From:Marcus Marion
Sent:Wednesday, April 25, 2018 8:24 AM
To:Priscilla Martinez
Subject:FW: Freeport Parkway - Proposed Traffic Control Changes
This is a correspondence for the Freeport project
From: Kent Collins
Sent: Wednesday, April 25, 2018 8:18 AM
To: Darryl Zbranek <dzbranek@coppelltx.gov>; Marcus Marion <MMarion@coppelltx.gov>; George Marshall
<GMarshall@coppelltx.gov>; Michael Garza <MGarza@coppelltx.gov>
Subject: FW: Freeport Parkway - Proposed Traffic Control Changes
FYI, the bridge over Grapevine Creek did not respond well to Texas Sterling’s attempt to remove the sidewalk from the
west edge. Below is a string of emails with Volk regarding assessment by the structural engineer.
Thanks,
Kent
From: Kent Collins
Sent: Wednesday, April 25, 2018 8:16 AM
To: 'Jay Volk' <jay@jvolkconsulting.com>
Cc: Claudio Segovia <claudio@jvolkconsulting.com>
Subject: RE: Freeport Parkway - Proposed Traffic Control Changes
Jay, I think the contractor understands and appreciates that their method caused the damage and they seem prepared
to deal with it. They need direction from our designers and the City. My request for your team is to:
1. As quickly as possible, assess whether traffic has to stay off of the outside lane, or if there is an option to plate
over the damaged stretch (or some other short-term solution)
2. Within a week (as A&F suggests) provide an analysis of options for the detour of both north and southbound
traffic to the western lanes. Given the difficulty in removing the sidewalk, they have suggested leveling up to
curbline with asphalt, but there may be a better option
I have been on-site and the area of damage if limited, and appears to be isolated to underneath the sidewalk. Given the
limited scope of damage, it seems that some fairly quick-to-implement options may be available. If we need to meet on-
site, let me know.
Thanks,
Kent
From: Jay Volk \[mailto:jay@jvolkconsulting.com\]
Sent: Tuesday, April 24, 2018 10:50 PM
To: Kent Collins <KCollins@coppelltx.gov>
Cc: Claudio Segovia <claudio@jvolkconsulting.com>
Subject: Re: Freeport Parkway - Proposed Traffic Control Changes
1
Kent, with respect, the contractors actions in taking a jackhammer to the bridge superstructure were reckless at
best. We will do what we can to resolve the matter quickly, but a resolution tomorrow is not realistic.
Sent from my iPhone
On Apr 24, 2018, at 7:31 PM, Kent Collins <KCollins@coppelltx.gov> wrote:
Jay/Claudio, we need a recommendation regarding handling traffic tomorrow, not next week. The
detour option evaluation can wait, but do we really need the one lane taken down or can we do
something to remediate quickly?
Kent M. Collins, P.E.
Director of Public Works
972.304.7019
On Apr 24, 2018, at 4:56 PM, Claudio Segovia <claudio@jvolkconsulting.com> wrote:
Kent and Darryl,
We ran this by Aguirre & Fields, please see their response below:
Based on the photos attached, it’s clear that the bridge deck has been significantly damaged and the
flexural capacity significantly reduced. Our first recommendation is to barricade the lane nearest to the
damage immediately. To evaluate if their proposal for the HMAC level-up is feasible, we’ll need time to
perform an analysis of the existing bridge deck and girders. We’ll get back to you early next week with
our recommendations.
I’ve cc’d Geoff and Eugene in case there are any other questions/comments on this.
Thanks.
Claudio Segovia | Engineer
J. VOLK consulting
830 Central Parkway East | Suite 300 | Plano | TX 75074
972-201-3100 (office)
972-201-3102 (direct)
972-322-7026 (mobile)
972-201-3099 (fax)
www.jvolkconsulting.com
Service with Integrity, Initiative and Innovation
From: Eric Giebelhaus <Eric.Giebelhaus@strlco.com>
Sent: Tuesday, April 24, 2018 3:08 PM
To: Kent Collins <KCollins@coppelltx.gov>
Cc: Marcus Marion <MMarion@coppelltx.gov>; Darryl Zbranek <dzbranek@coppelltx.gov>; Joe Soto
<Joe.Soto@strlco.com>; Jimmy Reed <Jimmy.Reed@strlco.com>; Jay Volk <jay@jvolkconsulting.com>;
Claudio Segovia <claudio@jvolkconsulting.com>
Subject: Freeport Parkway - Proposed Traffic Control Changes
Kent,
2
Please review the attached proposal. I would like to meet to discuss this once you have had a chance to
consider it.
Thanks,
Eric Giebelhaus
Project Manager– North Texas Division
Texas Sterling Construction Co.
| 1441 Airport Freeway Suite 350, Euless, Texas 76040 |
| 469.346.8085 Cell |