ST0502B-CS180525 (2) City of Coppell Project No. ST15-01A Freeport Parkway Baseline Primavera P6 Schedule Narrative As of Data Date: May 25, 2018 6activitiesadded from04/25version. Coppellletterdated04/26notestimecharges beginning04/26andcontractexpirationon10/28. 550daysusedforallschedules.CheckSCand contractexpirationdateswith04/26timecharges start. Criticalitem.Confirm whatthestatusofthisis. Whywastheschedulechanged?Changes toschedulearetypicallynotdonewith monthlyupdates.RefertoSection1.7ofthe SpecBook(requirement#2). 1723 - Freeport Activity IDActivity NameOriginalRemainingTotal FloatStartFinish Time Calendar chargesstartedon 20182019 DurationDuration c AprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNov 04/26,butappearstobe 343312009-Apr-18 04-Oct-191723 - Freepor 1723 1723 - Freeport-countedfromthisactivity. A A1000Project Start0009-Apr-187 DayProject Start SeeA1670. A1320Duration530498009-Apr-1804-Oct-197 Day A1530Bridge ROW Issue0009-Apr-1825-Apr-18 7 Day A1600Project Time Charges523498009-Apr-1804-Oct-197 Day A1330Milestone 1190167626-Apr-1807-Nov-187 Day A1670Start Time Charges0026-Apr-187 DayStart Time Charges A1340Milestone 212512515908-Nov-1813-Mar-197 Day A1350Milestone 31461461315-Mar-1908-Aug-197 Day A1020Project Finish00004-Oct-197 DayProject Finish 582432309-Apr-1828-Jun-185 DayStage 1 StagStage 1e 9009-Apr-1827-Apr-18 5 DayWater WaterWater A165Sawcut for Removals - Water Line & Detour3009-Apr-1811-Apr-18 5 Day A155Water Line 45+80 to 48+256012-Apr-1817-Apr-18 5 Day A138Crossing @ 44+703018-Apr-1818-Apr-18 5 Day Appearstobeanew A137Crossing @36+164019-Apr-1825-Apr-18 5 Day scheduleactivitysince A136Crossing @ 28+263026-Apr-1827-Apr-18 5 Day 04/09version.Notingthe 582432312-Apr-1828-Jun-185 DayTCP Setup Stage 2 TCP TCP Setup Stage 2S potentialdelaycausedby A166Sawcut for Removals - Bridge Sidewalk1012-Apr-1820-Apr-18 5 Day theRRcrossingarm. A105Remove Sidewalk SB5023-Apr-1815-May-185 Day A260Railroad Crossing Arm Delay1524426-Apr-1828-Jun-185 DayRailroad Crossing Arm Delay A107Remove Bridge Median1015-May-1815-May-185 Day A109Removals - Detours1016-May-1816-May-185 Day A110Install Stage Detours3016-May-1818-May-185 Day A108Set & Pin PCTB - Demo Edge2021-May-1821-May-185 Day A106Set PCTB - Center Stripe112225-May-1825-May-185 DaySet PCTB - Center Stripe A161Railroad Install Temp Crossing Arms00428-Jun-185 DayRailroad Install Temp Crossing Arms 002325-May-1825-May-185 DayStorm Drain StorStorm Drainm A139Storm Drain Rehab @ 17+23002325-May-1825-May-185 DayStorm Drain Rehab @ 17+23 11010620621-May-1807-Nov-18Stage 2 - NB Dividend to Bethel StagStage 2 - NB Dividend to Bethele A1620Switch Traffic to Stage 21021-May-1821-May-185 Day A1630Remove Concrete Pavement & Sidewalk - South of RR882225-May-1807-Jun-185 DayRemove Concrete Pavement & Sidewalk - South of RR A2420Complete Pavement Removal North of RR33429-Jun-1803-Jul-185 DayComplete Pavement Removal North of RR 223608-Jun-1811-Jun-185 DaySanitary Sewer SanitSanitary Sewera A149Install SS @ 26+56 w/ Temp Connection223608-Jun-1811-Jun-185 DayInstall SS @ 26+56 w/ Temp Connection 7575411-Jun-1826-Sep-185 DayStorm Drain StorStorm Drainm A150Storm Drain Impovements NB333611-Jun-1814-Jun-185 DayStorm Drain Impovements NB