Vista Ridge 1st P-CS 881116 (2) FIL COPY MEI~R~DLlq November 16, 1988 Steve Goram, Director of Public Works Steven M. Morton, Chief Developmental Inspector Vista Ridge / Utility Estimate Revision Steve, as per your request to change estimate to reflect the exterior of the existing 12" D.I.P. along MacArthur to Vista Ridge,· instead of the extension of a 16" from existing 16" @ Parkway Boulevard. The revised cost estimates are as follows: Revised Construction Cost Estimate MacArthur Boulevard 1) 12" D.I.P. 1880 if 2) 12" Gate Valve 6 3) Fire Hydrant 4 4) Street Bore 100 5) Line Lowering 1 ls 6) Bridge Mounting 2 $36.00 $64,800.00 $1200.00 '$7200.00 $1700.00 $6800.00 $160.00 $16,000.00 $20,000.00 $20,000.00 $15,000.00 $30,000.00 TOTAL $144,800.00 Alternate #1 / 2 Aerial Crossing 160 If @ $280.00 Alternate #2 / 2 Creek Lowering 200 if @ $100.00 $74,368.00 $33,200.00 SIV~I/bb