ST9801-CN000728CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Coppell Road Reconstruction Project # S798 -01
CONTRACTOR: Ed Bell Construction
OWNER: City of Coppell
CHANGE ORDER NO.: 3
1 �
DATE: 7/28/00
Item Description Quantity Unit Unit Price Total
Drainage Channel Revisions
ADD:
New 12" Grouted Rock Rip -rap 440 SY 56.55 $24,882.00
Total Revision to Contract Amount $24,882.00
Previous contract amount
Net increase in contract amount
Revised contract amount
Net increase in contract time of completion
Revised Contract time of completion
$2,028,660.31
$24,882.00
$2,053,542.31
7 Calendar Days
292 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord
and satisfaction of all past and future liability originating under any clause in the Contract by reason of this
revision to the Contract.
Agreed
T H E C 1 T Y O F
COPPELL
T
X S 9
A g 1
July 28, 2000
Doug Teter, Vice President
Ed Bell Construction
10605 Harry Hines Blvd.
P.O. Box 540787
Dallas, TX 75354 -0787
Re: Coppell Road Project # ST 98 -01 Change Order #3
Dear Mr. Teter:
Attached are three originals of Change Order #3 for the referenced project. Please
review the change order, sign and return two originals to me. Keep one copy for
your file.
If you have any questions concerning this issue please feel free to contact me at
972/304 -3686.
Sincerely,
?l�n /e� 41
Kenneth M. Griffin, E.
Director of Engineering /Public Works
255 PARKWAY * PO BOX 478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
FAX (214) 352 -3201
ED BELL CONSTRUCTION COMPANY
POST OFFICE BOX 540787 10605 HARRY HINES
DALLAS, TEXAS 75354 -0787 DALLAS, TEXAS 75220
August 12, 2000
Mr. Mike Martin, P.E.
Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019 -4409
Re: Coppell Road Reconstruction
SH 121 to Sandy Lake Road
Coppell Project #: ST 98 -01
Dear Mr. Martin:
TELEPHONE (214) 358 -6581
Enclosed for your review and incorporation into the contract are two executed copies of change
order #3 for the referenced project.
Sincerely,
ell Con t ction Company
Robert D. Weber
Project Engineer
xc: Mr. Kevin C. Young, E.I.T., Freese and Nichols, Inc., 1701 N. Market Street
Sait:, 500 L13 Dalla T x^ '7521M
.� sl, 1 �.' u.0 ^ i t.v L.
o j 4e � �[_ & AQAL O PORTUNITY EMPLOYER