ST9801-CNS000621FAX (214) 352 -3201 TELEPHONE (214) 358 -6581
ED BELL CONSTRUCTION COMPANY
POST OFFICE BOX 540787 10605 HARRY HINES
DALLAS, TEXAS 75354 -0787 DALLAS, TEXAS 75220
June 21, 2000
Mr. Mike Martin, P.E.
Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019 -4409
Re: Coppell Road Reconstruction
SH 121 to Sandy Lake Road
Coppell Project #: ST 98 -01
Dear Mr. Martin:
Enclosed for your review and incorporation into the contract are two executed copies of change
order #2 for the referenced project.
Sincerely,
el Constru n Company
Robert D. Weber
Project Engineer
xc: Mr. Kevin C. Young, E.I.T., Freese and Nichols, Inc., 1701 N. Market Street
Suite 500 LB51, Dallas, Texas 75202
AN EQUAL OPPORTUNITY EMPLOYER
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Coppell Road Reconstruction Project # ST98 -01
CONTRACTOR: Ed Bell Construction
OWNER: City of Coppell
CHANGE ORDER NO.: 2
DATE: /( 6119100
Item Description Quantity Unit Unit Price Total
Drainage Channel Revisions
ADD:
New Reconstruct Channel 1 LS 7,900.00 $7,900.00
Bottom & Slopes
New 12" Grouted Rock Rip -rap 395 SY 38.00 $15,010.00
New Remove 26" Pecan Tree 1 EA 160.00 $160.00
Total R e v ision to Contra Amount $23,070.00
Previous contract amount $2,005,590.31
Net increase in contract amount $23,070.00
Revised contract amount $2,028,660.31
Net increase in contract time of completion 15 Calendar Days
Revised Contract time of completion 285 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord
and satisfaction of all past and future liability originating under any clause in the Contract by reason of this
revision to the Contract.
ineer Date
Agreed to
J z // /
Accep?d by Owner Ddte
0 ck,� PhLIIIPS��ep�� C �t- y ( antr