for
construction and maintenance. Channel and levee side slopes were
fixed at 3 horizontal to 1 vertical. Since the overbank areas were
fixed, the distance between levees varied with the changes in channel
width.
Conveyances at ~alected cross sections were determined from the
existing conditions SPF discharge and the slope of the hydraulic grade
line. The depth of flow was also noted. Channel sizes in the
artificial sections were utlimately determined by varying iteratively
the channel bottom width until the conveyance and depth in the
artificial channel section matched the existing conditions SPF
conveyance and depth at the same location. Iterations were made one
section at a time. Subsequent increases in the discharges, after the
hydrology was recomputed to account for the loss of valley storage,
caused the water surface elevations as published for the MD1 scenario
to exceed the existing conditions SPF elevations by significant
amounts. Roughness coefficients used in conveyance computations were
0.040 for the channel and 0.070 for the overbank areas. The physical
dimensions of this system are identified in appendix B, table B-29.
5. Maximum Development 2 (MD2)
As in MD1 this scenario represents a condition in which all flood
flows are contained within a levee system. This scenario emulates the
Dallas floodway/levee system with the width between levees arbitrarily
fixed at 1300 feet. The channel depth is 20 feet with side slopes 3
horizontal to 1 vertical. In the West Fork and Elm Fork models, the
channel width was varied iteratively until conveyance and depth in the
artificial section matched the existing conditions SPF conveyance and
depth at the same location. Roughness coefficients used in the
conveyance computations were 0.040 for the channel and 0.070 for the
overbank areas. The physical dimensions of this system are shown in
appendix B, table B-54. o
B. Computation of Water Surface Elevations With Hydrology
Revised for Each Scenario
Valley storage data were developed for each scenario with a range of
20 discharges from 200 cfs to over 400,000 cfs. Water surface
elevations, using revised hydrology for the 10 yr, 25 yr, 50 yr, 100
yr, and SPF discharges, were computed for the following scenarios:
1. Existing Conditions (1985)
a. Trinity River
b. West Fork
c. Elm Fork
2. Future Without
a. Trinity River
b. West Fork
c. Elm Fork
3. 404 Permits in Floodway Fringe Only - Existing Dallas
Floodway
a. Trinity River
b. West Fork
c. Elm Fork
4. 404 Permits in Floodway Fringe Only
a. Trinity River
(1). 200 ft channel Dallas floodway - No floodway
extension
(2). 100 ft channel Dallas floodway - No floodway
extension
(3). 200 ft channel Dallas floodway - With floodway
extension
(4). 100 ft channel Dallas floodway - With floodway
extension
5. Maximum Development 1 - MD1
a. Trinity River
(1). 200 ft channel Dallas floodway - No floodway
extension
(2). 100 ft channel Dallas floodway - No floodway
extension
h. West Fork (artificial sections)
c. Elm Fork (artificial sections upstream of Sandy
Lake Road)
6. Maximum Development 2 - MD2
a. Trinity River
(1). 200 ft channel Dallas floodway - No floodway
extension
(2). 100 ft channel Dallas floodway - No floodway
extension
b. West Fork (artificial sections)
c. Elm Fork (artificial sections upstream of Sandy
Lake Road)
Ail hydrology beyond existing conditions was computed assuming
ultimate urbanization conditions. The Dallas floodway and floodway
extension levees were assumed to extend vertically to contain all
flows for each scenario in terms of computation of valley storage and
water surface elevations.
A hydraulic computer model was not developed for the MD1 and MD2
scenarios for the West Fork or Elm Fork due to time and cost
constraints, therefore, storage data were determined graphically. A
set of conveyance curves was developed, one curve for each optimum
channel configuration, with conveyance, K, plotted against depth of
flow. Revised reach lengths and a separate curve showing the
relationship of area to discharge at each artificial section were
provided to the hydrologists for the determination of valley storage
and flood frequency discharges.
Once revised hydrology was computed for the MD1 and MD2 scenarios,
conveyance was computed by the relationship Q=KS 1/2, where Q is the
discharge at an artificial section, and S is the slope of the
hydraulic grade line at the same section. The depth of flow
corresponding to each K value was read directly from the curve unique
to a particular section. Water surface elevations were determined
by adding the depth of flow read from the curve to the thalweg
elevation at the corresponding section.
