Warren Addition-CS 940117January 17, 1994
Mr. Eugene Middleton
Winkleman & Associates
12800 Hiilcrest Road Suite 200
Dallas, TX 75230
RE: Warren Crossing
Development Fee Assessment
Dear Mr. Middleton:
Enclosed is a copy of the City of Coppell Development Fee Assessment list, along with a copy of
the Development Fee Calculations for Warren Crossing.
Please provide a check made payable to the City of Coppell in the amount of $8,400.00 and forward
it to Mr. Alan Johnson, Acting Finance Director, along with a copy of the Fee Assessment List.
Please provide our office a copy of the Engineer's Estimate or contract for this project so the
construction inspection fee can be verified.
By providing a copy of your paid receipt to our office, it will help us to verify payment of the
required fees and insure a successful beginning of this project.
We look forward to working with you on this project. If you have any questions, please do not
hesitate to contact me~
Sincerely,
Kenneth M. Griffin, P.E.
City Engineer
cc: Steve Goram, Director of Public Works
Alan Johnson, Acting Finance Director
Greg Jones, Building Official
Doug Stevens, Engineering Technician
CITY OF COPPELL
DEVELOPIVIENT FEES
Date: January 17, 1994
Project: Warren Crossing
TOTAL AMOUNT DUE
ASSESSMENT PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $ 5,200.00 $ 5,200.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $ 800.00 -0-
(100%due at Issuance of Building Permit)
Wastewater Impact Fee $1,800.00 $ 1,800.00
(100% due prior to Council Approval)
Sewer Tap Inspection Fee $ 800.00 -0-
(100%due at Issuance of Building Permi0
Utility Final Inspection Fee $ 400.00 -0-
(100%due at Issuance of Building Permi0
Water Meter Fee (Lots) $178.00 -O-
(100%due at Issuance of Building Permi0
Water Meter Deposit $ 240.00 -0-
(100%due at Issuance of Building Permi0
Street Light Fee *
(lO0%due prior to Acceptance of Project)
Park Fee $ 2,800.00 $1,400.00
(50% due prior to Council Approval)
(50%due prior to Issuance of Building Permit)
TOTAL $12,218.00
TOTAL AMOUNT DUE PRIOR TO $ 8,400.00
COUNCIL APPROVAL
+ Construction Inspection Fee
(2 % of Project Cost due prior to
preconstruction meeting)
* This fee cannot be assessed until after TU Electric submits the lighting plan for the proposed project. Once the plan
is submitted, $292.60 per light will be assessed.
CITY OF COPPF~LL
DEVELOPMENT FEES
Date: January 17, 1994
Project: Warren Crossing
I
TOTAL AMOUNT DUE
ASSESSMENT PRIOR TO
COUNCIL
Water lmI~-'t Fee $ 5,200.00 $ 5,200.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $ 800.00 -0-
(100%due at Issuance of Building Permit)
Wastewater Impact Fee $1,800.00 $1,800.00
(100% due prior to Council Approval)
Sewer Tap Inspection Fee $ 800.00 -0-
(100%due at Issuance of Building Permi0
Utility Final Inspection Fee $ 400.00 -0-
(100%due at Issuance of Building Permi0
Water Metro- Fee (Lots) $178.00 -0-
(100%due at Issuance of Building Permi0
Water Met~ Deposit $ 240.00 -0-
(100%due at Issuance of Building Permit)
Street l.~,ht Fee *
(100%due prior to Acceptance of Project)
Park Fee $ 2,800.00 $1,400.00
(50% due prior to Council Approval)
(50%due prior to Issuance of Building Permit)
TOTAL $12,218.00
TOTAL AMOUNT DUE PRIOR TO $ $t400.00
COUNCIL APPROVAL
+ Construction Inspection Fee
(2~ of Project Cost due prior to
preconstmction meeting)
· This fee cannot be asaessed until after TU Electric submits the lighting plan for the propm2d project. Onc~ the plan
is submi_-_~, $292.60 per light will be assessed.
Water ~eter Fee (Lots)
~ - 5/8" ~ 3/4" Residential Meters @ $22.25 = $~78.00
100% due prior to issuance of building permit.
Water Weter Deposit
8 meters @ $30.00 ea = $240.00
100% due prior to issuance of building permit.
Street Lighting Fee
Shall be assessed and paid prior to final acceptance of project.
Note: This fee cannot be assessed until after TU Electric
submits the lighting plan for the proposed project. Once
plan is submitted $292.60 per light will be assessed.
Park Fee
8 Residential Lots at $350.00 each = $ 2.800.00
Units (Multi family) at $350.0O each = $
For those developments having preliminary plat approval after
October 26, 1993, the following assessment is determined:
Residential lots at $1,285.00 ea = $
Units (Multi-Family) at $1,285.00 ea = $
50% of the amount specified above shall be paid by the Developer;
prior to Council approval of final plat.
50% remaining shall be paid by the Builder at such time as a
building permit is issued.
Please advise the Developer of these fees and due dates.
If yOU have any questions regarding these assessments, please
advise.
HLP / dm
cc: Steven G. Goram
Director of Public Works
STREET SIGN ASSESSMENT
for
The following assessment is being made in'accordance with the City
of Coppell Subdivision Ordinance Appendix A Chapter VIII A. The
following cost of those sign materials required are based on
current pricing which is reviewed on a regular basis.
SIGN UNIT PRICE OUANTITY EXTENDED PRICE
No Parking S53.10 n/a
Speed Limit $63.54
Yield $58.56
Stop $65.12
Street Name $~.60
Stop & Street Combo $96.85
OTHER
No Outlet {$~#; S65.12
No Outlet Blade $11,60
* Cost breakdowns may be obtained from Public Works by written
request.
FEES.HLP/WARREN