ST1501A-CS180919
Priscilla Martinez
From:Marcus Marion
Sent:Sunday, September 23, 2018 1:15 PM
To:Priscilla Martinez
Subject:Freeport - Pay estimate and Schedule
Attachments:1723 - 08-2018 Update_BGE Comments.pdf; 1723 Project Narrative 08-27-2018_BGE
Comments.pdf; 1723 Freport Aug 2018 Longest Path_BGE Comments.pdf
This is a correspondence for Freeport PKWY about the schedule
From: Darryl Zbranek
Sent: Friday, September 21, 2018 7:30 AM
To: FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Subject: FW: Pay estimate and Schedule
From: David Crysup <DCrysup@bgeinc.com>
Sent: Wednesday, September 19, 2018 3:01 PM
To: Darryl Zbranek <dzbranek@coppelltx.gov>
Subject: RE: Pay estimate and Schedule
Darryl,
Please see the attached comments and observations on the August schedule update.
Brief summary:
Per the schedule, it appears that Stage 2 roadway subgrade work on the NB side and all bridge work has stopped
due to utility conflicts. Work is scheduled to restart on 09/28/2018.
The work directive from the City to stop time notes the City will review costs to demob/mob when impacts are
known. Please let me know if we can help assess that against the requirements of the specifications.
Project Finish Date now shows to be December 3, 2019. Consider this when providing updates to citizens and
Council. The original finish date was October 4, 2019, so about 2 months later.
Please let me know if you have any questions.
David
From: Darryl Zbranek \[mailto:dzbranek@coppelltx.gov\]
Sent: Friday, September 7, 2018 9:34 AM
To: David Crysup <DCrysup@bgeinc.com>
Subject: Pay estimate and Schedule
FYI
1
Darryl Zbranek
Chief Construction Inspector
City of Coppell, TX
(972)304-7090
www.coppelltx.gov
To stop receiving messages from FreeportProjectST1501 group, stop following it.
2