ST1501A-CS181108
Daily Field Report - Nov 8, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:04:30 PM
Equipment:Drill RigTraveled mi.
Types of Tests/Observations Performed:
Concrete, Other, Pier Observation
Documents Referenced:
Sheet # B - 23 Detail # 1
Observations/Remarks:
Kleinfelder arrived on jobsite for pier observation of N.B. Freeport Pkwy. Bent # 2. Kleinfelder observed
workers drill three 36diameter piers and penetrated into dark gray unweathered shale. All piers were drilled in
general accordance with the project drawings. Details were documented on straight drilled shaft report.
Kleinfelder sampled from 9 yd.concrete load. Kleinfelder performed test consisting of ambient temperature,
concrete mix temperature, slump, and one set of four 6x12concrete cylinder mold samples. Test results were
recorded on report. Workers placed concrete from trucks through chutes into trimme pipe center of pier rebar
steel cages.
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
Reviewed by: Cody Solvin on 11/12/2018 4:07:26 AM CT
Page 1 of 2
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 8, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Plans and Markups
Fig. A:
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
Reviewed by: Cody Solvin on 11/12/2018 4:07:26 AM CT
Page 2 of 2
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 9, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:Jimmy Reed w/ TSCTime Start:04:30 PM
Equipment:Drill Rig, CraneTraveled mi.
Types of Tests/Observations Performed:
Concrete, Other, Pier observation
Documents Referenced:
Sheet # B-2 Detail # 1
Observations/Remarks:
Kleinfelder arrived on jobsite for pier observation of N.B. Abutment Bent # 4 at Freeport Pkwy. Kleinfelder
observed workers drill two 36diameter piers and penetrated into dark gray bearing stratum for N.B. Abutment
Bent # 4 of Freeport Pkwy. Workers drilled piers in general accordance with the project drawings. Details were
documented on straight drilled shaft report.
Kleinfelder sampled from middle batch of 7 yd.concrete load. Kleinfelder performed test consisting of ambient
temperature, concrete mix temperature, slump, and one set of four 6x12concrete cylinder mold samples.
Test results were recorded on report. Workers placed concrete from trucks through chutes into trimme pipe at
center of pier rebar steel cages.
Kleinfelder picked up one set of cylinders that were performed on 11-8-18 by Mike Perez w/ Kleinfelder.
Marcus w/ City of Coppell was notified of pier observation by Kleinfelder.
Acknowledged By SignatureKleinfelder Representative Signature
Jimmy Reed w/ TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
Reviewed by: Cody Solvin on 11/12/2018 4:07:26 AM CT
Page 1 of 2
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 9, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Plans and Markups
Fig. A:
Acknowledged By SignatureKleinfelder Representative Signature
Jimmy Reed w/ TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
Reviewed by: Cody Solvin on 11/12/2018 4:07:26 AM CT
Page 2 of 2
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 10, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:07:00 AM
Traveled mi.
Types of Tests/Observations Performed:
Sample Pick Up Compression Tests
Documents Referenced:
Observations/Remarks:
Kleinfelder arrived on jobsite for cylinder pickup of one set of cylinders that were performed on 11-9-18 by Mike
Perez w/ Kleinfelder. Kleinfelder picked up set of cylinders and departed jobsite.
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
Reviewed by: Cody Solvin on 11/12/2018 4:07:26 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 21, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:03:30 PM
Equipment:CraneTraveled mi.
Types of Tests/Observations Performed:
Concrete
Documents Referenced:
Observations/Remarks:
Kleinfelder arrived on jobsite for concrete placement of bottom walls at N.B. Freeport Pkwy. Abutment # 4.
Concrete arrived on jobsite at 2:15 pm. Kleinfelder sampled from 10 yd.concrete load. Kleinfelder performed
test consisting of ambient temperature, concrete mix temperature, air content %, slump, and one set of five
4x8concrete cylinder mold samples. Test results were recorded on report. Workers placed concrete from
trucks through chutes into bucket. Concrete was placed from bucket into forms of bottom walls. Concrete was
consolidated with a mechanical vibrator.
Marcus w/ City of Coppell was notified of concrete test results by Kleinfelder.
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
75563
Reviewed by: Joel Peters on 11/27/2018 1:39:11 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
DFR #: 20183887.001A181119 CK
Daily Field Report - Nov 19, 2018 DFR
KLF Project #: 20183887.001A
byColton KrumCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:11:30 PM
Types of Tests/Observations Performed:
Concrete
Documents Referenced:
Observations/Remarks:
I was dispatch to perform concrete sampling and testing. I spoke Jimmy with TSC about specifications and
concrete locations. TSC was placing concrete for a pier. Concrete temperature was 55 degrees. Concrete was
placed with bucket. I performed slump, air, and temperature testing. I created one set of 5(4x8) cylinders for
compressing testing for one 7 day, three 28 days, and one hold. All results were given to Jimmy.
Acknowledged By SignatureKleinfelder Representative Signature
TSCColton Krum
Representing Company Company NameKleinfelder Representative Print Name
74492
Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 17, 2018 KLF Project #: 20183887.001A
byPatrick MartinCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:?Time Start:11:00 AM
Traveled mi.
Types of Tests/Observations Performed:
Sample Pick Up Compression Tests
Documents Referenced:
Observations/Remarks:
I arrived on project site located off of Freeport Road in Coppell, Texas. I picked up 1 set of 5(4x8) cylinders
cast by MP on 11-16-18.
