To: Ken Griffin, P.E.
Director of Engineering and Public Works
City of Coppell
Fax #: (972) 304-3570
Subject: Wrangler Drive Reconstruction Project (Project No. ST 96-01)
Date: April 27, 1998
Pages: 4, including this cover sheet.
COMMENTS:
Ken-
I received a phone call from Ed Bell Construction this aRemoon during which I became
aware that we had inadvertently omitted the quantities for the conswuction of the temporary
HMAC pavement transition at Sta. I7+84 from the Unit Price Bid Schedule. Ed Bell
Construction was assuming that the temporary asphalt work was a subsidiary item. This
work should have been included in the quantities for Pay Items No. II-12, 11-13 & II-14.
I am recommending that the following Addendure No. 2 be faxed today to those who have
picked-up plans in order to clarify and correct this issue. Please review this information and
let me know how you would like to proceed.
Thanks.
From the desk Of...
MIchael A, Jones, P.E.
A hard copy of this information will be sent in the Principal
mail today. Teague Nail and PerkinS, Inc.