The results of each scenario, indicating the flood frequency and
corresponding discharges and water surface elevations at selected
locations along the Trinity River, West Fork and Elm Fork, are
provided in tables A-1 - A-21 at the end of the appendix. Tables
A-22 - A-24 indicate peak discharges and reaches for the Trinity
River, West Fork, and Elm Fork. Existing conditions water surface
profiles for the Trinity River, West Fork and Elm Fork are shown in
figures A-4 - A-23.
III. Summary
The results of the hydraulic analysis indicate continued development
of the West Fork and Elm Fork valleys, until the available valley
storage is progressively reduced and a substantial length of the total
reach is channelized, will produce a discharge from a flood event the
order of magnitude of the design flood which will exceed the capacity
of the existing Dallas floodway system (per original design parameters
and contract plans). It should be noted that significant settlement
of the levees has occurred in some locations, therefore, the full four
not universally available at the present time.
feet
of
freeboard
is
Some restoration of these settlement areas has been completed by the
City of Dallas, however, a complete evaluation of the system has not
been made.
The effects of channelization and loss of valley storage is most
significanlty illustrated in the MD1 and MD2 scenarios which produce
large contrasts in flood discharges and water surface elevations for
the Trinity River, West Fork and Elm Fork as compared to the existing
conditions..
The analyses of existing conditions indicate, with Joe Pool Lake on
line, the discharges produced by a design flood are about 6 percent
greater than the original design discharge of the Dallas floodway
system. About 3 feet of the original 4 feet of freeboard of the
The analysis also indicates ultimate
Dallas
floodway
would
remain.
urbanization of the watershed (exclusive of further floodplain
development in the West Fork and Elm Fork) will produce a discharge
for a design flood in the Dallas floodway (Trinity River) about 7
percent greater than the design flood. When ultimate urbanization is
combined with a level of flood plain development in the West Fork and
Elm Fork valleys in accordance to the FEMA floodway plan, the
discharge from a design flood would be about 25 percent greater than
the original design discharge. Such a discharge would reduce the
existing freeboard of the Dallas floodway system to l~ss than 1 foot.
The hydraulic and hydrologic portions of this report were completed
with the purpose of providing hydraulic and hydrologic information for
the Trinity River Regional EIS. The results of this study should not
be considered conclusive, but rather the data should be considered a
basis for predicting comparative impacts to the flood plain and
adjacent wetland areas of the Trinity River, West Fork and Elm Fork.
Data generated by this study should be helpful in focusing attention
to areas of potential flood damage which impose threats to the
environment and human safety. The results of this study should not be
used beyond the intended scope of the Trinity River Regional EIS and
do not supersede the Dallas FIS. ~
TABLE A-3
ELM FORK
EXISTING CONDITIONS 1985
Flood Water Levee Channel
Flood Discharge Surface Crest Flow Line
Location ~requency (cfs) Elevation Elevation Elevation
Loop 12, 10-Yr 20300 417.8 * 434.0 389.2
Sta 294+60 25-Yr 27100 420.3 *
50-Yr 34200 422.1 *
lO0-Yr 42700 424.9 *
SPF 87800 434.3 *
Royal Lane, 10-Yr 23100 427.1 -- 401.4
Sta 592+20 25-Yr 30400 427.9
50-Yr 37400 429.0
100-Yr 45300 430.3
SPF 88000 437.1
Valley View Lane., 10-Yr 23100 431.2 441.0 402.0
Sta 711+50 25-Yr 30500 432.4
50-Yr 36900 433.3
100-Yr 44600 434.2
SPF 86800 439.2
Sandy Lake Road, 10-Yr 23000 441.3 -- 414.5
Sta 967+60 25-Yr 28000 441.5
50-Yr 35000 442.3
100-Yr 41000 443.1
SPF 79000 447.4
IH 35E, 10-Yr 11300 449.3 -- 424.0
Sta 1138+20 25-Yr 13800 449.7
50-Yr 16100 450.1
100-Yr 21000 450.6
SPF 62000 452.8
Hwy 121, 10-Yr 6300 456.9 -- 430.0
Sta 1503+10 25-Yr 6300 457.2
50~Yr 9000 458.3
100-Yr 21000 461.5
SPF 62000 468.4
* Water surface elevations produced by West Fork peak discharges and Elm Fork
coincident discharges.
