ST1501A-CS180904
Priscilla Martinez
From:Marcus Marion
Sent:Thursday, September 06, 2018 8:45 AM
To:Priscilla Martinez
Subject:Freeport Reconstruction - Bridge Conflicts Zayo
This is a correspondence for the Freeport PKWY about the conflict utilities
From: Rocky Crockett <rocky.crockett@zayo.com>
Sent: Tuesday, September 4, 2018 3:42 PM
To: Darryl Zbranek <dzbranek@coppelltx.gov>; Thomas Capps <thomas.capps@zayo.com>
Cc: FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Subject: RE: Coppell / Freeport Reconstruction Bridge Conflicts Zayo
Darryl,
I have been in contact with Future Telecom Today and Later tonight or in the morning I’m to receive Cost and Time line
for the duct dig up.
Regards
Rocky Crockett
Project Manager, OSP| Zayo Group
From: Darryl Zbranek \[mailto:dzbranek@coppelltx.gov\]
Sent: Tuesday, September 04, 2018 3:29 PM
To: rocky.crockett@zayo.com; thomas.capps@zayo.com
Cc: FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Subject: RE:Coppell / Freeport Reconstruction Bridge Conflicts Zayo
Rocky and Thomas,
Do you have an update on the Zayo utility conflicts on Freeport Parkway at the bridge area.
From: Darryl Zbranek
Sent: Wednesday, August 29, 2018 6:41 AM
To: 'rocky.crockett@zayo.com' <rocky.crockett@zayo.com>; 'Eric Giebelhaus' <Eric.Giebelhaus@strlco.com>; 'Jimmy
Reed' <Jimmy.Reed@strlco.com>; 'Joe Soto' <Joe.Soto@strlco.com>; FreeportProjectST1501
<freeportprojectst1501@coppelltx.gov>
Cc: thomas.capps@zayo.com
Subject: RE: Freeport Reconstruction Bridge Conflicts Zayo
Rocky,
I have not received a response from the below email sent last week. Please let me know the schedule of when your
contractor will be on site to uncover the Zayo utilities in the conflict areas of our drill shafts.
1
Thank you,
Darryl Zbranek
Chief Construction Inspector
City of Coppell, TX
(972)304-7090
www.coppelltx.gov
From: Darryl Zbranek
Sent: Friday, August 24, 2018 3:28 PM
To: 'rocky.crockett@zayo.com' <rocky.crockett@zayo.com>; 'Eric Giebelhaus' <Eric.Giebelhaus@strlco.com>; Jimmy
Reed <Jimmy.Reed@strlco.com>; Joe Soto <Joe.Soto@strlco.com>; FreeportProjectST1501
<freeportprojectst1501@coppelltx.gov>
Subject: RE: Freeport Reconstruction Bridge Conflicts Zayo
Rocky,
During our meeting this morning we had discussions about Zayo having a contractor excavate and locate the Zayo/Level
3/Century Link utilities in three areas that our drill shafts conflict with. The first area is on the South end of the bridge
where a wing wall drill shaft is to be located. The second is where a drill shaft on abutment 1 is to be located. The third
conflict is the drill shaft on bent 2. We also discussed Zayo hiring a contractor move the Zayo/ Level 3/Century Link
utility in the area at abutment 4, on the North end of the bridge. This line needs to be relocated to avoid the drill shaft.
Zayo requested that the City of Coppell assist with the excavations in these locations by paying Texas Sterling
Contractors approximately $5,000.00 for this work. The actual amount will be determined after the work is complete
based on Time & Materials. The City of Coppell is willing to help with the excavation of the three areas under the
condition that Zayo can have a contractor on site to begin the work by Wednesday August 29, 2018 at 9AM. If Zayo can
meet this schedule, the City will direct Texas Sterling to begin the excavations in the three areas early next week. We will
need written approval from Zayo for Texas Sterling to excavate over the utilities and request that a Zayo representative
be on site during the excavation as a precaution and acceptance of the liability of work directed on behalf of Zayo.
Please let me know if Zayo is agreeable.
Thank you,
Darryl Zbranek
Chief Construction Inspector
City of Coppell, TX
(972)304-7090
www.coppelltx.gov