A186Complete Inlet Tops after Paving88417-Sep-1826-Sep-185 DayComplete Inlet Tops after Paving 636028722-May-1820-Aug-185 DayWater Line WateWater Liner A140Steel Casing 23+81 to 26+1616022-May-1823-May-185 Day A144Install 16" Main in Bore3024-May-1824-May-185 Day Remaining Level of EffortActual WorkCritical Remaining Work Page 1 of 7 Run Date 25-May-18 Actual Level of EffortRemaining WorkMilestone Data Date 25-May-18 Activity IDActivity NameOriginalRemainingTotal FloatStartFinishCalendar20182019 DurationDuration c AprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNov A143Install 16" Main 27+13 to 36+1688425-May-1806-Jun-185 DayInstall 16" Main 27+13 to 36+16 A164Install 16" Main 36+16 to 45+8077407-Jun-1815-Jun-185 DayInstall 16" Main 36+16 to 45+80 A142Install 16" Main 19+00 to 23+1044418-Jun-1821-Jun-185 DayInstall 16" Main 19+00 to 23+10 A145Install Hydrants, Crossings, etc 19+00 to45+8088422-Jun-1803-Jul-185 DayInstall Hydrants, Crossings, etc 19+00 to45+80 A141Install Hydrants, Crossing, etc Divident to 19+0066405-Jul-1812-Jul-185 DayInstall Hydrants, Crossing, etc Divident to 19+00 A146Connect to Existing @ 19+0811905-Jul-1805-Jul-185 DayConnect to Existing @ 19+08 A147Finish Connecting Services22413-Jul-1817-Jul-185 DayFinish Connecting Services A148Grout Existing Water Line1010417-Jul-1831-Jul-185 DayGrout Existing Water Line A169Install 20" Waterline on Southwestern111128731-Jul-1815-Aug-185 DayInstall 20" Waterline on Southwestern A170Replace Pavement on Southwestern3328715-Aug-1820-Aug-185 DayReplace Pavement on Southwestern 65654224-May-1806-Sep-18Bridge BridgeBridge A103Demo Existing Bridge544824-May-1801-Jun-185 DayDemo Existing Bridge A104Grading Proposed Bridge114804-Jun-1804-Jun-185 DayGrading Proposed Bridge A261Drill Sub Mobilization10104805-Jun-1818-Jun-185 DayDrill Sub Mobilization A111Drill Shafts444819-Jun-1822-Jun-185 DayDrill Shafts A118Drill Shaft Cure337223-Jun-1826-Jun-187 DayDrill Shaft Cure A112Bent 2 Columns224825-Jun-1826-Jun-185 DayBent 2 Columns A113Bent 3 Columns224826-Jun-1828-Jun-185 DayBent 3 Columns A119Bent 2 Column Cure337626-Jun-1829-Jun-187 DayBent 2 Column Cure A114Abut 1 Cap224828-Jun-1802-Jul-185 DayAbut 1 Cap A120Bent 3 Column Cure337828-Jun-1801-Jul-187 DayBent 3 Column Cure A115Abut 4 Cap224802-Jul-1805-Jul-185 DayAbut 4 Cap A121Abut 1 Cap Cure338202-Jul-1805-Jul-187 DayAbut 1 Cap Cure A116Bent 2 Cap224806-Jul-1810-Jul-185 DayBent 2 Cap A122Abut 4 Cap Cure337806-Jul-1809-Jul-187 DayAbut 4 Cap Cure A168Install CTB @ Abutments337106-Jul-1811-Jul-185 DayInstall CTB @ Abutments A117Bent 3 Cap224810-Jul-1812-Jul-185 DayBent 3 Cap A123Bent 2 Cap Cure337410-Jul-1813-Jul-187 DayBent 2 Cap Cure A124Bent 3 Cap Cure337112-Jul-1815-Jul-187 DayBent 3 Cap Cure A151Install Riprap Under New Bridge334812-Jul-1817-Jul-185 DayInstall Riprap Under New Bridge A125Set Beams114818-Jul-1818-Jul-185 DaySet Beams A126Set Overhang11114819-Jul-1803-Aug-185 DaySet Overhang A127Install Precast Panels & PMD444803-Aug-1809-Aug-185 DayInstall Precast Panels & PMD A128Tie Deck Steel224809-Aug-1810-Aug-185 DayTie Deck Steel A129Pour Deck114810-Aug-1813-Aug-185 DayPour Deck A130Cure Deck886913-Aug-1821-Aug-187 DayCure Deck A131Install Ped Rail on Deck w/ Conduit10104821-Aug-1806-Sep-185 