CORPS OF ENGINEERS U.S. ARMY
o
THAL.[O-~~ 430
DISTANCE IN FEET/lO0
Coppetl, Texas 75019
214 - 462 - 0022
The City With A Beautiful Future
July 3, 1986
Federal Emergency Management Agency
Federal Insurance Administration
Office of Risk Assessment
Risk Studies Division
500 C Street S.W.
Washington, D.C. 20472
Re: Flood Insurance Study Revision along the Elm
Fork Trinity River in Dallas, County, Coppell,
Texas (Vistoplex Development on Sandy Lake Rd.)
Attention: Mr. Matt Miller
Dear Mr. Miller:
The City of Coppell has received a Technical Report from
the consulting engineering firm of Caffey and Morrison,
Inc., on the existing and proposed flood plain and
floodway conditions along the Elm Fork Trinity River,
adjacent to Sandy Lake Rd., Coppell, Texas. This
report, prepared by Caffey and Morrison, Inc., includes
a detailed hydraulic analysis of the existing channel
and overbank conditions, as well as proposed improve-
ments. The report also includes the HEC-Z computer printout,
flood plain and flood way maps and possible revisions
of the existing flood insurance maps. It is our under-
standing that this same information has already been
submitted to your office for review. The City of
Coppell has reviewed this material and agrees with its
content.
If you have technical questions about this report,
please contact Mr. Ron Morrison, P.E., with Caffey and
Morrison, Inc. (1-817-649-8110). Any administrative
questions should be directed to the office (1-214-462-
0022).
Thank you for your consideration of this very important
request.
Sincerely,
"~i~tE~ Powell, P.E.
Engineer
cc: Mr. Wayne Ginn, P.E., Ginn, Inc.
Mr. Ron Morrison, P.E., Caffey and Morrison, Inc.
Mr. Bill Kuno, Federal Emergency Mangement
Agency, Region IV
NET ACREAGE 12.6 AC .. -.-.
OFFICE 711,140 SI:: .
RETAIL 63,903 SF
Sandy Lake Road ..... · ·
Preliminary Site Plan
. INC.
CAFFEY AND MORRISON, INC.
ENGINEERS -- HYDROLOGISTS
May 23, 1986
Mr. Ed Powell
City Engineer
City of Coppell
P.O. Box 478
Coppell, Texas 75019
Re: Flood Insurance Study Revision along the Elm Fork
Trinity River in Dallas County, Coppell, Texas
Job No. 85048
Dear Mr. Powell:
The enclosed flood study of an area adjacent to Sandy Lake
Road along the Elm Fork Trinity River which is in your city
has been submitted for your review with respect to its
general content and concept. The study was prepared in
order that a Flood Insurance Study Revision might be
obtained in the project area from the Federal Emergency
Management Agency. Final approval cannot be obtained until
as-built plans have been submitted to FEMA. Your city has
final approval authority over such matters in your
jurisdiction.
If the study meets with your approval in general content and
concept, you are respectfully requested to write FEMA and so
inform them. Also request that FEMA review the material for
the purpose of issuing approval for a Flood Insurance Study
Revision.
In order to save a few days, we have already forwarded
copies of the flood study to the FEMA Regional and
Washington offices and to the Corps of Engineers for their
permitting review. Initiation of the review by FEMA is
dependent upon their receipt of your letter indicating the
approval of the floodway revision.
Should you have any questions about the study or need a
better understanding of the development objectives, please
call us.
Sincerely yours,
Ca~_gy and Morrison, Inc.
Vice President
2212 ARLINGTON DOWNS RD., SUITE 105 · ARLINGTON, TEXAS 76011 · (817) 649-8110 · METRO 640-8101
Coppell, Texas 75019
214 - 462- 0022
/~ The City With A Beautiful Futu e
March 21, 1986
Mr. Bill Kuno
Federal Emergency
Management Agency, Region IV
Hazards g Mitigation Division
Federal Center
Denton, Texas 76201
RE: Village at Cottonwood Creek
Coppell, Texas
Dear Mr. Kuno:
The City of Coppell has received a Technical Report on existing and
proposed flood plain and floodway conditions along Cottonwood Branch
within the reference subdivision. ~is report, prepared by Wier and
Associates, Inc., includes a detailed hydraulic analysis of the existing
channel and overbank conditions, as well as proposed improvements. The
report also includes the HEC-Z computer printout, flood plain and
floodway maps, and other data necessary to provide a conditional letter
of map revision and possible revisions of the existing flood insurance
maps. It is our understanding that this same info~ation has already
been submitted to your office for review.
