Waterside P3-CS 950816 COPPELL UTILITIES
DATE: August 16, 1995 ~J
TO: Larry Davis, Construction Inspector
FROM: Howard Pafford, Utilities Superintenden
RE: Final Walk-Through for Waterside Estates Phase III
Utilities personnel performed a walk-thru on the above referenced
project this morning and the following items were found to be
deficient;
* Lot 14 Blk. H-Lot cleanout missing.
* Inflow coming in manhole at Mariners Ct. and Cove
Dr. .
* Lot 11Blk. G-Water service leak.
* Lot 5 Blk. H-Replace meter setter.
* Install brass elbows on all 2" blowoffs.
* Main line valve missing at Parkway and MacArthur.
* Lot 8 Blk.G-Repour concrete pad for lot cleanout.
Please ensure that each of these items are corrected prior to
final acceptance of this project.
HLP/hp