DayInstall Ped Rail on Deck w/ Conduit 9797308-Jun-1807-Nov-18Roadway RoadRoadway A196Retaining Wall 45+51 to 48+2411116708-Jun-1825-Jun-185 DayRetaining Wall 45+51 to 48+24 A197Retaining Wall 63+82 to 65+15666725-Jun-1802-Jul-185 DayRetaining Wall 63+82 to 65+15 A171Balance Subgrade 1+55 to 36+0099405-Jul-1817-Jul-185 DayBalance Subgrade 1+55 to 36+00 A239Balance Subgrade 36+00 to 67+6899418-Jul-1830-Jul-185 DayBalance Subgrade 36+00 to 67+68 A172Fine Grade Subgrade66431-Jul-1807-Aug-185 DayFine Grade Subgrade A1734" HMAC Ty B88408-Aug-1817-Aug-185 Day4" HMAC Ty B A174Tie Steel - Paving Pass 155420-Aug-1824-Aug-185 DayTie Steel - Paving Pass 1 A180Paving - Pass 133424-Aug-1829-Aug-185 DayPaving - Pass 1 A175Tie Steel - Paving Pass 255429-Aug-1806-Sep-185 DayTie Steel - Paving Pass 2 A187Cure Paving - Pass 1331129-Aug-1801-Sep-187 DayCure Paving - Pass 1 Remaining Level of EffortActual WorkCritical Remaining Work Page 2 of 7 Run Date 25-May-18 Actual Level of EffortRemaining WorkMilestone Data Date 25-May-18 Activity IDActivity NameOriginalRemainingTotal FloatStartFinishCalendar20182019 DurationDuration c AprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNov A178Tie Steel - 2nd Half Cross Streets223603-Sep-1805-Sep-185 DayTie Steel - 2nd Half Cross Streets A176Tie Steel - Turn Lanes (13 turn lanes)221206-Sep-1811-Sep-185 DayTie Steel - Turn Lanes (13 turn lanes) A181Paving - Pass 233406-Sep-1811-Sep-185 DayPaving - Pass 2 A182Pave - Turn Lanes221211-Sep-1813-Sep-185 DayPave - Turn Lanes A188Cure Paving - Pass 233611-Sep-1814-Sep-187 DayCure Paving - Pass 2 A189Cure - Turn Lanes331613-Sep-1816-Sep-187 DayCure - Turn Lanes A177Tie Steel - 1st Half Cross Streets222117-Sep-1819-Sep-185 DayTie Steel - 1st Half Cross Streets A183Pave - 1st Half Cross Streets222119-Sep-1821-Sep-185 DayPave - 1st Half Cross Streets A190Cure - 1st Half Intersections333121-Sep-1824-Sep-187 DayCure - 1st Half Intersections A184Pave - 2nd Half Cross Streets222325-Sep-1827-Sep-185 DayPave - 2nd Half Cross Streets A195Backfill Pavement33427-Sep-1801-Oct-185 DayBackfill Pavement A191Cure 2nd Half Intersections333327-Sep-1830-Sep-187 DayCure 2nd Half Intersections A193Install Colored Stamped Concrete552727-Sep-1804-Oct-185 DayInstall Colored Stamped Concrete A179Tie Steel - Driveways222401-Oct-1803-Oct-185 DayTie Steel - Driveways A198Grade for Sidewalk1212402-Oct-1817-Oct-185 DayGrade for Sidewalk A185Pave - Driveways332403-Oct-1808-Oct-185 DayPave - Driveways A194Cure Stamped Concrete333704-Oct-1807-Oct-187 DayCure Stamped Concrete A192Cure - Driveways333308-Oct-1811-Oct-187 DayCure - Driveways A199Pave Sidewalk & Trail88418-Oct-1829-Oct-185 DayPave Sidewalk & Trail A200Backfill Sidewalk & Trail22430-Oct-1831-Oct-185 DayBackfill Sidewalk & Trail A201Grass & Landscape Outside55431-Oct-1807-Nov-185 DayGrass & Landscape Outside 110110928-May-1831-Oct-185 DayRailroad RailrRailroado A156Railroad Installed Concrete Panels NB1111428-May-1828-May-185 DayRailroad Installed Concrete Panels NB A157Railroad Installed Ped Crossing Arms NB1111628-May-1828-May-185 DayRailroad Installed Ped Crossing Arms NB A158Connect Pavement NB223817-Sep-1819-Sep-185 DayConnect Pavement NB A159Build Sidewalk at RR Crossing