If you have any technical questions about the report, please contact Mr.
David McCa~er, P.E., with Wier and Associates, -Inc. (817-265-2006).
ky administrative questions should be directed to this office
(214-462-0022).
Thank you for your consideration of this very important request.
Sincerer,
Powell, P.E.
City Engineer
City of Coppell
cc: Mr. W. Wayne Ginn, P.E., Ginn, Inc.
Mr. David McCarver, P.E., Wier & Assoc., Inc.
TOTAL ACREAGE 18.3756 AC
OFFICE 78,140 SF
RETAIL 63,903 SF \ ""
5andy Lake ~oad .......
Prelimin~r7 Site Plan
I
'
I
!
. INC.
CAFFEY AND MORRISON, INC. ~
ENGINEERS -- HYDROLOGISTS
May 23, 1986
Mr. Ed Powell
City Engineer
City of Coppell
P.O. Box 478
Coppell, Texas 75019
Re: Flood Insurance Study Revision along the Elm Fork
Trinity River in Dallas County, Coppell, Texas
Job No. 85048
Dear Mr. Powell:
The enclosed flood study of an area adjacent to Sandy Lake
Road along the Elm Fork Trinity River which is in your city
has been submitted for your review with respect to its
general content and concept. The study was prepared in
order that a Flood Insurance Study Revision might be
obtained in the project area from the Federal Emergency
Management Agency. Final approval cannot be obtained until
as-built plans have been submitted to FEMA. Your city has
final approval authority over such matters in your
jurisdiction.
If the study meets with your approval in general content and
concept, you are respectfully requested to write FEMA and so
inform them. Also request that FEMA review the material for
the purpose of issuing approval for a Flood Insurance Study
Revision.
In order to save a few days, we have already forwarded
copies of the flood study to the FEMA Regional and
Washington offices and to the Corps of Engineers for their
permitting review. Initiation of the review by FEMA is
dependent upon their receipt of your letter indicating the
approval of the floodway revision.
Should you have any questions about the study or need a
better understanding of the development objectives, please
call us.
Sincerely yours,
Caffey and Morrison, Inc.
L-~Ronald W. Morrison, P.E. Vice President
2212
ARLINGTON
DOWNS
RD.,
SUITE
· ARLINGTON, TEXAS760~ · (817) 649-8110 · METRO 640-8101
105
SAMPL-E~TRANSMi TTAL LETTER
November 27, 1985
Mr. Matt Miller
Federal Emergency Management Agency
Federal Insurance Administration
Office of Risk Assessment
Risk Studies Division
500 C Street S.W.
Washington D.C. 20472
Dear Mr. Miller:
Mr. Robert Hawrylak of Hawr¥1ak and Associates, Inc. of
Arlington, Texas has submitted the attached Flood Study of the
Freeport North Addition along Cottonwood Branch in Coppell,
Texas. As City Engineers, we have reviewed the material in regard
to general content and concept and it meets with our approval.
In view of this, we request that FEMA review the material as a
Conditional Revision and provide comments. Upon a favorable
review by FEMA and completion of the project, we intend to submit
as-built plans to obtain a final Flood Insurance Study .Revision.
We have asked that the firm preparing the report, Caffey and
Morrison, Inc. of Arlington, Texas, send a copy of the report to
your office and'to'the FEMA regional office in Denton, Texas.
We understand that in order for the channelization tb ~emain in
the condition for which it was designed, it is necessary for the
city to maintain the channels relatively free of heavy growth.
Our city ordinance addresses this and the city accepts
responsibility for maintenance .of the channels through this
project.
We have submitted a copy of this letter and the accompanying
report to the FEMA Region Six office in Denton, Texas. We
appreciate your attention to this request and look forward to
your reply.
Sincerely,
Wayne Ginn, P.E.
Ginn, Inc.
