ST1501A-CS180517
Priscilla Martinez
From:Marcus Marion
Sent:Thursday, May 17, 2018 7:43 AM
To:Priscilla Martinez
Subject:Freeport Submittal 11.0 Consultant Review
This is a correspondence for Freeport about the panels
From: Darryl Zbranek
Sent: Wednesday, May 16, 2018 10:18 AM
To: FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Subject: FW: Freeport Submittal 11.0 Consultant Review
FYI
From: Eric Giebelhaus \[mailto:Eric.Giebelhaus@strlco.com\]
Sent: Wednesday, May 16, 2018 10:15 AM
To: Darryl Zbranek <dzbranek@coppelltx.gov>
Cc: Marcus Marion <MMarion@coppelltx.gov>
Subject: FW: Freeport Submittal 11.0 Consultant Review
Darryle,
Bexar is ready to start casting as soon as we have the details for the inspection worked out. Please look at the below
email for what we need to get it scheduled and started.
Thanks,
Eric Giebelhaus
Project Manager– North Texas Division
Texas Sterling Construction Co.
| 1441 Airport Freeway Suite 350, Euless, Texas 76040 |
| 469.346.8085 Cell |
From: Ricardo Rocha <ricardo.rocha@bexarconcrete.com>
Sent: Wednesday, May 16, 2018 10:04 AM
To: Eric Giebelhaus <Eric.Giebelhaus@strlco.com>
Subject: RE: Freeport Submittal 11.0 Consultant Review
1
As mentioned before we cannot cast on this job until we have in writing who the inspector will be and their
information. That includes scheduling the panels to be cast. Once we have that information we can proceed to set a
schedule to cast, and our production team will contact your inspector with the date and time of casting so that they may
be present.
I hope this answers any questions you may have about proceeding with the casting if not please feel free to contact
myself or Ralph Morales here at the office.
Thanks,
Ricardo Rocha
From: Eric Giebelhaus \[mailto:Eric.Giebelhaus@strlco.com\]
Sent: Wednesday, May 16, 2018 8:58 AM
To: Ricardo Rocha <ricardo.rocha@bexarconcrete.com>
Subject: RE: Freeport Submittal 11.0 Consultant Review
When will you be casting the panels, specific days?
From: Ricardo Rocha <ricardo.rocha@bexarconcrete.com>
Sent: Friday, May 11, 2018 2:53 PM
To: Eric Giebelhaus <Eric.Giebelhaus@strlco.com>
Subject: RE: Freeport Submittal 11.0 Consultant Review
Eric,
Can you please include Ralph Morales in your response I will be leaving shortly for the weekend and he will be
here til 5:00 . ralph.moralez@bexarconcrete.com
From: Eric Giebelhaus \[mailto:Eric.Giebelhaus@strlco.com\]
Sent: Friday, May 11, 2018 2:17 PM
To: Ricardo Rocha <ricardo.rocha@bexarconcrete.com>
Subject: RE: Freeport Submittal 11.0 Consultant Review
Let me know when you will be casting them so the City can decide how they want to do the inspection.
From: Ricardo Rocha <ricardo.rocha@bexarconcrete.com>
Sent: Friday, May 11, 2018 2:10 PM
To: Eric Giebelhaus <Eric.Giebelhaus@strlco.com>
Subject: RE: Freeport Submittal 11.0 Consultant Review
Eric,
We received the Approved Shop Drawings Thank You very much for that. We would now like to know who you want
to Inspect the Panels. Note: Bexar Concrete Works I, Ltd. has qualified personnel to do an in-house inspection and can
provide
you with copies of the documents for your use, let me know how you want to proceed.
Thanks,
Ricardo Rocha
From: Eric Giebelhaus \[mailto:Eric.Giebelhaus@strlco.com\]
Sent: Friday, May 11, 2018 1:38 PM
To: Ricardo Rocha <ricardo.rocha@bexarconcrete.com>
2
Cc: Ralph Moralez <ralph.moralez@bexarconcrete.com>; Joe Soto <Joe.Soto@strlco.com>; Jimmy Reed
<Jimmy.Reed@strlco.com>
Subject: FW: Freeport Submittal 11.0 Consultant Review
See attached. They are approved as noted and the note does not apply to what you are making.
Thanks,
Eric Giebelhaus
Project Manager– North Texas Division
Texas Sterling Construction Co.
| 1441 Airport Freeway Suite 350, Euless, Texas 76040 |
| 469.346.8085 Cell |
From: Kent Collins <KCollins@coppelltx.gov>
Sent: Friday, May 11, 2018 11:22 AM
To: Eric Giebelhaus <Eric.Giebelhaus@strlco.com>
Cc: Claudio Segovia <claudio@jvolkconsulting.com>; Jay Volk <jay@jvolkconsulting.com>; FreeportProjectST1501
<freeportprojectst1501@coppelltx.gov>
Subject: FW: Freeport Submittal 11.0 Consultant Review
Eric, see attached response to Submittal 11. We will discuss inspection and get back to you on that question.
Thanks,
Kent
From: Claudio Segovia \[mailto:claudio@jvolkconsulting.com\]
Sent: Monday, April 23, 2018 8:02 AM
To: FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Cc: Jay Volk <jay@jvolkconsulting.com>
Subject: Freeport Submittal 11.0 Consultant Review
Good morning,
A&F has completed their review of TSC’s Submittal 11.0; it looks like there’s only one minor comment. See attached
reviewed submittal and updated submittal log for reference.
Regarding the inspection of the panel fabrication, A&F has no specific requirement for who completes the inspection
and defers to the City’s inspection requirements, but asks that the inspection documents get forwarded to them when
complete.
Let us know if you have any questions or need anything else.
3
Thank you!
Claudio Segovia | Engineer
J. VOLK consulting
830 Central Parkway East | Suite 300 | Plano | TX 75074
972-201-3100 (office)
972-201-3102 (direct)
972-322-7026 (mobile)
972-201-3099 (fax)
www.jvolkconsulting.com
Service with Integrity, Initiative and Innovation
You're receiving this message because you're a member of the FreeportProjectST1501 group. If you don't want to receive
any messages or events from this group, stop following it in your inbox.
View group email | View group files
4