Loading...
City of Coppell - Starleaf Pump Station Redundancy vs Cost    Technical Memorandum    (Starleaf Pump Station Study) Page 1 of 3 To: Jamie Brierton, CIP Coordinator Jerry Davis, Water Operations Supervisor From: Bryant Caswell, PE (Texas PE #91721) Dorian French, PE, RPLS, DWRE (Texas PE #40453) Jennifer Roath, EIT (Texas EIT #48676) Date: July 19, 2016 Subject: Starleaf Pump Station – Water Distribution System Redundancy vs Cost As part of the SPS Study, Brown & Gay Engineers Inc., (BGE) has performed a supplemental hydraulic analysis of the City’s water distribution system with Village Parkway Pump Station (VPPS) offline and only the proposed Starleaf Pump Station (SPS) running in order to analyze three levels of redundancy. Reducing the capacity of the facility below fully redundant will offer the City cost savings through smaller pumps, storage tanks, and possibly building size. The purpose of this memorandum is to outline the levels of redundancy and cost savings so the City can make an informed decision before moving into the pump selection and the design phases. WATER DEMAND  Currently, the City receives all of their treated water from Dallas Water Utilities (DWU). They are contracted to receive 18.5 MGD into the Village Parkway GST. Based on meter data from the past two years, the demand fluctuates between 2.4 and 17.1 MGD between winter and summer respectively. Figure 1 shows the daily DWU influent and VPPS discharge records from January 1, 2014 to September 30, 2015. Figure 1 – Daily Meter Data from 1/1/2014 ‐ 9/30/2015  0 2 4 6 8 10 12 14 16 18 20 1/1 2/1 3/1 4/1 5/1 6/1 7/1 8/1 9/1 10/1 11/112/1 1/1 2/1 3/1 4/1 5/1 6/1 7/1 8/1 9/1Flow (MGD)Date DWU Influent VP Discharge 2014 2015     Technical Memorandum (Starleaf Pump Station Study)  Page 2 of 3 To achieve complete redundancy where the SPS is able to supply the entire system through peak summer demand, SPS would require 18 MGD capacity. While complete redundancy would offer the City the most protection, scaling back the pumps and storage would offer substantial cost savings. If SPS is sized for 12 MGD capacity, then the redundancy would be reduced to seven months, from about October to April based on 2104 & 2015 meter data. To provide an adequate window for major maintenance to VPPS, a minimum six month window is recommended. MODELING  Three redundancy scenarios were tested using the hydraulic model developed for Technical Memorandum #2 – Hydraulic Study. These scenarios assumed VPPS was completely offline, including all pumps and storage tanks. Supply from DWU was only entering the Starleaf GST and SPS is the only source of supply for the City’s system. For each scenario, SPS had 3 pumps of identical size varying from 4,000 gpm to 7,000 gpm. The GST was either 5, 6, or 8 Mgal. Then demand was adjusted to model each redundancy level: 12, 14 and 18 MGD. Results of the scenarios are described in Table 1 and discussed in the subsequent sections. Table 1 – Modeling Scenario Results  Redundancy  Level  Pump Size  (gpm)  Tank Size  (Mgal) Comment  12 MGD  4,000 5 ESTs and GST below 5ft   4,000 6 ESTs and GST below 5ft  4,500 5 ESTs and GST cycle  4,500 6 ESTs and GST cycle  14 MGD  4,500 5 ESTs empty  4,500 6 ESTs and GST below 5ft  5,000 5 ESTs and GST below 5ft  5,000 6 ESTs and GST cycle  18 MG  7,000 5 ESTs empty  7,000 6 ESTs and GST below 5ft  7,000 8 ESTs and GST cycle  Redundancy Level 1 – 12 MGD  The lowest capacity level for pumping and storage redundancy recommended is 12 MGD. This would provide the City with approximately 7 months in which to perform major repairs at VPPS based on 2014 – 2015 meter data. When system demands reach 12 MGD, three pumps would be required during peak hour flows to avoid the ESTs from nearing empty. The minimum pump size required would be 4,500 gpm with a 5 Mgal tank.     