Consulting Engineers
16135 Preston Road
Suite 112
Dallas, Texas 75248
Region VI, Federal Center
800 North Loop 288
~ Denton, Texas 76201-3698
APPENDIX 1
FLOOD PROFILES FROM THE CITY OF COPPELL FIS
il
APPENDX 2
FEMA FLOOOWAY MAPS
CITY OF CARROLLTON AND COPPELL
AND CORPS WORK MAP
t9
APPENDIX 3
COMPARISON FLOOD PROFILES
FOR 1981 AND PRESENT CONDITIONS
2O
CO~4PARISON 100 YR WATER SURFACE
EL~4 FORK TRINITY RIVER
DALLAS COUNTY
448 ........
446...... t ......... ' --'"""'""~
445.... I .... ~'-"~ ....
443
-,: ~~ ~ . ',
44~
440
t
I
438 1. 1
g~O g30 g40 gso gBO g70 gBO ggo ~000 JO~O
DISTANCE, KEET X ~00
APPENDIX 4
FLOOD PROFILES FOR PRESENT CONDITIONS
PRESENT CONDITIONS 100 YR WATER SURFACE
' EL~ FORK TRINITY RIVER
DALLAS COUNTY
455 , '..,,-
· ,,, ~ ': .... ~.,~ ...........
450 ' ~' ~~:~ ~'~'
> 445 ....
Z
-.-.. 440
~ 435
I~ 430 .
~ 425 .....
0
:: 420
> 4t5
~,~ 4~0 _ _ . ................ = ....
405 _
920 940 960 980 tO00
DISTANCE, FEET x ~00
PRESENT 1O0-YR WATER SURFACE
EL~ FORK TRiNiTY RZVER
4§0I J I....... ! ..... I
455__' ................ I.... I
~ I
~. 450 .................. ~ ..............
(_9 ~ .....
-_.. ~4§
t''~ ~0
Et_ q~5 ...... [.
~ 430
:' 485 ~-~
~:~ 420
ao05 ioi5 i025 ~035 1045 i055 i0~5 i075 10~5 ~095
DISTANCE, FEET X
PRESENT O0-YFi XATER SUPlFACB
ELM FORK TFI]NTTY F::I_'[VFFI
DALLAS COUNTY
465 .......
4150 __
-.-.. 450 ....... ..= ............. - .... ----- .........
!-- 445 :
LLi -
I~. 440 .........
~ 435 ............... ! ...........
CZ)
''
! 430 ...........
>. 425 _ ,.,, ~FIA ._
LL[ J!
LLI 420'_ .... ~' . ............
4t5' .J 1
1085 i095 ii05 iii5 i125 li35 i145 ii55 i165 1175
DISTANCE, FEET X 100
APPENDIX 5
FLOODWAY DELINEATIONS FOR COMPARISON
APPENDIX 6
FLOODWAY/FLOOD PLAIN DELINEATIONS
FOR PRESENT CONDITIONS
23
APPENDIX 7
1981 CONDITION5 CROSS SECTIONS
CROSS SECTION 930
EL~ FORK TRINITY RIVER
DALLAS COUNTY
455 ....................................
/
n x A
;> 445 ..... /5 x .......
I 435 ......... / ~--_~: gl~ ~ .....
> 415 . ...................
111
I
405 .....
800 2400 4000 5600 7200 8800 i0400 i2000 i3600 15200
DISTASCE, FEET
CROSS SECTION g 7.8
ELM FORK TRINTY RIVER
DALLAS COUNTY
465 , .......................... · .....
:> 454 ..............
LH 443 . , - _ ..........
0 tq~I
i
::> 42't ...... ' ....
I
4'1( · , , II
· 950 2290 3620 4970 6310 7650 8990 iOa30 11670 `130'10
BISTANCF, FEET
CROSS SECTION 950.97
ELM FORK 'TRINTY RIVER
OALLAS COUNTY
460
~. 450
LD '
~-- 440
LIJ
1
3> 480 . ,'
[j_J ,
LIJ "
410
800 2300 3800 5300 6800 8300 9800 i i300 12800 14300
DISTANCE,FEET
CROSS SECTION 952.7
ELM FORK TRINTY RIVER
DALLAS COUNTY
455 ....
/
:> 446 , .........................
2~' 428 .......................
CD
H
I
3> 4~9 ..........