NB22930-Oct-1831-Oct-185 DayBuild Sidewalk at RR Crossing NB 441117-Sep-1820-Sep-185 DayTraffic Signals TraffiTraffic Signals A152Signal Drill Shafts at Southwestern NB221117-Sep-1818-Sep-185 DaySignal Drill Shafts at Southwestern NB A154Install Conduit from NB Corners w/ Pull Boxes221118-Sep-1820-Sep-185 DayInstall Conduit from NB Corners w/ Pull Boxes 59591407-Nov-1817-Feb-19Stage 3A - SB Dividend to Fritz StagStage 3A - SB Dividend to Fritze A3840Switch Traffic to Stage 3A11407-Nov-1808-Nov-185 DaySwitch Traffic to Stage 3A A3890Remove Concrete Pavement22908-Nov-1812-Nov-185 DayRemove Concrete Pavement 994713-Nov-1823-Nov-185 DayWater WaterWater A228Remove & Replace Existing Hydrants334713-Nov-1815-Nov-185 DayRemove & Replace Existing Hydrants A229Complete Crossing @ 13+60224716-Nov-1819-Nov-185 DayComplete Crossing @ 13+60 A230Complete Crossing @ 16+05224720-Nov-1821-Nov-185 DayComplete Crossing @ 16+05 A231Complete Crossing @ 22+68224722-Nov-1823-Nov-185 DayComplete Crossing @ 22+68 36361426-Nov-1821-Jan-195 DayStorm Drain StorStorm Drainm A240Storm Drain Impovements SB224726-Nov-1827-Nov-185 DayStorm Drain Impovements SB A241Complete Inlet Tops after Paving221417-Jan-1921-Jan-195 DayComplete Inlet Tops after Paving 2626413-Nov-1821-Dec-185 DaySanitary Sewer SanitSanitary Sewera A236Install SS 32+33 to 23+8988913-Nov-1822-Nov-185 DayInstall SS 32+33 to 23+89 A232Drill Shafts for Aerial SS Crossing33415-Nov-1820-Nov-185 DayDrill Shafts for Aerial SS Crossing A233Columns for Aerial SS Crossing33420-Nov-1823-Nov-185 DayColumns for Aerial SS Crossing A234Caps for Aerial SS Crossing22423-Nov-1827-Nov-185 DayCaps for Aerial SS Crossing A235Casing for Aerial SS Crossing33427-Nov-1804-Dec-185 DayCasing for Aerial SS Crossing A237Install SS 23+89 to 17+3988404-Dec-1814-Dec-185 DayInstall SS 23+89 to 17+39 Remaining Level of EffortActual WorkCritical Remaining Work Page 3 of 7 Run Date 25-May-18 Actual Level of EffortRemaining WorkMilestone Data Date 25-May-18 Activity IDActivity NameOriginalRemainingTotal FloatStartFinishCalendar20182019 DurationDuration c AprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNov A238Rehab Existing SS Manholes55414-Dec-1821-Dec-185 DayRehab Existing SS Manholes 54541808-Nov-1808-Feb-19Bridge BridgeBridge A203Demo Existing Bridge55408-Nov-1815-Nov-185 DayDemo Existing Bridge A204Grading Proposed Bridge112215-Nov-1816-Nov-185 DayGrading Proposed Bridge A205Drill Shafts552216-Nov-1823-Nov-185 DayDrill Shafts A206Bent 2 Columns222223-Nov-1826-Nov-185 DayBent 2 Columns A220Drill Shaft Cure333823-Nov-1826-Nov-187 DayDrill Shaft Cure A207Bent 3 Columns222227-Nov-1828-Nov-185 DayBent 3 Columns A221Bent 2 Column Cure334127-Nov-1830-Nov-187 DayBent 2 Column Cure A208Abut 1 Cap222228-Nov-1804-Dec-185 DayAbut 1 Cap A222Bent 3 Column Cure334428-Nov-1801-Dec-187 DayBent 3 Column Cure A209Abut 4 Cap222205-Dec-1807-Dec-185 DayAbut 4 Cap A223Abut 1 Cap Cure334605-Dec-1808-Dec-187 DayAbut 1 Cap Cure A210Bent 2 Cap222207-Dec-1811-Dec-185 DayBent 2 Cap A224Abut 4 Cap Cure334407-Dec-1810-Dec-187 DayAbut 4 Cap Cure A219Install CTB @ Abutments334107-Dec-1812-Dec-185 DayInstall CTB @ Abutments A211Bent 3 Cap222211-Dec-1814-Dec-185 DayBent 3 Cap A225Bent 2 Cap Cure333911-Dec-1814-Dec-187 