Gateway BP(1.4)-LR180514MASONRY OBSERVATIONS REPORT Report Number:94171346.0242 Service Date:05/14/18 8901 Carpenter Fwy, Ste 100 Report Date:05/21/18 Dallas, TX 75247-4547 214-630-1010 Reg No: F-3272 Client Project Haverty Furniture Co Inc Haverty's Warehouse Expansion Attn: Glenn Boone 770 Gateway Blvd 780 Johnson Ferry Rd NE Ste 800 Coppell, TX 75019 Atlanta, GA 30342 Project Number: 94171346 Services: Masonry observation. Terracon Rep.: Scooter Day Reported To: Contractor: Report Distribution: (1) Haverty Furniture Co Inc, Glenn Boone (1) City of Coppell TX, Marcus Marion (1) Kajima Building & Design Group Inc., Craig Farwick (1) Kajima Building & Design Group Inc., Juan Hernandez Reviewed By:____________________________________ (1) Kent Companies, George Sellers (1) Macgregor Assoc Architects, Muhammed Dikko Joel Warriner, P.E. Senior Project Manager The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. AF0006, 10-16-13, Rev.3 Page 1 of 1 Services Requested By:Juan Hernandez W/ KBD Group Masonry Contractor:C & B Masonry Location of Observed Activity:G.3/8-10 Courses 13-18, D-C.8/8.8, Courses 13-15, C.8/8.8-10, Courses 13-15, G.3/8-10, Courses 18-24, G.3/8-10, Courses18-24 Masonry Type:CMU Block Size:8-inch Block Type:Normal Activities Observed:Masonry, mortar, grout and reinforcing steel Ambient Temperature:The temperature during today's masonry activities was observed to be 83 degrees Fahrenheit. The ambient temperature over the last 24 hours ranged from 70 to 90 degrees Fahrenheit. Mortar:Type N mortar used in the masonry construction was observed to have been mixed in accordance with project specifications. Grout:Approximately 9 cubic yards of 3000-psi grout supplied by Contractor (Mix ID: Spec Mix) was placed using low lift methods Weather Protection:Weather protection consisted of Working inside of warehouse. Drawings Referenced:S-203/Slab Foundation, S4-00/General Notes, dated 05/01/17 Summary:Today's masonry activities were observed to have been completed in general accordance with project documents. Results were reported to Juan Hernandez w/KBD Group at the completion of today's activities. Additional Comments:Installed metal embeds in compliance with blueprints. General cleanup of entire work area. Moving scaffolds to clean up work area.