LLJ
4~0 ., · ..................
950 2250 3550 4850 6:t50 7450 8750 :tO050 11350 :t2650
DISTANCE, FEET
CROSS SECTION 966.2
ELM FORK TRINTY RIVER
DALLAS COUNTY
460 ..................
::> 450 ..........
LLJ CAt ~ATI 0¢
~ 430 ..............
CD
3>- 420 : . .......
I
300 :1800 3300 4800 6300 7800 9300 :10800 12300 :13800
DISTANCE, FEET
C,qOSS SECTION 958.
ELM FORK TRINTY RIVER
DALLAS 60UNTY
450
F- 440 I
IIJ C~]LI ~A"F'I Ot
(D
~- 420
Ltl 1.
300 &800 3300 4800 6300 7800 9300 10800 &2300 ~3800
DISTANCE, FEET
APPENDIX 8
PRESENT CONDITIONS CROSS SECTIONS
CBOSS SECTION §30 ·
ELM FOBK TBINITY BIVEB
DALLAS COUNTY
455 ...........................................
~. 445 .....
Z
I 4~5
. . I]lllJ~l
> 4t5.......................
Iill
405 ...... .-,
BO0 ~400 4000 5800 7800 8800 ~0400 tSO00 t~BO0 ~5~00
DISTaStE, FEET
:~' CROSS SECTION g37.8
ELM FORK TRINTY RIVER
DALLAS COUNTY
/,1
Yr-
I-.- 443 ,.
,' ~LL ., '/.",' ' ; ; '
~ 432 '
O
H /,, ~..
:>,. 42J.
I
410
950 2290 3630 4970 63i0 7650 8990 &0330 ~ i670 &30 lO
DISTANCE, FEET
CROSS SECTION 950 . 97
ELM FORK TRINTY RIVER
BALLAS COUNTY
~ , , ;J~il I;11 I
! / ~ I LI II111 IMI I,I I ' · ..... l', ." ' ,/
I /
~-- 440
II1
420[
800 2300 3800 5300 6800 8300 9800 i laO0 12800 14300
DISTANCE, FEET
CROSS SECTION 952.7
ELH FORK TRINTY RIVER
DALLAS COUNTY
455 .. . ....
/
~ 446 .- - .............
I 437
Ii1
: : ~. D. ~A I~
I .
~ 4~g ...............
ILJ~
4~0 ..... - ...........
950 ~250 3550 4850 6~50 7450 8750 ~0050 ~350 ~2650
DISTANCE, FEET
CBOSS SBCTION 966.2
ELM FOBK TB!WTY BIV~B
DALLAS COUNTY
460 ........................
> 4~_o ....
3oo ~oo ~oo ~oo ~oo ~oo ~3oo ~o~oo ~oo ~oo
0 ISTANCE, FEET
CROSS S~CT~ON 966.
ELH FORK TR~NTY R~VER
DALLAS COUNTY
450
> 445
Z
i--- 440
'
_j I
1
425 [
~00 ~800 ~00 4800 6~00 7800 9~00
DISTANCE, FEET
CROSS SBCITOW 967.6
EL~ FORK TRiNTY RIVER
DALLAS COUNTY
440
~o
> 420
I~_1
_ I
1000 2400 3800 5200 6600 8000 9400 JO800 12200 13600
DISTANCE, FEET
CROSS SECT.T. ON 968. t
ELM FORK TRT_NTY R~.VER
BALLAS COUNTY
460
C--a
b'-'-'> 450
Z
I---- 440
;z~ 430 r
°
;> 420
_J I
300 ~800 ,3300 4800 6300 7800 9300 10800 ~.2300 ~.3800
DISTANCE, FEET
CROSS SECTION ~.006
ELN FORK I'BINTY RIVER
DALLAS COUNTY
460
444
436
428
420 J I
300 ~800 3300 4800 6300 7800 9300 ~OaO0 ~2300 ~3800
DZSTANCE, FEET
CF:lOSS SECT ~[ON 'l 0 ~I 4
ELM FORK TRT_NTY R~VER
DALLAS COUNTY
46§
i
t-- 449
iiii iii iiiJii~,
-~4~: l' l~ ,.,~ ,
0 ' ! i
~ 433 ............ __~ ! i i
485 '
~ .... ~ __~ .....
