From:Marcus Marion
Sent:Wednesday, October 03, 2018 7:33 AM
To:Priscilla Martinez
Subject:Freeport Reconstruction
This is a correspondence for the Freeport PKWY project
From: Darryl Zbranek
Sent: Wednesday, September 26, 2018 3:20 PM
To: Whidden, Chad S <Chad.Whidden@charter.com>
Cc: FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Subject: RE: Freeport Reconstruction
Chad,
The locates on Freeport show Spectrum Cables beyond the area Bridgepoint worked in that are in conflict with the new
road construction project. When we met Kevin on site he was going to check if the marked cable were actually
Spectrums. There are definitely conflicts on the next phase of the project in the Freeport / Bethel area. I need someone
from Spectrum to meet us on site to let us know that we are clear in the current construction area on Freeport from
Bethel to Southwestern and to look at the area of the next phase of construction. We need to meet as soon as possible,
as I stated earlier our road re-construction project is on hold due to these issues. Please let me know when we can meet
on site.
Thanks,
DZ
From: Whidden, Chad S <Chad.Whidden@charter.com>
Sent: Wednesday, September 26, 2018 3:01 PM
To: Darryl Zbranek <dzbranek@coppelltx.gov>
Subject: FW: Freeport Reconstruction
Darryl, from what I am being told, the splicing was completed on this. Can you confirm if there are still conflicts?
From: Brad Edmondson \[mailto:Brad@gardner100.com\]
Sent: Wednesday, September 26, 2018 1:49 PM
To: Whidden, Chad S
Subject: Re: Freeport Reconstruction
Yes, splicing was completed on this
Sent via the Samsung Galaxy S®6 active, an AT&T 4G LTE smartphone
-------- Original message --------
From: "Whidden, Chad S" <Chad.Whidden@charter.com>
1
Date: 9/26/18 1:43 PM (GMT-06:00)
To: Brad Edmondson <Brad@gardner100.com>
Subject: FW: Freeport Reconstruction
Brad, did GTI do the cutover for this? Just need to know if it was completed.
From: Darryl Zbranek \[mailto:dzbranek@coppelltx.gov\]
Sent: Wednesday, September 26, 2018 1:41 PM
To: Whidden, Chad S
Subject: RE: Freeport Reconstruction
It was Bridgepoint.
From: Whidden, Chad S <Chad.Whidden@charter.com>
Sent: Wednesday, September 26, 2018 1:40 PM
To: Gwin, Phillip B <Phillip.Gwin@charter.com>
Cc: FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>; Darryl Zbranek <dzbranek@coppelltx.gov>; Causey,
Kevin W <Kevin.Causey@charter.com>
Subject: RE: Freeport Reconstruction
Phillip, who was the contractor on this project?
From: Darryl Zbranek \[mailto:dzbranek@coppelltx.gov\]
Sent: Wednesday, August 29, 2018 2:31 PM
To: Causey, Kevin W; Whidden, Chad S
Cc: FreeportProjectST1501
Subject: RE: Freeport Reconstruction
Kevin and Chad,
Please see the e-mails below. The City of Coppell is doing a road reconstruction project on Freeport Parkway From
Bethel to Dividend. We have conflicts with the Spectrum utilities near Bethel Road. A bore has been completed lowering
the line across Freeport but I don’t think it was swapped over to the new line. I have been trying to get a schedule on the
swap over but have had no response. Our contact with Spectrum has been Phillip Gwin but I understand that one of you
is the new contact for the Spectrum reroutes. I would like to set up a meeting on site to discuss the project. Please
respond.
Thank you,
Darryl Zbranek
Chief Construction Inspector
City of Coppell, TX
(972)304-7090 - O
(469)507-9095 - C
www.coppelltx.gov
From: Darryl Zbranek
Sent: Wednesday, August 29, 2018 6:55 AM
To: 'Smith, Renata' <C-Renata.Smith@charter.com>; 'Lehr, Bob E' <Bob.Lehr@charter.com>; 'Cox, Serita L'
2
<Serita.Cox@charter.com>
Cc: 'Gwin, Phillip B' <Phillip.Gwin@charter.com>; 'Brazell, Randy' <Randy.Brazell2@charter.com>; 'Mosley, Ryann' <C-
Ryann.Mosley@charter.com>; FreeportProjectST1501 <freeportprojectst1501@coppelltx.gov>
Subject: RE: Freeport Reconstruction
All,
From the correspondence below received by the City of Coppell, the work in question on Freeport Parkway should have
been scheduled for the week of 8-17-2018 or on the week of 8-22-2018. Does anyone know if this work has been
completed? If it has not, does anyone know when it will be completed? Our previous contact with Spectrum was Phillip
Gwin. Phillip informed me that he is no longer on relocation projects. Would someone please let me know who the new
contact person is for the City of Coppell area. I would like to set up a meeting on site to go over the work and can be
reached by the below contact information.
Thank you,
Darryl Zbranek
Chief Construction Inspector
City of Coppell, TX
(972)304-7090 – O
(469)507-9095
www.coppelltx.gov
From: Darryl Zbranek
Sent: Monday, August 27, 2018 3:11 PM
To: 'Smith, Renata' <C-Renata.Smith@charter.com>; 'Lehr, Bob E' <Bob.Lehr@charter.com>; 'Cox, Serita L'
<Serita.Cox@charter.com>
Cc: 'Gwin, Phillip B' <Phillip.Gwin@charter.com>; 'Brazell, Randy' <Randy.Brazell2@charter.com>; 'Mosley, Ryann' <C-
Ryann.Mosley@charter.com>
Subject: RE: Freeport Reconstruction
I would like to set up an onsite meeting to go over the work that is to be done. Who would be the person with Spectrum
/ Charter for the relocation?
