RE: Review Comments Responses to Black Walnut Café—Paving Reconstruction
Black Walnut Café—North Gateway Plaza Addition, Lot 7R, Block A
775 N Denton Tap Road, Coppell,TX 75019
Dear George Marshall,
We're in receipt of plan markups and the following comment and offer the following response and
enclosed revised plans:
FIRE LANE RECONSTRUCTION
1. When and how long will the fire lane be shut down. Will both businesses be shut down during
this work?
Construction is anticipated to commence shortly after an approved permit and pre-
construction meeting. Construction of the fire lane should take about 2 to 3 weeks. The
portions of the fire lane that will be left open will afford emergency vehicle access.
Sidewalk construction in front of the doors may cause a short-term business shut down
but no longer than a day. Continuous pedestrian access is anticipated for all other
construction phases.
Please feel free to contact us with any further questions or concerns towards this project.
Sincerely:
BAIRD, HAMPTON & BROWN
G ne Capps, Fes/
Project Manager, Civil Engineer
Enclosure: 3 Copies of: Black Walnut Café—Paving Reconstruction&Landscaping Improvements
CC: Jamie Marrs—Black Walnut Café
Sean Quinn—Black Forest Ventures, LLC
3801 William D Tate,Suite 500 I Grapevine,TX 76051 I PH:817-251-8550 I FX:817-251-8810