Loading...
ST1501A-CS180427 (3) Priscilla Martinez From:Claudio Segovia <claudio@jvolkconsulting.com> Sent:Thursday, April 27, 2017 4:52 PM To:Claudio Segovia Subject:Coppell - Freeport Reconstruction - Franchise Relocations Attachments:Freeport SUE.kmz Good afternoon, We are working on a road project in the City of Coppell, TX and will be reconstructing/modifying Freeport Parkway from Dividend Drive to West Bethel Road. The improvements include a wider pavement section as well as the addition of sidewalks/trails throughout the length of the project and the construction of a new bridge. A 90% Set of Reconstruction Plans has been submitted to the City of Coppell and we are now just making minor revisions to issue the final plans. The City has asked us to distribute these plans to ensure proper relocations as necessary. The plans can’t be sent through e- mail since the files are too large but they have been uploaded to our FTP site: File Transfer Login: http://www.jvolkconsulting.com/ Email/username: coppell@jvolkconsulting.com Password: FreeportJVC A SUE Level B study has been done for the project limits and I’ve attached a .kmz file that can be opened in Google Earth showing what was found. The plans also show the lines per the study. We received your contact information through the study. Please confirm that you are the appropriate contact or if I need to contact someone else for coordination. The City of Coppell is planning to start construction near the end of Summer. Please look over the plans to make sure that there are/will be no conflicts with your franchise utilities and that all of your utilities are shown. Because of the pavement widening and sidewalk addition, there are several lines/structures that will need to be relocated and we’d like to begin coordination as soon as possible. Let me know if you have any questions. Thank you! Claudio Segovia | Engineer J. VOLK consulting 830 Central Parkway East | Suite 300 | Plano | TX 75074 972-201-3100 Ext. 208 (office) 972-322-7026 (mobile) 972-201-3099 (fax) www.jvolkconsulting.com Service with Integrity, Initiative and Innovation 1 Priscilla Martinez From:Marcus Marion Sent:Tuesday, July 24, 2018 8:49 AM To:Priscilla Martinez Subject:Freeport PKWY - Zayo, Century Link, Level 3 Attachments:Coppell - Freeport Reconstruction - Franchise Relocations This is a correspondence for the Freeport PKWY project From: Darryl Zbranek Sent: Wednesday, July 18, 2018 11:47 AM To: FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov> Subject: FW: Freeport Coordination - Zayo, Century Link, Level 3 From: Claudio Segovia \[mailto:claudio@jvolkconsulting.com\] Sent: Tuesday, July 3, 2018 12:05 PM To: Darryl Zbranek <dzbranek@coppelltx.gov> Cc: Jay Volk <jay@jvolkconsulting.com> Subject: Freeport Coordination - Zayo, Century Link, Level 3 Darryl, Here’s a summary of the communication as requested:  After the SUE study was complete, we sent an e-mail (4/27/17) to additional franchise companies that we had not originally contacted. This included GXT, Level3, and Zayo. The e-mail included the kmz file of the SUE and a link to download the 90% set of plans. We asked for contacts to confirm receipt, review the plans and make sure there would be no conflicts with the proposed work and that we show everything they have. I’ve attached the e-mail for reference.  On 5/23/17, we sent an invitation to the contacts we had confirmation on thus far, this did not include the referenced companies as we had not been able to get a hold of a designated contact.  In a phone call around 8/29/17, James Roberts with GXT said he represents Zayo, Centurylink and Level 3 so future coordination was done with him.  Our CAD file was requested and sent 8/29/17, the CAD file sent included the linework for the existing utilities.  The paving plans showing the existing utilities in red was also sent 8/29/17.  Between 9/29/17 and 10/17/17, Thomas MacNutt with Level3 contacted us but it was only concerning a handhole they were relocating on Wrangler/Freeport. We ended up staking the best location for the new handhole. After this however, we were only coordinating with James Roberts.  On 10/9/18, we gave James bidding schedule for the project.  On 3/9/18, he asked if we had relocation plans for any other Telecoms along Freeport, we did not.  Late March, 2018, he asked for a City contact to coordinate relocation requirements along Freeport, we gave him Kent’s information, but we’re not sure if he was then redirected to someone else. We figured this was to work through the relocation items but hadn’t seen any proposed plans at that point. Hope this helps, sorry for the issues! Claudio Segovia | Engineer 1 J. VOLK consulting 830 Central Parkway East | Suite 300 | Plano | TX 75074 972-201-3100 (office) 972-201-3102 (direct) 972-322-7026 (mobile) 972-201-3099 (fax) www.jvolkconsulting.com Service with Integrity, Initiative and Innovation To stop receiving messages from FreeportProjectST1501 group, stop following it. 2