ST1501A-CS180615
Priscilla Martinez
From:Marcus Marion
Sent:Friday, June 15, 2018 1:34 PM
To:Priscilla Martinez
Subject:Freeport Reconstruction - Subgrade Inspection
This is a correspondence about the subgrade on Freeport PKWY
From: Kent Collins
Sent: Friday, June 15, 2018 7:53 AM
To: Jay Volk <jay@jvolkconsulting.com>; Joel Peters <JDPeters@kleinfelder.com>; FreeportProjectST1501
<freeportprojectst1501@coppelltx.gov>; Claudio Segovia <claudio@jvolkconsulting.com>
Subject: FW: Freeport Reconstruction Subgrade Inspection
Jay, to echo Eric’s sentiment, in my mind the questions are: how do we control the subgrade moisture after Texas
Sterling is complete with the project so the roadway does not fail prematurely. And, do we need to consider an alternate
pavement section to stabilize the subgrade knowing that the moisture content of the subgrade may be an issue. I still
like the benefits of the asphalt base, but do we need to consider some depth of subgrade stabilization (for example, do
we go to lime treated subgrade with a 1”-2” asphalt cap)? Please review and let us know. This is obviously a critical
issue.
Thanks,
Kent
From: Eric Giebelhaus \[mailto:Eric.Giebelhaus@strlco.com\]
Sent: Thursday, June 14, 2018 11:11 AM
To: Joel Peters <JDPeters@kleinfelder.com>; Darryl Zbranek <dzbranek@coppelltx.gov>; Jay Volk
<jay@jvolkconsulting.com>; Kent Collins <KCollins@coppelltx.gov>; FreeportProjectST1501
<freeportprojectst1501@coppelltx.gov>
Cc: Jimmy Reed <Jimmy.Reed@strlco.com>; Joe Soto <Joe.Soto@strlco.com>; Marcus Marion
<MMarion@coppelltx.gov>; Jamie Brierton <JBrierton@coppelltx.gov>; Rick Hammerberg
<rhammerberg@kleinfelder.com>
Subject: RE: Freeport Reconstruction Subgrade Inspection
This is not about compaction but the long term viability of building a road on this kind of material. We can get
compaction, what we can’t do is control the moisture content after the road is built. The high moisture content under
the existing roadway will become the condition of the subgrade under the new pavement after the project is completed.
This subgrade isn’t solid and will continue to pump causing damage to the pavement.
Thanks,
Eric Giebelhaus
Project Manager– North Texas Division
Texas Sterling Construction Co.
| 1441 Airport Freeway Suite 350, Euless, Texas 76040 |
| 469.346.8085 Cell |
1
From: Joel Peters <JDPeters@kleinfelder.com>
Sent: Thursday, June 14, 2018 11:07 AM
To: Darryl Zbranek <dzbranek@coppelltx.gov>; Jay Volk <jay@jvolkconsulting.com>; Kent Collins
<KCollins@coppelltx.gov>; FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Cc: Jimmy Reed <Jimmy.Reed@strlco.com>; Eric Giebelhaus <Eric.Giebelhaus@strlco.com>; Joe Soto
<Joe.Soto@strlco.com>; Marcus Marion <MMarion@coppelltx.gov>; Jamie Brierton <JBrierton@coppelltx.gov>; Rick
Hammerberg <rhammerberg@kleinfelder.com>
Subject: RE: Freeport Reconstruction Subgrade Inspection
Thank you, Darryl…you beat me to it.
Yes, the moistures are about 7%-14% above optimum moisture for the proctor samples we have. Recent density tests
that we have taken on waterline backfill to depths of -3 ft have varied in the 0%-4% above optimum range, and able to
achieve 95% compaction or better. For this type of clay, placement and compaction in this moisture range is ideal,
whereas, higher moisture contents elevated up to +5 to 6% or more over optimum moisture may make it more difficult
to attain proper compaction and/or present possible constructability issues.
Please let us know if there any questions regarding this information, at this time.