Technical Memorandum (Starleaf Pump Station Study)  Page 3 of 3 Redundancy Level 2 – 14 MGD  14 MGD of pumping capacity with 6 Mgal of storage would provide approximately 9 months in which to perform major repairs at VPPS. When the system demands reach 14 MGD three 4,500- 5,000 gpm pumps would be required during peak demand. The minimum pump size required would be 4,500 gpm with a 6 Mgal tank. Redundancy Level 3 – 18 MGD  Complete redundancy in the system would be achieved with 7,000 gpm pumps running during peak hourly flow. A 6 Mgal tank almost emptied during the model run however, the model only simulated a 72 hour period. More than three days of continuous peak demand would likely have emptied the tank. Therefore, to achieve complete redundancy an 8 Mgal tank is recommended. COST COMPARISON  The cost difference for the pumps and tanks at each redundancy level is summarized in Table 2. This comparison only considers the direct cost of the pumps and tank, and does not include the building, site work, yard piping, and other related costs. Table 2 – Cost Comparison between Redundancy Levels  Redundancy  Level  Pump   Tank   Total Size (gpm) Cost1 Size (Mgal) Cost1  12 MGD  4,500  $321,000  5  $2,900,000 $3,221,000  14 MGD  5,000  $345,000  6  $3,400,000 $3,745,000  18 MGD  7,000  $525,000  8  $4,200,000 $4,725,000  1. Costs shown are based on average vendor and contractor prices, see attachment  The building cost may vary based on the redundancy level, and will likely provide further cost savings, but other uses such as maintenance and office space make it difficult to quantify at this point. The type of pump, vertical turbine or horizontal split case, may have no significant impact on the building cost. Although the building footprint for vertical turbine pumps will be less than that required for horizontal split case pumps, significantly more excavation and subgrade preparation would be required. Although detailed pump selections were performed for this analysis, it is to be discussed further in Technical Memorandum 3 – Pump Type Selection, once the stations capacity is determined. RECOMMENDATIONS   It is recommended that the SPS be designed for a 14 MGD capacity to provide a 9 month redundancy window to VPPS. The estimated savings by reducing the capacity from 18 MGD to 14 MGD would be approximately $980,000. ATTACHMENTS: Contractor and Vendor Cost Comparisons City of Coppell Starleaf Pump Station Project - Pump Cost Comparison Proj No. 3451 Pump* Capacity         (gpm) Horizonal Split  Case  Vertical  Turbine Horizonal Split  Case  Vertical  Turbine 4,500 50,000$          75,000$          210,000$       92,600$          5,000 75,000$          75,000$          210,000$       95,500$          7,000 100,000$        150,000$        190,000$       255,000$        *Costs shown are for a single pump. The pump station will have three (3) pumps of equal size.  Pierce Pump Solutions Cost Comparison Table  $‐  $50,000  $100,000  $150,000  $200,000  $250,000  $300,000 4,500 5,000 7,000 Capacity (gpm)  Cost vs. Pump Size (gpm) City of Coppell Starleaf Pump Station Project - GST Tank Cost Comparison Proj No. 3451 Tank  Vol (Mgal)Foundation Tank Total Tank Total Tank Total  1 2 500,000$       1,025,000$    1,525,000$   950,000$      1,450,000$    3 4 5 1,100,000$    1,775,000$          2,875,000$    6 1,200,000$    2,250,000$    3,450,000$   2,045,000$          3,245,000$    7 8 1,500,000$    2,800,000$    4,300,000$   2,871,000$   4,371,000$   2,530,000$          4,030,000$    DN Tanks Preload Cost Comparison Table Crom $0 $500,000 $1,000,000 $1,500,000 $2,000,000 $2,500,000 $3,000,000 $3,500,000 $4,000,000 $4,500,000 $5,000,000 12345678 Volume (Mgal) Cost vs. GST Vol (Mgal)