From: Darryl Zbranek
Sent: Monday, August 27, 2018 11:29 AM
To: 'Smith, Renata' <C-Renata.Smith@charter.com>; Lehr, Bob E <Bob.Lehr@charter.com>; Cox, Serita L
<Serita.Cox@charter.com>
Cc: Gwin, Phillip B <Phillip.Gwin@charter.com>; Brazell, Randy <Randy.Brazell2@charter.com>; Mosley, Ryann <C-
Ryann.Mosley@charter.com>
Subject: RE: Freeport Reconstruction
All, do we have an update on when this work will be completed?
Thanks,
3
Darryl Zbranek
Chief Construction Inspector
City of Coppell, TX
(972)304-7090 - O
(469)507-9095 - C
www.coppelltx.gov
From: Smith, Renata <C-Renata.Smith@charter.com>
Sent: Thursday, July 26, 2018 3:47 PM
To: Lehr, Bob E <Bob.Lehr@charter.com>; Cox, Serita L <Serita.Cox@charter.com>
Cc: Darryl Zbranek <dzbranek@coppelltx.gov>; Gwin, Phillip B <Phillip.Gwin@charter.com>; Brazell, Randy
<Randy.Brazell2@charter.com>; Mosley, Ryann <C-Ryann.Mosley@charter.com>
Subject: RE: Freeport Reconstruction
Bob,
If we get this scheduled by tomorrow it can go for 8/22/18
Renata Smith
Project Coordinator
C-Renata.Smith@charter.com
1565 Chenault St.
Dallas, TX 75228
From: Lehr, Bob E
Sent: Thursday, July 26, 2018 11:36 AM
To: Cox, Serita L <Serita.Cox@charter.com>; Smith, Renata <C-Renata.Smith@charter.com>
Cc: Darryl Zbranek <dzbranek@coppelltx.gov>; Gwin, Phillip B <Phillip.Gwin@charter.com>; Brazell, Randy
<Randy.Brazell2@charter.com>
Subject: RE: Freeport Reconstruction
st
Renata please schedule for 1 available, can you give us an estimated date? Appears to be week ending 8/17 is that
correct?
From: Gwin, Phillip B
Sent: Thursday, July 26, 2018 10:13 AM
To: Lehr, Bob E <Bob.Lehr@charter.com>; Brazell, Randy <Randy.Brazell2@charter.com>
Cc: Darryl Zbranek <dzbranek@coppelltx.gov>
Subject: FW: Freeport Reconstruction
Do you have a splice date for this one? It is PID 670111.
4
From: Darryl Zbranek \[mailto:dzbranek@coppelltx.gov\]
Sent: Thursday, July 26, 2018 10:08 AM
To: Gwin, Phillip B <Phillip.Gwin@charter.com>
Subject: RE: Freeport Reconstruction
Hello Phillip, just checking to see if you have a date on when the cable will be swapped over to the new on Freeport
Parkway near the Hard Eight Restaurant in Coppell Tx.
Thanks,
Darryl Zbranek
Chief Construction Inspector
City of Coppell, TX
(469)507-9095 (cell)
www.coppelltx.gov
The contents of this e-mail message and
any attachments are intended solely for the
addressee(s) and may contain confidential
and/or legally privileged information. If you
are not the intended recipient of this message
or if this message has been addressed to you
in error, please immediately alert the sender
by reply e-mail and then delete this message
and any attachments. If you are not the
intended recipient, you are notified that
any use, dissemination, distribution, copying,
or storage of this message or any attachment
is strictly prohibited.
The contents of this e-mail message and
any attachments are intended solely for the
addressee(s) and may contain confidential
and/or legally privileged information. If you
are not the intended recipient of this message
or if this message has been addressed to you
in error, please immediately alert the sender
by reply e-mail and then delete this message
and any attachments. If you are not the
intended recipient, you are notified that
any use, dissemination, distribution, copying,
or storage of this message or any attachment
is strictly prohibited.
The contents of this e-mail message and
any attachments are intended solely for the
addressee(s) and may contain confidential
5
and/or legally privileged information. If you
are not the intended recipient of this message
or if this message has been addressed to you
in error, please immediately alert the sender
by reply e-mail and then delete this message
and any attachments. If you are not the
intended recipient, you are notified that
any use, dissemination, distribution, copying,
or storage of this message or any attachment
is strictly prohibited.
Brad Edmondson
Fiber Manager
Gardner Telecommunications LLC.
555 S. Town East Blvd., Mesquite TX 75149
\[O\]: 972-329-9933 | \[F\]: 972-329-9944 | \[C\]:972-342-7059
www.gardner100.com
E-MAIL CONFIDENTIALITY NOTICE:
The contents of this e-mail message and any attachments are intended
solely for the addressee(s) and may contain confidential and/or legally
privileged information. If you are not the intended recipient of this
message or if this message has been addressed to you in error, please
immediately alert the sender by reply e-mail and then delete this message
and any attachments. If you are not the intended recipient, you are
notified that any use, dissemination, distribution, copying, or storage of
this message or any attachment is strictly prohibited.
The contents of this e-mail message and
any attachments are intended solely for the
addressee(s) and may contain confidential
and/or legally privileged information. If you
are not the intended recipient of this message
or if this message has been addressed to you
in error, please immediately alert the sender
by reply e-mail and then delete this message
and any attachments. If you are not the
intended recipient, you are notified that
any use, dissemination, distribution, copying,
6
or storage of this message or any attachment
is strictly prohibited.
To stop receiving messages from FreeportProjectST1501 group, stop following it.
7