ST1501A-CS180919 (4)
Activity IDActivity NameActivityCountLongestPathCalendarOriginalDurationRemainingDurationTotalFloatStartFinish1723 - Freeport1723 - Freeport87367d288d0d04-09-2018 A12-03-2019A1320Duration17 Day530d463d0d04-09-2018 A12-03-2019A1600Project Time Charges17 Day523d463d0d04-09-2018 A12-03-2019A1330Milestone 117 Day190d129d4d04-26-2018 A01-03-2019A1020Project Finish17 Day0d0d0d12-03-2019Stage 1Stage 115 Day1d1d3d08-27-201808-27-2018TCP Setup Stage 2TCP Setup Stage 215 Day1d1d3d08-27-201808-27-2018A1060Set PCTB - Center Stripe15 Day1d1d3d08-27-201808-27-2018Stage 2 - NB Dividend to BethelStage 2 - NB Dividend to Bethel1799d79d2d08-06-2018 A01-03-2019RoadwayRoadway1599d79d2d08-06-2018 A01-03-2019A3060Spectrum Conflict at 65+0017 Day7d32d6d08-06-2018 A09-28-2018A3070Frontier Conflict 45+00 to 67+6817 Day7d32d6d08-06-2018 A09-28-2018A3190Century Link Conflict at 9+1317 Day7d32d6d08-06-2018 A09-28-2018A3530Finish Balance Subgrade after Conflict17 Day3d3d6d09-29-201810-01-2018A1720Fine Grade Subgrade15 Day6d6d4d10-02-201810-09-2018A17304" HMAC Ty B15 Day8d8d4d10-09-201810-19-2018A1740Tie Steel - Paving Pass 115 Day5d5d4d10-19-201810-26-2018A1800Paving - Pass 115 Day3d3d4d10-26-201810-31-2018A1750Tie Steel - Paving Pass 215 Day5d5d4d10-31-201811-07-2018A1810Paving - Pass 215 Day3d3d4d11-07-201811-12-2018A1880Cure Paving - Pass 217 Day3d3d4d11-12-201811-15-2018A1980Grade for Sidewalk15 Day12d12d2d11-21-201812-11-2018A1990Pave Sidewalk & Trail15 Day8d8d2d12-11-201812-21-2018A2000Backfill Sidewalk & Trail15 Day2d2d2d12-21-201812-26-2018A2010Grass & Landscape Outside15 Day5d5d2d12-26-201801-03-2019Traffic SignalsTraffic Signals25 Day4d4d2d11-15-201811-21-2018A1520Signal Drill Shafts at Southwestern NB15 Day2d2d2d11-15-201811-19-2018A1540Install Conduit from NB Corners w/ Pull Boxes15 Day2d2d2d11-19-201811-21-2018Stage 3A - SB Dividend to FritzStage 3A - SB Dividend to Fritz2458d58d2d01-03-201904-07-2019A3840Switch Traffic to Stage 3A15 Day1d1d2d01-03-201901-04-2019Sanitary SewerSanitary Sewer65 Day24d24d2d01-11-201902-13-2019A2320Drill Shafts for Aerial SS Crossing15 Day3d3d2d01-11-201901-16-2019A2330Columns for Aerial SS Crossing15 Day3d3d2d01-16-201901-21-2019A2340Caps for Aerial SS Crossing15 Day2d2d2d01-21-201901-22-2019A2350Casing for Aerial SS Crossing15 Day3d3d2d01-22-201901-25-2019A2370Install SS 23+89 to 17+3915 Day8d8d2d01-28-201902-06-2019A2380Rehab Existing SS Manholes15 Day5d5d2d02-07-201902-13-2019BridgeBridge15 Day5d5d2d01-04-201901-11-2019A2030Demo Existing Bridge15 Day5d5d2d01-04-201901-11-2019RoadwayRoadway1531d31d2d02-18-201904-07-2019A24504" HMAC Ty B15 Day3d3d2d02-18-201902-21-2019A2460Tie Steel - Paving Pass 115 Day2d2d2d02-21-201902-22-2019A2520Paving - Pass 115 Day2d2d2d02-25-201902-26-2019A2660Cure Paving - Pass 117 Day3d3d3d02-27-201903-02-2019A2530Paving - Pass 215 Day2d2d1d03-04-201903-05-2019A2540Pave - Turn Lanes15 Day2d2d1d03-06-201903-07-2019A2680Cure - Turn Lanes17 Day3d3d2d03-07-201903-10-2019A2490Tie Steel - 1st Half Cross Streets15 Day1d1d2d03-11-201903-11-2019A2550Pave - 1st Half Cross Streets15 Day2d2d2d03-12-201903-13-2019A2690Cure - 1st Half Intersections17 Day3d3d3d03-14-201903-17-2019A2500Tie Steel - 2nd Half Cross