Freeport NIP(2.2)-LR011127 (2) REPORT OF DRILLED BELLED PIER OBSERVATION Report Number: 94011204.0062 8901 Carpenter Frwy., Suite #100 Service Date: November 13, 2001 Dallas, Texas 75247 (214) 630-1010 Client: TNA North American, Inc. Report Date: November 27, 2001 Attn: Ternj Raley Project: Sales Office & Warehouse Fac. 1321 Valwood Parkway, Suite 440 Coppell, Texas Carrollton TX 75006 Project Number: 94011204 Services: Drilled belled pier observation. On this date, an HBC Engineering technician arrived at the above referenced jobsite as scheduled for drilled belled pier observation. See the attached sheet(s) for recorded data. NOTE: At 12:45 p.m., the pier drilling rig broke down. HBC's technician was requested to be on standby until the mechanic checked out the pier drilling rig. At 2:00 p.m., the mechanic arrived and started working on the pier drilling rig. At 2:45 p.m., HBC's technician was informed that the pier drilling rig was finished for the day and the pier holes were backfilled. Technician: Steve Campbell ///J/ Report Distribution: ~'~n~'meeri' 'ng, Inc. (1) TNA North American, Inc. (1) FACServices Inc (1) Carrell Poole & Yost Architecture (1) David Kent Reviewed by: (1) R L Goodson Consulting Engineers (1) City of Coppell - Bldg Insp Eric J. Cleveland, P.E. (1) Pacific Builders Inc (1) City of Coppell - Constr Insp Senior Project Engineer The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written approval of Terracon. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. Page 1 of 1 ~,,~ ENGINEERING, INC. 8901 Carpenter Frwy., Suite #100 Dallas, Texas 75247 Project: Sales Office & Warehouse Fac. Report No.: 94011204.0062 Coppell, Texas Date of Service: 11/13/01 Project No.: 94011204 Technician: S. Campbell Driller: Auger Drilling, Inc. Page: 1 of 2 Pier Identification B.4/7.2 B.TFA2 B.9/7.2 C.3/7.2 C.7/7.2 Pier Diameter (in.) 18 18 18 18 18 Bell Diameter (in.) 36 36 36 36 36 *Top of Pier Elevation (ft) N/A N/A N/A N/A N/A Re({. Depth from Exist. Grade Iff) 15.0 15.0 15.0 15.0 15.0 Initial Depth of Pier from Existing Grade (fi) 14.5 15.0 14.9 14.3 15.5 Final Depth of Pier from Existing Grade(ft) See Note See Note See Note See Note See Note Depth from Top of Concrete (ft) See Note See Note See Note See Note See Note Condition of Bottom (wet or dry) Dry Dry Dry Dry Dry Plumb Within Tolerance (yes or no) Yes Yes Yes Yes Yes Casing Diameter (in) N/A N/A N/A N/A N/A Cased Depth (ft) N/A N/A N/A N/A N/A Number of Vertical Bars (ea.) 5 5 5 5 5 Reinforcing Bar Size (#) 6 6 6 6 6 Length of Vertical Bars (ft.) See Note See Note See Note See Note See Note Time Drilling was Completed See Note See Note See Note See Note See Note Time Concrete was Placed See Note See Note See Note See Note See Note *Elevation was provided by others. REPORT OF DRILLED BELLED PIERS H~ ENGINEERING, I~C. 8901 Carpenter Frwy., Suite #100 Dallas, Texas 75247 Project:Sales Office & Warehouse Fac. - Dock, SE side of building Report No.:94011204.0062 Coppell, Texas Date of Service:11/13/01 ProlectNo.: 94011204 Technician: S. Campbell Driller: Auger Drilling, Inc. Page: 2 of 2 Pier Identification NE NW S Pier Diameter (in.) 18 18 18 Bell Diameter (in.) 36 36 36 *Top of Pier Elevation (ft) N/A N/A N/A Req. Depth from Exist. Grade (ft) 15.0 15.0 15.0 Initial Depth of Pier from Existing Grade (fi) 13.7 13.5 14.8 Final Depth of Pier from Existing Grade (fi) 13.8 13.5 14.8 Depth from Top of Concrete (ft) 13.8 13.0 14.8 Condition of Bottom (wet or dry) Dry Dry Dry Plumb Within Tolerance (yes or no) Yes Yes Yes Casing Diameter (in) N/A N/A N/A Cased Depth (ft) N/A N/A N/A Number of Vertical Bars (ea.) 5 5 5 Reinforcing Bar Size (#) 6 6 6 Length of Vertical Bars (ft.) 14.4 12.0 15.4 Time Drilling was Completed 10:10 a.m. 10:40 a.m. 11:00 a.m. Time Concrete was Placed 11:10 a.m. 11:00 a.m. 11:05 a.m. *Elevation was provided by others. CONCRETE COMPRESSIVE STRENGTH TEST Report Number: 94011204.0070 ~,~N~.,,~. 8901 Carpenter Frwy., Suite #100 Service Date: November 19, 2001 Dallas, Texas 75247 (214) 630-1010 Client: TNA North American, Inc. Report Date: November 27, 2001 Attn: Terr~ Raley Project: Sales Office & Warehouse Fac. 1321 Valwood Parkway, Suite 440 Coppell, Texas Carrollton TX 75006 Project Number: 94011204 Material Information Sample Information Specified Strength: 3000 psi @ 28 Days Sample Time: 12:30pm Date Cast: November 19, 2001 Technician: Jason Kale Batch Time: 11:12am Plant: 31 Weather Conditions: Cloudy, windy Supplier: TXI Accumulative Yards: 10 Truck No: 139 Ticket No: 3027168 Placement Method: Direct Discharge Mix I.D. No.: 8273 Sample Locations: See attached sketch Water Added Onsite Before Test: 5 Gallons Placement Location: Paving Field Test Data Test Result Specification Test Method Slump, inches: 4.25 3-5 ASTM C-143 Air Content, %: 5.0 3-6 ASTM C-231 Concrete Temperature, o F: 71 ASTM C1064 Ambient Temperature, o F: 54 ASTM C-1064 Plastic Unit Weight, pcf: Laboratory Test Data Age at Maximum Compressive Set Specimen Diameter Area Date Test Load Strength No. ID (inches) (sq. inches) Tested (days) (lbs) (psi) 1 I 6.00 28.27 11/26/2001 7 89,270 3,160 1 2 6.00 28.27 11/26/2001 7 87,920 3,110 Average 3,140 1 3 12/17/2001 28 1 4 12/17/2001 28 NOTE: Concrete Mix Design 9505 (with no entrained air) was used for the paving concrete placement. Approximately 50 cubic yards was placed using the remaining concrete from the Elevated Slab and Slab Leaveout concrete placements. Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength samples. Technician: Jason Kale Report Distribution: ~~_ .~. ~.ne.ering, Inc. (1) TNA North American, Inc. (1) FACServices inc (1) Carrell Poole & Yost Architecture (1) David Kent Reviewed by: (1) R L Goodson Consulting Engineers (1) City of Coppell - Bldg lnsp Eric 3. Cleveland, P.E. (1) Pacific Builders Inc (1) City of Coppell - Constr insp Senior Project Engineer The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written approval of Terracon. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. Page 1 of 1