ST1501A-CS180406
Priscilla Martinez
From:Marcus Marion
Sent:Friday, April 06, 2018 3:28 PM
To:Priscilla Martinez
Subject:Freeport - Pay Estimates
This is a correspondence for Freeport PKWY
From: Eric Giebelhaus \[mailto:Eric.Giebelhaus@strlco.com\]
Sent: Friday, April 6, 2018 10:01 AM
To: Kent Collins <KCollins@coppelltx.gov>
Cc: George Marshall <GMarshall@coppelltx.gov>; Marcus Marion <MMarion@coppelltx.gov>
Subject: RE: Freeport - Pay Estimates
The excel file is exactly what I was looking for.
From: Kent Collins <KCollins@coppelltx.gov>
Sent: Friday, April 06, 2018 10:00 AM
To: Eric Giebelhaus <Eric.Giebelhaus@strlco.com>
Cc: George Marshall <GMarshall@coppelltx.gov>; Marcus Marion <MMarion@coppelltx.gov>
Subject: RE: Freeport - Pay Estimates
Eric, here are some of the project forms that were included in the project specs. Let me know of any questions.
Thanks,
Kent Collins, P.E.
Assistant Director of Public Works - Engineering
972-304-7019
From: Eric Giebelhaus \[mailto:Eric.Giebelhaus@strlco.com\]
Sent: Friday, April 6, 2018 9:34 AM
To: Kent Collins <KCollins@coppelltx.gov>
Cc: George Marshall <GMarshall@coppelltx.gov>; Marcus Marion <MMarion@coppelltx.gov>
Subject: Freeport - Pay Estimates
Kent,
Does Coppell have a specific spreadsheet you want us to use in creating the pay estimates or should I just provide
something?
Thanks,
Eric Giebelhaus
Project Manager– North Texas Division
Texas Sterling Construction Co.
| 1441 Airport Freeway Suite 350, Euless, Texas 76040 |
| 469.346.8085 Cell |
1
2