ST9801-CS000609 (2)FAX (214) 352-3201 ~'~ /~ TELEPHONE (214) 358-6581
ED BELL CONSTRUCTION COMPANY
POST OFFICE BOX 540787 10605 HARRY HINES
DALLAS, TEXAS 75354-0787 DALLAS, TEXAS 75220
June 9, 2000
Mr. Kent Collins, P.E.
Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019~4409
Re:
Coppell Road Reconstruction
SH 121 to Sandy Lake Road
Coppell Project #: ST 98-01
Dear Mr. Collins:
We have reviewed the proposed revisions (2nd iteration) to the channel and submit the following
prices and quantities for the extra work required by the revisions:
Reconstruct Channel Bottom and Slopes 1 LS
Concrete Tree Well 20 CY
Stone Veneer 225 SF
6t Grouted Rock Rip-rap 502 SY
6" Live Oak (B&B) 1 EA
8" Live Oak (B&B) 1 EA
$7,900.00 per LS
$1,140.00 per CY
$24.50 per SF
$38.00 per SY
$1,310.00 per EA
$1,950.00 per EA
$7,900.00
$22,800.00
$5,512.50
$19,076.00
$1,310.00
$2,210.00
The quantities for the concrete tree well and the stone veneer are based upon the revised channel
plan sheet issued by Freese Nichols, Inc. Our additional time requirement to complete the work
associated with option 1 is fifteen (15) calendar days and for option 2 is twenty one (21) calendar
days.
If you have any questions regarding this information, don't hesitate to contact our office.
Sincerely,
RobZ~'~'. W~ber
Project Engineer
Company
XC:
Mr. Kevin C. Young, E.I.T., Freese and Nichols, Inc., 1701 N. Market Street
Suite 500 LB51, Dallas, Texas 75202