DayBent 2 Cap Cure A226Bent 3 Cap Cure333714-Dec-1817-Dec-187 DayBent 3 Cap Cure A218Install Riprap Under New Bridge442214-Dec-1820-Dec-185 DayInstall Riprap Under New Bridge A212Set Beams112220-Dec-1821-Dec-185 DaySet Beams A213Set Overhang662221-Dec-1831-Dec-185 DaySet Overhang A214Install Precast Panels & PMD552231-Dec-1808-Jan-195 DayInstall Precast Panels & PMD A215Tie Deck Steel222208-Jan-1910-Jan-195 DayTie Deck Steel A216Pour Deck112210-Jan-1911-Jan-195 DayPour Deck A227Cure Deck883211-Jan-1919-Jan-197 DayCure Deck A217Install Ped Rail on Deck w/ Conduit10102221-Jan-1904-Feb-195 DayInstall Ped Rail on Deck w/ Conduit A202Form & Pour West Sidewalk & Median442204-Feb-1908-Feb-195 DayForm & Pour West Sidewalk & Median 5757313-Nov-1817-Feb-19Roadway RoadRoadway A243Balance Subgrade662513-Nov-1821-Nov-185 DayBalance Subgrade A244Fine Grade Subgrade22521-Dec-1824-Dec-185 DayFine Grade Subgrade A2454" HMAC Ty B33426-Dec-1831-Dec-185 Day4" HMAC Ty B A246Tie Steel - Paving Pass 122431-Dec-1803-Jan-195 DayTie Steel - Paving Pass 1 A252Paving - Pass 122403-Jan-1907-Jan-195 DayPaving - Pass 1 A247Tie Steel - Paving Pass 222407-Jan-1908-Jan-195 DayTie Steel - Paving Pass 2 A266Cure Paving - Pass 133507-Jan-1910-Jan-197 DayCure Paving - Pass 1 A248Tie Steel - Turn Lanes22409-Jan-1911-Jan-195 DayTie Steel - Turn Lanes A253Paving - Pass 222310-Jan-1914-Jan-195 DayPaving - Pass 2 A254Pave - Turn Lanes22314-Jan-1916-Jan-195 DayPave - Turn Lanes A267Cure Paving - Pass 2332014-Jan-1917-Jan-197 DayCure Paving - Pass 2 A268Cure - Turn Lanes33416-Jan-1919-Jan-197 DayCure - Turn Lanes A259Backfill Pavement221616-Jan-1917-Jan-195 DayBackfill Pavement A249Tie Steel - 1st Half Cross Streets11221-Jan-1921-Jan-195 DayTie Steel - 1st Half Cross Streets A262Grade for Sidewalk441421-Jan-1925-Jan-195 DayGrade for Sidewalk A255Pave - 1st Half Cross Streets22222-Jan-1923-Jan-195 DayPave - 1st Half Cross Streets A269Cure - 1st Half Intersections33324-Jan-1927-Jan-197 DayCure - 1st Half Intersections A263Pave Sidewalk221425-Jan-1928-Jan-195 DayPave Sidewalk A250Tie Steel - 2nd Half Cross Streets11228-Jan-1928-Jan-195 DayTie Steel - 2nd Half Cross Streets Remaining Level of EffortActual WorkCritical Remaining Work Page 4 of 7 Run Date 25-May-18 Actual Level of EffortRemaining WorkMilestone Data Date 25-May-18 Activity IDActivity NameOriginalRemainingTotal FloatStartFinishCalendar20182019 DurationDuration c AprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNov A251Tie Steel - Driveways221129-Jan-1930-Jan-195 DayTie Steel - Driveways A256Pave - 2nd Half Cross Streets22229-Jan-1930-Jan-195 DayPave - 2nd Half Cross Streets A264Backfill Sidewalk111429-Jan-1929-Jan-195 DayBackfill Sidewalk A265Grass & Landscape Outside221430-Jan-1931-Jan-195 DayGrass & Landscape Outside A257Pave - Driveways221031-Jan-1901-Feb-195 DayPave - Driveways A270Cure 2nd Half Intersections33331-Jan-1903-Feb-197 DayCure 2nd Half Intersections A271Cure - Driveways331601-Feb-1904-Feb-197 DayCure - Driveways A258Install Colored Stamped Concrete88204-Feb-1913-Feb-195 DayInstall Colored Stamped Concrete A272Cure Stamped Concrete33314-Feb-1917-Feb-197 DayCure Stamped Concrete 22421-Dec-1826-Dec-185 DayLighting LightLightingi A285Install Conduit Between