Streets15 Day1d1d2d03-18-201903-18-2019A2560Pave - 2nd Half Cross Streets15 Day2d2d2d03-19-201903-20-2019A2700Cure 2nd Half Intersections17 Day3d3d3d03-21-201903-24-2019A2580Install Colored Stamped Concrete15 Day8d8d2d03-25-201904-03-2019A2720Cure Stamped Concrete17 Day3d3d3d04-04-201904-07-2019LightingLighting15 Day2d2d2d02-14-201902-18-2019A2850Install Conduit Between Medians15 Day2d2d2d02-14-201902-18-2019Stage 3B - Median Dividend to AirlineStage 3B - Median Dividend to Airline1113d13d2d04-08-201904-28-2019A3850Switch Traffic to Stage 3B15 Day1d1d3d04-08-201904-08-2019A3900Remove Concrete Pavement15 Day1d1d3d04-09-201904-09-2019RoadwayRoadway911d11d2d04-10-201904-28-2019A2730Balance & Fine Grade Subgrade15 Day2d2d3d04-10-201904-11-2019A27404" HMAC Ty B15 Day1d1d3d04-11-201904-12-2019-2-1123456789101112131415161718192021222324252627FebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJun201820192020DurationProject Time ChargesMilestone 1Set PCTB - Center StripeSpectrum Conflict at 65+00Frontier Conflict 45+00 to 67+68Century Link Conflict at 9+13Finish Balance Subgrade after ConflictFine Grade Subgrade4" HMAC Ty BTie Steel - Paving Pass 1Paving - Pass 1Tie Steel - Paving Pass 2Paving - Pass 2Cure Paving - Pass 2Grade for SidewalkPave Sidewalk & TrailBackfill Sidewalk & TrailGrass & Landscape OutsideSignal Drill Shafts at Southwestern NBInstall Conduit from NB Corners w/ Pull BoxesSwitch Traffic to Stage 3ADrill Shafts for Aerial SS CrossingColumns for Aerial SS CrossingCaps for Aerial SS CrossingCasing for Aerial SS CrossingInstall SS 23+89 to 17+39Rehab Existing SS ManholesDemo Existing Bridge4" HMAC Ty BTie Steel - Paving Pass 1Paving - Pass 1Cure Paving - Pass 1Paving - Pass 2Pave - Turn LanesCure - Turn LanesTie Steel - 1st Half Cross StreetsPave - 1st Half Cross StreetsCure - 1st Half IntersectionsTie Steel - 2nd Half Cross StreetsPave - 2nd Half Cross StreetsCure 2nd Half IntersectionsInstall Colored Stamped ConcreteCure Stamped ConcreteInstall Conduit Between MediansSwitch Traffic to Stage 3BRemove Concrete PavementBalance & Fine Grade Subgrade4" HMAC Ty B1723 - 08-27-18 Up: 1723 - FreeportCoppell Freeport WBS_109-17-2018 11:10MilestoneCurrent WorkActual WorkCritical Remaining Work% CompleteRemaining Level of EffortActual Level of EffortPage 1 of 2 Data Date: 08-27-2018Project ID: 1723 - 08-27-18 Up Activity IDActivity NameActivityCountLongestPathCalendarOriginalDurationRemainingDurationTotalFloatStartFinishA2750Tie Steel - Paving Pass 115 Day2d2d3d04-12-201904-16-2019A2780Pave - Pass 115 Day1d1d3d04-16-201904-17-2019A2810Cure Pass 117 Day3d3d3d04-17-201904-20-2019A2790Pave - Pass 215 Day1d1d1d04-22-201904-22-2019A2770Tie Steel - Paving Pass 315 Day2d2d1d04-23-201904-24-2019A2800Pave - Pass 315 Day1d1d1d04-24-201904-25-2019A2830Cure Pass 317 Day3d3d2d04-25-201904-28-2019Stage 4A - SB Fritz to BethelStage 4A - SB Fritz to Bethel2593d93d0d04-29-201909-23-2019A3860Switch Traffic to Stage 4A15 Day1d1d2d04-29-201904-29-2019A3910Remove Concrete Pavement15 Day8d8d2d04-30-201905-09-2019Sanitary SewerSanitary Sewer25 Day6d6d2d05-10-201905-20-2019A2940Install SS @ Southwestern15 Day4d4d2d05-10-201905-15-2019A2950Complete SS Rehab Work15 Day2d2d2d05-16-201905-20-2019Storm