ST1501A-CS180815 Priscilla Martinez From:Marcus Marion Sent:Wednesday, August 15, 2018 11:11 AM To:Priscilla Martinez Subject:Freeport PKWY - Utility Conflicts This is a correspondence on the utility conflicts From: Darryl Zbranek Sent: Wednesday, August 15, 2018 8:13 AM To: FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov> Cc: Claudio Segovia <claudio@jvolkconsulting.com>; Jay Volk <jay@jvolkconsulting.com> Subject: FW: Freeport PKWY All, I contacted Rocky Crockett with Zayo and they are trying to set up a contractor to pothole and locate their utility in the areas of conflict at the Bridge. He is going to notify me of when they will meet on site with the contractor. As far as the issues with Frontier please see below. If there are any questions please let me know. Thanks, Darryl Zbranek Chief Construction Inspector City of Coppell, TX (469)507-9095 (cell) www.coppelltx.gov Begin forwarded message: From: "Crenshaw, Andy" <andy.g.crenshaw@ftr.com> Date: August 14, 2018 at 4:56:34 PM CDT To: Marcus Marion <MMarion@coppelltx.gov>, "Barksdale, Barry" <barry.k.barksdale@ftr.com> Subject: RE: Freeport PKWY Marcus: We are waiting on our Engineering Dept. to determine what size cable will need to be placed from the pedestal in conflict to the south of Hard Eight up to the corner @ Hard Eight. We are also going to have to expose a 900pr. cable @ the corner and swing in over into the 3x5 that was placed on top of the storm drain. I have met them on-site twice on the last week (once today). It sounds like they should have a solution by the end of the week. Then it will be setting into motion. I honestly, think it will still probably be 2-3 weeks before we have cable in the ground and cut over. Andy Andy G. Crenshaw Local Manager – Construction Frontier Communications 1 C: 214/425-9008 From: Marcus Marion \[mailto:MMarion@coppelltx.gov\] Sent: Tuesday, August 14, 2018 4:00 PM To: Crenshaw, Andy <andy.g.crenshaw@ftr.com>; Barksdale, Barry <barry.k.barksdale@ftr.com> Subject: Freeport PKWY WARNING: External email. Please verify sender before opening attachments or clicking on links. Hey Andy, I know Mr. Barry is still on vacation, but we wanted to get an update on the fiber by Hard8 and the fiber that goes under the creek crossing and when it will be finished. I guess I just wanted an update on all you have left for the Freeport project. Think you can help me with these? Thank you This communication is confidential. Frontier only sends and receives email on the basis of the terms set out at http://www.frontier.com/email_disclaimer. To stop receiving messages from FreeportProjectST1501 group, stop following it. 2