Medians22421-Dec-1826-Dec-185 DayInstall Conduit Between Medians 454510118-Feb-1930-Apr-19Stage 3B - Median Dividend to Airline StagStage 3B - Median Dividend to Airlinee A3850Switch Traffic to Stage 3B11318-Feb-1918-Feb-195 DaySwitch Traffic to Stage 3B A3900Remove Concrete Pavement11319-Feb-1919-Feb-195 DayRemove Concrete Pavement 141410120-Feb-1915-Mar-19Roadway RoadRoadway A273Balance & Fine Grade Subgrade22320-Feb-1921-Feb-195 DayBalance & Fine Grade Subgrade A2744" HMAC Ty B11321-Feb-1922-Feb-195 Day4" HMAC Ty B A275Tie Steel - Paving Pass 122322-Feb-1926-Feb-195 DayTie Steel - Paving Pass 1 A278Pave - Pass 111326-Feb-1927-Feb-195 DayPave - Pass 1 A276Tie Steel - Paving Pass 222327-Feb-1928-Feb-195 DayTie Steel - Paving Pass 2 A281Cure Pass 133327-Feb-1902-Mar-197 DayCure Pass 1 A279Pave - Pass 211104-Mar-1904-Mar-195 DayPave - Pass 2 A277Tie Steel - Paving Pass 322105-Mar-1906-Mar-195 DayTie Steel - Paving Pass 3 A282Cure Pass 23316505-Mar-1908-Mar-197 DayCure Pass 2 A280Pave - Pass 311106-Mar-1907-Mar-195 DayPave - Pass 3 A283Cure Pass 333207-Mar-1910-Mar-197 DayCure Pass 3 A284Colored Stamped Median Pavement2211113-Mar-1915-Mar-195 DayColored Stamped Median Pavement 77520-Feb-1904-Mar-19Lighting LightLightingi A286Install Illumination Drill Shafts (15 ea)22620-Feb-1922-Feb-195 DayInstall Illumination Drill Shafts (15 ea) A287Complete Conduit22822-Feb-1925-Feb-195 DayComplete Conduit A289Cure Illumination Drill Shafts66822-Feb-1927-Feb-197 DayCure Illumination Drill Shafts A288Set Illumination & Wiring22628-Feb-1904-Mar-195 DaySet Illumination & Wiring 383811107-Mar-1930-Apr-195 DayLandscaping LandLandscapings A290Install Irrigation System4411107-Mar-1913-Mar-195 DayInstall Irrigation System A291Install Landscape Borders2211115-Mar-1919-Mar-195 DayInstall Landscape Borders A292Install Landscaping181811119-Mar-1912-Apr-195 DayInstall Landscaping A293Install City Monument121211112-Apr-1930-Apr-195 DayInstall City Monument 9797811-Mar-1908-Aug-19Stage 4A - SB Fritz to Bethel StagStage 4A - SB Fritz to Bethele A3860Switch Traffic to Stage 4A11211-Mar-1911-Mar-195 DaySwitch Traffic to Stage 4A A3910Remove Concrete Pavement88212-Mar-1921-Mar-195 DayRemove Concrete Pavement 66222-Mar-1901-Apr-195 DaySanitary Sewer SanitSanitary Sewera A294Install SS @ Southwestern44222-Mar-1927-Mar-195 DayInstall SS @ Southwestern A295Complete SS Rehab Work22228-Mar-1901-Apr-195 DayComplete SS Rehab Work 58581701-Apr-1920-Jun-195 DayStorm Drain StorStorm Drainm A308Storm Drain Impovements SB55201-Apr-1908-Apr-195 DayStorm Drain Impovements SB A309Complete Inlet Tops after Paving331717-Jun-1920-Jun-195 DayComplete Inlet Tops after Paving 3838222-Mar-1914-May-195 DayWater Line WateWater Liner Remaining Level of EffortActual WorkCritical Remaining Work Page 5 of 7 Run Date 25-May-18 Actual Level of EffortRemaining WorkMilestone Data Date 25-May-18 Activity IDActivity NameOriginalRemainingTotal FloatStartFinishCalendar20182019 DurationDuration c AprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNov A311Bore Casing Under Railroad (102 LF)1010622-Mar-1904-Apr-195 DayBore Casing Under Railroad (102 LF) A310Complete SB Water Connections 28+26 to 45+8022208-Apr-1910-Apr-195 DayComplete SB Water Connections 