DrainStorm Drain15 Day8d8d2d05-20-201905-30-2019A3080Storm Drain Impovements SB15 Day8d8d2d05-20-201905-30-2019Water LineWater Line55 Day27d27d2d05-30-201907-10-2019A3100Complete SB Water Connections 28+26 to 45+8015 Day2d2d2d05-30-201906-04-2019A3120Install 16" Water Main 45+80 to 67+6815 Day15d15d2d06-04-201906-25-2019A3140Connect to Existing @ 67+6815 Day1d1d2d06-25-201906-26-2019A3130Complete Connections North of 45+8015 Day2d2d2d06-26-201907-01-2019A3150Remove/Grout Existing Water Line15 Day6d6d2d07-01-201907-10-2019RoadwayRoadway1546d46d0d07-10-201909-23-2019A3210Fine Grade Subgrade15 Day3d3d2d07-10-201907-15-2019A32204" HMAC Ty B15 Day6d6d2d07-15-201907-23-2019A3230Tie Steel - Paving Pass 115 Day3d3d2d07-23-201907-26-2019A3290Paving - Pass 115 Day3d3d2d07-26-201907-31-2019A3240Tie Steel - Paving Pass 215 Day3d3d2d07-31-201908-05-2019A3300Paving - Pass 215 Day3d3d2d08-05-201908-08-2019A3310Pave - Turn Lanes15 Day3d3d2d08-08-201908-13-2019A3450Cure - Turn Lanes17 Day3d3d2d08-13-201908-16-2019A3260Tie Steel - 1st Half Cross Streets15 Day2d2d0d08-19-201908-21-2019A3320Pave - 1st Half Cross Streets15 Day3d3d0d08-21-201908-26-2019A3460Cure - 1st Half Intersections17 Day3d3d0d08-26-201908-29-2019A3270Tie Steel - 2nd Half Cross Streets15 Day2d2d0d08-29-201909-02-2019A3330Pave - 2nd Half Cross Streets15 Day3d3d0d09-03-201909-05-2019A3470Cure 2nd Half Intersections17 Day3d3d0d09-06-201909-09-2019A3350Install Colored Stamped Concrete15 Day10d10d0d09-09-201909-23-2019Stage 4B - Median Airline to BethelStage 4B - Median Airline to Bethel5367d288d0d04-09-2018 A12-03-2019RoadwayRoadway15 Day5d5d0d11-22-201912-03-2019A3820Permanent Striping15 Day5d5d0d11-22-201912-03-2019LandscapingLandscaping4361d288d0d04-09-2018 A12-03-2019A3880Duration17 Day530d463d0d04-09-2018 A12-03-2019A3790Install Irrigation System15 Day12d12d0d09-23-201910-09-2019A3800Install Landscape Borders15 Day8d8d0d10-09-201910-21-2019A3810Install Landscaping15 Day24d24d0d10-21-201911-22-2019-2-1123456789101112131415161718192021222324252627FebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJun201820192020Tie Steel - Paving Pass 1Pave - Pass 1Cure Pass 1Pave - Pass 2Tie Steel - Paving Pass 3Pave - Pass 3Cure Pass 3Switch Traffic to Stage 4ARemove Concrete PavementInstall SS @ SouthwesternComplete SS Rehab WorkStorm Drain Impovements SBComplete SB Water Connections 28+26 to 45+80Install 16" Water Main 45+80 to 67+68Connect to Existing @ 67+68Complete Connections North of 45+80Remove/Grout Existing Water LineFine Grade Subgrade4" HMAC Ty BTie Steel - Paving Pass 1Paving - Pass 1Tie Steel - Paving Pass 2Paving - Pass 2Pave - Turn LanesCure - Turn LanesTie Steel - 1st Half Cross StreetsPave - 1st Half Cross StreetsCure - 1st Half IntersectionsTie Steel - 2nd Half Cross StreetsPave - 2nd Half Cross StreetsCure 2nd Half IntersectionsInstall Colored Stamped ConcretePermanent StripingDurationInstall Irrigation SystemInstall Landscape BordersInstall Landscaping1723 - 08-27-18 Up: 1723 - FreeportCoppell Freeport WBS_109-17-2018 11:10MilestoneCurrent WorkActual WorkCritical Remaining Work% CompleteRemaining Level of EffortActual Level of EffortPage 2 of 2 Data Date: 08-27-2018Project ID: 1723 - 08-27-18 Up