Thank you.
Joel Peters, PE
Project Manager
7805 Mesquite Bend Dr, Suite 100
Irving, TX 75063
o| 972.868.5900
d| 972.868.5916
m| 214.876.5559
f| 972.409.0008
2
From: Darryl Zbranek \[mailto:dzbranek@coppelltx.gov\]
Sent: Thursday, June 14, 2018 10:37 AM
To: Jay Volk <jay@jvolkconsulting.com>; Joel Peters <JDPeters@kleinfelder.com>; Kent Collins
<KCollins@coppelltx.gov>; FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Cc: Jimmy Reed <Jimmy.Reed@strlco.com>; Eric Giebelhaus <Eric.Giebelhaus@strlco.com>; Joe Soto
<Joe.Soto@strlco.com>; Marcus Marion <MMarion@coppelltx.gov>; Jamie Brierton <JBrierton@coppelltx.gov>
Subject: RE: Freeport Reconstruction Subgrade Inspection
External Email.
Jay, see the attached test reports. Moisture of the existing material appears to be higher than optimum.
Darryl Zbranek
Chief Construction Inspector
City of Coppell, TX
(469)507-9095 (cell)
www.coppelltx.gov
From: Jay Volk \[mailto:jay@jvolkconsulting.com\]
Sent: Thursday, June 14, 2018 9:39 AM
To: Darryl Zbranek <dzbranek@coppelltx.gov>; Joel Peters <JDPeters@kleinfelder.com>; Kent Collins
<KCollins@coppelltx.gov>; FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Cc: Jimmy Reed <Jimmy.Reed@strlco.com>; Eric Giebelhaus <Eric.Giebelhaus@strlco.com>; Joe Soto
<Joe.Soto@strlco.com>; Marcus Marion <MMarion@coppelltx.gov>; Jamie Brierton <JBrierton@coppelltx.gov>
Subject: RE: Freeport Reconstruction Subgrade Inspection
Darryl, do we know how these figures compare with the optimum moisture content for the soils?
Jay Volk | President
830 Central Parkway East | Suite 300 | Plano | TX 75074
972-201-3101 (office)
972-201-3101 (direct)
972-965-2864 (mobile)
972-201-3099 (fax)
www.jvolkconsulting.com
From: Darryl Zbranek <dzbranek@coppelltx.gov>
Sent: Wednesday, June 13, 2018 9:46 AM
To: Joel Peters <JDPeters@kleinfelder.com>; Jay Volk <jay@jvolkconsulting.com>; Kent Collins
<KCollins@coppelltx.gov>; FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Cc: Jimmy Reed <Jimmy.Reed@strlco.com>; Eric Giebelhaus <Eric.Giebelhaus@strlco.com>; Joe Soto
<Joe.Soto@strlco.com>; Marcus Marion <MMarion@coppelltx.gov>; Jamie Brierton <JBrierton@coppelltx.gov>
Subject: RE: Freeport Reconstruction Subgrade Inspection
3
All, I received a hard copy of the subgrade moisture test results from Kleinfelder taken on 6/7/2018 after our site
meeting held on 6/6/2018. Please review and respond with any comments, concerns, or questions.
Thanks,
Darryl Zbranek
Chief Construction Inspector
City of Coppell, TX
(469)507-9095 (cell)
www.coppelltx.gov
-----Original Appointment-----
From: Darryl Zbranek
Sent: Friday, June 1, 2018 2:48 PM
To: Jimmy Reed; Eric Giebelhaus; Joe Soto; Joel Peters; Jamie Brierton; Jay Volk; Marcus Marion; Kent Collins;
FreeportProjectST1501
Subject: Freeport Reconstruction Subgrade Inspection
When: Monday, June 4, 2018 2:00 PM-4:00 PM (UTC-06:00) Central Time (US & Canada).
Where: Intersection of Freport and Fritz
Texas Sterling has concerns of the moisture content of the subgrade in the Northbound lanes of Freeport. Meeting on
site to discuss the issue.