ST1501A-CS180726 Freeport Parkway Reconstruction Weekly Construction Meeting 7-26-18 Attendees: Eric Giebelhaus – TSC, Jimmy Reed - TSC , Marcus Marion, Darryl Zbranek, 1. Construction Activities This Period: a. Water line tie ins – Preparing for and installing water line stubs South of bridge and the water line tie in at Gateway Blvd. b. RPM continue to grade and remove excess material South of the bridge and on Tuesday moved to North of bridge and made it to the railroad tracks. c. TSC continue to locate existing utilities, work continues pot holing for the Zayo conduits. They worked on Wednesday and Thursday and will be back next week. 2. Construction Activities Planned next period: a. Continue potholing for franchise utilities in bridge area. b. Continue water line connections between Southwestern and Wrangler. c. RPM to continue grading and removing excess material. 3. Construction Issues: a. Condition of Southwestern Blvd – Street and inlets are in bad shape, there are a lot of patches, potholes, and cracks in Southwestern where water line pavement repair will tie in to existing street. TSC will provide pricing for extra paving work in Southwestern. b. 8” water line T, drawing sheet C-30. Drawings do not show permanent paving repair in the cross cut for the water line. RFI Submitted. This will be added pavement repair. c. There appears to be existing fiber line in the way of the drill shafts on the Northbound side of the Bridge. TSC began drilling the shafts on 6-21-2018. They completed drill shafts 1-6 and 1-7. TSC had to cut a section of water line out of the way for drill shaft 1-8. While they were doing this the locate company was out marking utilities and their marks were in conflict with some of the drill shafts, including drill shaft 1-8. 6-22-18 TSC had Wylie Drilling move to the North abutment. Wylie drilled drill shafts 4-9 and 4-8. While starting drill shaft 4-7 they hit a Frontier fiber line that was not marked and drilling stopped. TSC has requested the locating company to meet on site which is scheduled for Friday 6-29-19. TSC claims that locates were never marked in the creek area and thought they were ok to drill. We have received photos from the locating th company showing marks in the creek area on May 15. TSC to continue potholing to find the exact location of fiber line. 7-17-18 met on site with Zayo – Rocky Crockett. Zayo will have lines located. d. While RPM was removing pavement in the Northbound lanes of Freeport on 6-29-18 they uncovered a Spectrum line running across Freeport just below the pavement just South of the Hard 8 driveway. Spectrum to lower line. Spectrum was on site 7-19-18 lowering the line. e. 7-24-18 - While TSC was digging for the water line installation in Southwestern they hit the Water Line T which was not an 8” WL the plans showed, but was an 1.5” service line to Oncor’s Substation. The Service has not been used within the last year, so they will replace the service at a later date. 4. As-built items: a. 16” WL A Sta. 37+35.93 shifted fire hydrant to miss existing valves. b. 16” WL A Sta. 37+67.93 shifted fire hydrant to miss existing FH. c. 16” water line “A” Sta. 27+80 – water line alignment adjustment to miss existing fire hydrant. d. 16” water line ”A” Sta. 36+00 – water line vertical adjustment to go under a communication duct bank. e. Water line “A” Sta. 22+80 to Sta. 19+00. TSC will move water line alignment into the street due to existing utilities in the ROW interfering with the planned alignment. f. Water line “T”. Plans show an 8” water line to be replaced. This is a 1.5” service line for the Oncor substation that will be replaced with a 2” service line. 5. Areas of Concern: a. Saturated sub-grade. We have a response back from J Volk stating that Alpha Testing recommends the exposed soil subgrade be observed during proof-rolling. Any soft, wet, loose material exposed during the proof-roll should be removed and recompacted. TSC gave us a proposal for installing an edge drain on the edges of the road. b. Street light removal – Oncor was scheduled to remove street lights during the week of th July 9, that did not happen. We have a new contact with Oncor who is checking on the light removal and will let us know when it will happen. c. Pond at Kroger. TSC has concerns with the pond at Kroger. Plans call for a rock gabion basket at the road side of the pond. TSC is concerned with the possibility of the pond water migrating through the gabion basket to the road sub-grade. J Volk to review.