ST1501A-CS180629
Priscilla Martinez
From:Marcus Marion
Sent:Friday, June 29, 2018 3:40 PM
To:Priscilla Martinez
Subject:Freeport - Utility Conflict with Road Grade
Attachments:TSC 1723-008 - Utility Conflict with Road Grade.pdf
This is a correspondence for the Freeport PKWY project about conduit being found while concrete was being removed
From: Eric Giebelhaus \[mailto:Eric.Giebelhaus@strlco.com\]
Sent: Friday, June 29, 2018 12:46 PM
To: Jamie Brierton <JBrierton@coppelltx.gov>
Cc: FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>; Joe Soto <Joe.Soto@strlco.com>; Jimmy Reed
<Jimmy.Reed@strlco.com>; Darryl Zbranek <dzbranek@coppelltx.gov>; Marcus Marion <MMarion@coppelltx.gov>
Subject: Freeport - Utility Conflict with Road Grade
Jamie,
Is there any way to can setup a meeting with all of the utility companies who have facilities along Freeport Parkway?
We have been trying to get Zayo out to the project with no success, they are in conflict at the bridge. Frontier is also at
conflict at the bridge but we have not been able to get an update on when Fishel will be complete with the relocation.
Now we have Spectrum in conflict near Bethel and they have cables laid out on the ground near Fritz that will be a
problem. The gas company staked their proposed running line and it looks like a conflict with the eastern drill shaft in
bent 2.
Thanks,
Eric Giebelhaus
Project Manager– North Texas Division
Texas Sterling Construction Co.
| 1441 Airport Freeway Suite 350, Euless, Texas 76040 |
| 469.346.8085 Cell |