Loading...
CF-Coppell Rd SC-CS010516From: "Ted Armstrong" <tarmstrong@vai-aei.com> To: "Jim Ragsdill (E-mail)" <jragsdil@ci.coppell.tx.us... Date: Wed, May 16, 2001 10:01 AM Subject: Preliminary Bid Results Jim: Here is the preliminary Bid Tabulation. The Iow bidder for the most part is in line with our estimate with one very large exception. Please look at Base Bid Item #6. TUCI was $322,000 over our estimate of $303,000. If calculate the mean for the other bidders, their average would be $304,000. If TUCI brought their bid for item #6 in line with the others by reducing it by $322,000, their total base bid would be $2,860,000 (3.4% over the estimate) and total bid including alternates would be $3,048,797 (0.38% over the estimate). Ted CC: "Sheri Moino (E-mail)" <smoino@ci.coppell.tx. us>