28+26 to 45+80 A312Install 16" Water Main 45+80 to 67+681515210-Apr-1901-May-195 DayInstall 16" Water Main 45+80 to 67+68 A314Connect to Existing @ 67+6811201-May-1902-May-195 DayConnect to Existing @ 67+68 A313Complete Connections North of 45+8022202-May-1906-May-195 DayComplete Connections North of 45+80 A315Remove/Grout Existing Water Line66207-May-1914-May-195 DayRemove/Grout Existing Water Line 8989822-Mar-1908-Aug-19Roadway RoadRoadway A320Balance Subgrade10103022-Mar-1904-Apr-195 DayBalance Subgrade A321Fine Grade Subgrade33215-May-1920-May-195 DayFine Grade Subgrade A3224" HMAC Ty B66220-May-1928-May-195 Day4" HMAC Ty B A323Tie Steel - Paving Pass 133228-May-1903-Jun-195 DayTie Steel - Paving Pass 1 A329Paving - Pass 133203-Jun-1906-Jun-195 DayPaving - Pass 1 A324Tie Steel - Paving Pass 233206-Jun-1911-Jun-195 DayTie Steel - Paving Pass 2 A343Cure Paving - Pass 133406-Jun-1909-Jun-197 DayCure Paving - Pass 1 A325Tie Steel - Turn Lanes (6 turn lanes)22211-Jun-1913-Jun-195 DayTie Steel - Turn Lanes (6 turn lanes) A330Paving - Pass 233211-Jun-1914-Jun-195 DayPaving - Pass 2 A331Pave - Turn Lanes33214-Jun-1919-Jun-195 DayPave - Turn Lanes A344Cure Paving - Pass 2332414-Jun-1917-Jun-197 DayCure Paving - Pass 2 A345Cure - Turn Lanes33219-Jun-1922-Jun-197 DayCure - Turn Lanes A326Tie Steel - 1st Half Cross Streets22024-Jun-1926-Jun-195 DayTie Steel - 1st Half Cross Streets A336Backfill Pavement44924-Jun-1927-Jun-195 DayBackfill Pavement A332Pave - 1st Half Cross Streets33026-Jun-1901-Jul-195 DayPave - 1st Half Cross Streets A337Install Gabions @ 61+8033928-Jun-1903-Jul-195 DayInstall Gabions @ 61+80 A346Cure - 1st Half Intersections33001-Jul-1904-Jul-197 DayCure - 1st Half Intersections A339Grade for Sidewalk1010903-Jul-1917-Jul-195 DayGrade for Sidewalk A327Tie Steel - 2nd Half Cross Streets22005-Jul-1909-Jul-195 DayTie Steel - 2nd Half Cross Streets A328Tie Steel - Driveways222309-Jul-1911-Jul-195 DayTie Steel - Driveways A333Pave - 2nd Half Cross Streets33009-Jul-1912-Jul-195 DayPave - 2nd Half Cross Streets A334Pave - Driveways332311-Jul-1916-Jul-195 DayPave - Driveways A347Cure 2nd Half Intersections33012-Jul-1915-Jul-197 DayCure 2nd Half Intersections A335Install Colored Stamped Concrete1010015-Jul-1929-Jul-195 DayInstall Colored Stamped Concrete A348Cure - Driveways333216-Jul-1919-Jul-197 DayCure - Driveways A340Pave Sidewalk1010917-Jul-1931-Jul-195 DayPave Sidewalk A349Cure Stamped Concrete331929-Jul-1901-Aug-197 DayCure Stamped Concrete A341Backfill Sidewalk22931-Jul-1902-Aug-195 DayBackfill Sidewalk A342Grass & Landscape Outside44902-Aug-1908-Aug-195 DayGrass & Landscape Outside 93931322-Mar-1901-Aug-195 DayRailroad RailrRailroado A297Railroad Installed Concrete Panels SB1110422-Mar-1922-Mar-195 DayRailroad Installed Concrete Panels SB A298Railroad Installed Ped Crossing Arms SB1110422-Mar-1922-Mar-195 DayRailroad Installed Ped Crossing Arms SB A299Connect Pavement SB114319-Jun-1920-Jun-195 DayConnect Pavement SB A300Build Sidewalk at RR Crossing SB111331-Jul-1901-Aug-195 DayBuild Sidewalk at RR Crossing SB 11111115-Jul-1901-Aug-19Traffic Signals TraffiTraffic Signals A302Signal Drill Shafts at Southwestern SB221315-Jul-1917-Jul-195 DaySignal Drill Shafts at Southwestern SB A304Install