300 ~800 3300 4800 6300 7800 9300 10800 12300 ~3800
DiSTANCX FSET
CROSS SECT I ON _~ 022
ELM FORK TRINTY RIVER
O~LL$S COUNTY
~. 457
Z
I--. 44g --i
o~ 44~t~'"~~~~ ~"
II
> 433 .~ ~r~ _ _11
425 __ ~ i ....... 1
0 i500 3000 4500 6000 7500 9000 i0500 12000 ~3500
DISTANCE, FEET
CROSS SECT ]] ON ~L030 . 2
EI_I~ FORK TRINTY RIVER
DALLAS COdNTY
457
449
,
44~
433
BOO ~000 3200 4400 5600 6BO0 BO00 9~00 10400 11600
DISTANCE, FEET
CROSS SECTION ~090
ELN FORK TRINTY RIVER
BALLAS 60UNTY
465
:::> 455
' 445
LL!
0z~'' 435
425
800 t800 2800 3800 4800 5800 6800 7800 8800 9800
DISTANCE, FEET
CROSS SECTION i 136.23
ELIVl FORK TR!NTY RIVER
DALLAS COUNTY
452
I--- 444I
I. JJ ·
436
LI.J
!
I~1
3500 4500 5500 6500 7500 8500 9500 i0500 i 1500 12500
OlSTANCE, FEET
CBOSS SECTION ~ ~36.73
ELM FORK TRINTY RIVER
DALLAS COUNTY
465 ! ! ilI
.-> 457
b,- 449 J /
0~ 44t. Ii
H i
~ 433 ,
LL! i
't
42_5 ___._L
P. 000 3000 4000 5000 6000 7000 8000 9000 t.0000 1. :1.000
DT_STANCE, FEE]-
CROSS SECT.iON ~37.2
EL_~4 FORK TR_~NTY R_T_ VER
DALL~,SCOUNTY
4~0~
428 ,
35oo 4500 55oo 6500 7500 a500 9500 ].o5oo ~ ~ioo ~.2~00
DISTANCE, FEET
CBOSS SECTI
~LM FOBK TBI~TY
DALLAS COUNTY
!!!
I11
,H '
~" 433 , ~ ' I
425
3500 4500 5500 6500 7500 8500 9500 i0500 :1. _t500 ~2500
DISTANCE, FEET
CROSS SECT i ON ~ ~ 38.8
ELM FORK TRINTY RIVER
OALL~S COUNTY
> 457
CD 1
t.-- 449 t
0 t
425 · ..... _J L ....
3500 4500 5500 6500 7500 8500 gsoo ~0500 ~ ~500 ~2§00
DISTANCE, FEET
CROSS SECTIOJ',,I _1. ~39. P.
i::L~ YORK '-I-~Zt'qTY I:::I:VER
DALLAS COUNTY
I---444
I _J J j ; J
~ 4~8
3000 4000 5000 6000 7000 BO00 go00 lO000 i lO0012000
DISTANCE, FEET
CROSS SBC'T'iON i I.~9.35
EL.M FORK-i"R~NTY RI_VE,q
DALLAS COUNTY
LU
441
0
~ 433
425
~350 3350 4350 5350 6350 7350 8350 9350 10350 11350
O I S ?ANCE, FEET
CFtOo -
~S ,8~CTlOiq i!5J. 39 67
EL~ FORi( TR)iNYY
~LAS COUNTY
~ ~ I ~ ~ /
3350 4350 5350 6350 7350 8350 9350 I0350 ~1350
D ~[ S~'~'~"?' F~
,~OSS SZC-r''~' '
_ :q .L ..'.L . ~,.. I
cLNI.FORK 'l'Ri,~'~, ~, ~, R~. vEq
DALLAS COUNTY
452 __
> 448 ...................................
~t'~ 440 ~ ...............
LL. ,
~ 434
3500 4500 5500 6500 7500 8500 9500 ~0500 ~ ~500 ~2500
APPENDIX 9
USGS GAGE CALIBRATION HEC-2 MOOEL
26
APPENDIX I0
BASELINE HEC-2 (1981 CONDITIONS) MODEL
~7
APPENDIX 11
PRESENT CONDITIONS HEC-2 FLOOD PLAIN
AND FLOODWAY MODEL