Loading...
1723 Project Narrative 10-25-2018 City of Coppell Project No. ST15-01A Freeport Parkway Baseline Primavera P6 Schedule Narrative As of Data Date: October 25, 2018 Texas Sterling Construction Company 1. PROJECT SUMMARY: Baseline Previous Current Schedule Schedule Schedule Project ID 1723 - Freeport Schedule File ID 1723 - Freeport 1723-09-2018 Update 1723 – 10-2018 Update Data Date 9-Apr-2018 25-September-2018 25-October-18 Contract Days Contract Duration from NTP 550 550 550 Time Extensions Granted 0 0 0 Amended Contract Duration 0 0 0 Current Completion Dates Begin Time Charges 9-Apr-2018 26-Apr-2018 26-Apr-2018 Substantial Completion 4-Oct-2019 25-Oct-2019 22-Nov-2019 Contract Expiration Date 4-Oct-2019 4-Oct-2019 28-Oct-2019 Working Day Variance -14 -42 The project is scheduled to achieve Substantial Completion on October 25, 2019. 2. CRITICAL PATH: Currently the Critical Path is on the roadwork utility conflict activities in Phase 2. 3. MONTHLY SCHEDULE NARRATIVE: All work on subgrade to make ready for paving is still suspended as of August 3, 2018 due to conflicts with existing utilities. Towards the end of the month work continued on Southwestern for WL-O FH and Tie-ins 4. MAJOR ACCOMPLISHMENTS or WORK PERFORMED DURING THE MONTH:  WL-O on Southwestern is currently being tested up to STA. 14+42.  Frontier copper conflict at proposed bridge drill shafts has been relocated  City of Coppell provided a redesign of the bridge at ABUT 1 for wing wall drill shaft 5. AREAS OF CONCERNS, POTENTIAL ISSUES, or DELAYS AFFECTING THE PROJECT: • Conflict with Zayo near Wrangler with subgrade installation. • Conflict with Spectrum near from Southwestern to Bethel. (Scheduled to be clear within 3 weeks) • Conflict with Frontier and the excavation required for paving between Southwestern and Bethel. Met with Frontier on 8/27/2018. They indicated they should be starting work to lower or relocate this line within the next week • WL-O tie-in to 24” existing pipe at STA. 15+90. Plans to existing 24” pipe have been redesigned and materials are currently be manufactured. Estimated lead time is approximately 3 weeks. • Substantial rain days has delayed work on bridge drill shafts. 6. CHANGES/EDITS TO THE SCHEDULE: • Pushed out all utility conflicts to 11/25/2018. 7. WEATHER DELAYS: • 10/8, 10/09, 10/12, 10/15-10/19, 10/24 no work due to extensive rain. 8. SCHEDULE COMMENTS ADDRESSED FROM CLIENT: Attachments: Current update PDF – Adobe PDF of full schedule. Current schedule XER - .xer file of schedule.