Conduit from SB Corners w/ Pull Boxes221517-Jul-1919-Jul-195 DayInstall Conduit from SB Corners w/ Pu A305Signal Drill Shaft Cure661717-Jul-1922-Jul-197 DaySignal Drill Shaft Cure A301Install Signal Poles & Wire881322-Jul-1901-Aug-195 DayInstall Signal Poles & Wire 333312009-Apr-1804-Oct-19Stage 4B - Med StagStage 4B - Median Airline to Bethele A3870Switch Traffic to Stage 4B11908-Aug-1909-Aug-195 DaySwitch Traffic to Stage 4B Remaining Level of EffortActual WorkCritical Remaining Work Page 6 of 7 Run Date 25-May-18 Actual Level of EffortRemaining WorkMilestone Data Date 25-May-18 Activity IDActivity NameOriginalRemainingTotal FloatStartFinishCalendar20182019 DurationDuration c AprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNov A3920Remove Concrete Pavement22909-Aug-1913-Aug-195 DayRemove Concrete Pavement 16162109-Aug-1903-Sep-19Bridge BridgeBridge A316Form & Pour NB Sidewalk222409-Aug-1912-Aug-195 DayForm & Pour NB Sidewalk A317Cure NB Sidewalk333313-Aug-1916-Aug-197 DayCure NB Sidewalk A318Form & Pour NB Traffic Rail10102316-Aug-1930-Aug-195 DayForm & Pour NB Traffic R A338Illumination and Banner Poles on Bridge222330-Aug-1903-Sep-195 DayIllumination and Banner P 3434013-Aug-1904-Oct-19Roadway RoadRoadway A363Balance & Fine Grade Subgrade22913-Aug-1914-Aug-195 DayBalance & Fine Grade Subgra A3644" HMAC Ty B22915-Aug-1916-Aug-195 Day4" HMAC Ty B A365Tie Steel - Paving Pass 111916-Aug-1919-Aug-195 DayTie Steel - Paving Pass 1 A368Pave - Pass 111919-Aug-1920-Aug-195 DayPave - Pass 1 A366Tie Steel - Paving Pass 211920-Aug-1921-Aug-195 DayTie Steel - Paving Pass 2 A372Cure Pass 1332520-Aug-1923-Aug-197 DayCure Pass 1 A373Cure Pass 2331321-Aug-1924-Aug-197 DayCure Pass 2 A369Pave - Pass 2111723-Aug-1926-Aug-195 DayPave - Pass 2 A367Tie Steel - Paving Pass 3111726-Aug-1927-Aug-195 DayTie Steel - Paving Pass 3 A370Pave - Pass 3111727-Aug-1928-Aug-195 DayPave - Pass 3 A374Cure Pass 3332327-Aug-1930-Aug-197 DayCure Pass 3 A350Tie Steel - Pass 4111728-Aug-1929-Aug-195 DayTie Steel - Pass 4 A351Pave Pass 4111502-Sep-1902-Sep-195 DayPave Pass 4 A352Cure Pass 4332103-Sep-1906-Sep-197 DayCure Pass 4 A383Colored Stamped Cross Walk221606-Sep-1910-Sep-195 DayColored Stamped Cros A371Colored Stamped Median Pavement221610-Sep-1912-Sep-195 DayColored Stamped Med A382Permanent Striping55027-Sep-1904-Oct-195 DayPermanent Strip 17171026-Aug-1920-Sep-19Lighting LightLightingi A375Install Illumination Drill Shafts (27 ea)881026-Aug-1904-Sep-195 DayInstall Illumination Drill S A376Complete Conduit441005-Sep-1910-Sep-195 DayComplete Conduit A378Cure Illumination Drill Shafts661405-Sep-1910-Sep-197 DayCure Illumination Drill S A377Set Illumination & Wiring881011-Sep-1920-Sep-195 DaySet Illumination & W 333312009-Apr-1804-Oct-19Landscaping LandLandscapings A388Duration530498009-Apr-1804-Oct-197 Day A379Install Irrigation System1212029-Jul-1914-Aug-195 DayInstall Irrigation System A380Install Landscape Borders88014-Aug-1926-Aug-195 DayInstall Landscape Borders A381Install Landscaping2424026-Aug-1927-Sep-195 DayInstall Landscapin Remaining Level of EffortActual WorkCritical Remaining Work Page 7 of 7 Run Date 25-May-18 Actual Level of EffortRemaining WorkMilestone Data Date 25-May-18 'A'notesanactualdate.