Acknowledged By SignatureKleinfelder Representative Signature
?Patrick Martin
Representing Company Company NameKleinfelder Representative Print Name
74018
Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 16, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:01:30 PM
Equipment:CraneTraveled mi.
Types of Tests/Observations Performed:
Concrete
Documents Referenced:
Observations/Remarks:
Kleinfelder arrived on jobsite for concrete placement of columns at N.B. Freeport Pkwy.
Bent # 3. Kleinfelder sampled from middle batch of 10 yd.concrete load. Kleinfelder performed test consisting
of ambient temperature, concrete mix temperature, air content %, slump, and one set of five 4x8concrete
cylinder mold samples. Test results were recorded on report. Workers placed concrete from trucks through
chutes into bucket. Concrete was placed from bucket into forms of columns. Concrete was consolidated with a
mechanical vibrator.
Marcus w/ City of Coppell was notified of all test results by Kleinfelder.
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
73790
Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 15, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:09:30 AM
Traveled mi.
Types of Tests/Observations Performed:
Sample Pick Up Compression Tests
Documents Referenced:
Observations/Remarks:
Kleinfelder arrived on jobsite for cylinder pickup of one set of cylinders that were performed on 11-14-18 by
Mike Perez w/ Kleinfelder. Kleinfelder picked up set of cylinders and departed jobsite.
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
73406
Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 14, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:04:00 PM
Equipment:Drill RigTraveled mi.
Types of Tests/Observations Performed:
Concrete, Other, Pier observation
Documents Referenced:
Sheet # B-23 Detail # 1
Observations/Remarks:
Kleinfelder arrived on jobsite for pier observation of N.B. Freeport Pkwy. Abutments # 1 and # 4. Kleinfelder
observed workers drill four piers of 36and18diameter. Workers penetrated into dark gray bearing stratum of
piers. All piers were drilled in general accordance with the project drawings. Details were documented on
straight drilled shaft report.
Kleinfelder sampled from 9 yd.concrete load. Kleinfelder performed test consisting of ambient temperature,
concrete mix temperature, slump, and one set of five 4x8concrete cylinder mold samples. Test results were
recorded on report. Workers placed concrete from trucks through chutes into center of pier rebar steel cages.
Kleinfelder picked up one set of cylinders that were performed on 11-13-18 by Mike Perez w/ Kleinfelder.
Marcus w/ City of Coppell was notified of pier observation by Kleinfelder.
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
72998
Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT
Page 1 of 3
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 14, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Plans and Markups
Fig. A:
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
72998
Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT
Page 2 of 3
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 14, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Plans and Markups
Fig. B:
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
72998
Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT
Page 3 of 3
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 13, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:03:30 PM
Equipment:Drill RigTraveled mi.
Types of Tests/Observations Performed:
Concrete, Other, Pier Obersavation
Documents Referenced:
Sheet # B-23 Detail # 1
Observations/Remarks:
Kleinfelder arrived on jobsite for pier observation of N.B. Freeport Pkwy. Abutment # 3. Kleinfelder observed
workers drill three 36piers and penetrated into dark gray bearing stratum for N.B. Freeport Pkwy. Abutment #
3. All piers were drilled in general accordance with the project drawings. Details were documented on straight
drilled shaft report.
Kleinfelder sampled from 9 yd.concrete load. Kleinfelder performed test consisting of ambient temperature,
concrete mix temperature, slump, and one set of five 4x8concrete cylinder mold samples. Test results were
recorded on report. Workers placed concrete from trucks through chutes into trimme pipe center of pier rebar
steel cages.
Marcus w/ City of Coppell was notified of pier observation by Kleinfelder.
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
72599
Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT
Page 1 of 2
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 13, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Plans and Markups
Fig. A:
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
72599
Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT
Page 2 of 2
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 20, 2018 KLF Project #: 20183887.001A
byMike PerezCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:07:30 PM
Traveled mi.
Types of Tests/Observations Performed:
Sample Pick Up Compression Tests
Documents Referenced:
Observations/Remarks:
Kleinfelder arrived on jobsite for cylinder pickup of one set of cylinders that were performed on 11-19-18 by
Colton Krum w/ Kleinfelder. Kleinfelder picked up set of cylinders and departed jobsite.
Acknowledged By SignatureKleinfelder Representative Signature
TSCMike Perez
Representing Company Company NameKleinfelder Representative Print Name
75131
Reviewed by: Cody Solvin on 11/28/2018 3:55:15 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 27, 2018 KLF Project #: 20183887.001A
byTim PickensCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:03:00 PM
Equipment:Crane
Types of Tests/Observations Performed:
Concrete
Documents Referenced:
Observations/Remarks:
I arrived onsite to perform concrete services for back wall on Bridge abutment # 4. I cast 1 set of 5 (4x8)
cylinders.
Acknowledged By SignatureKleinfelder Representative Signature
TSCTim Pickens
Representing Company Company NameKleinfelder Representative Print Name
76550
Reviewed by: Cody Solvin on 11/28/2018 3:55:15 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Nov 28, 2018 KLF Project #: 20183887.001A
byLuis V RiveraCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:Time Start:04:00 PM
Traveled mi.
Types of Tests/Observations Performed:
Sample Pick Up Compression Tests
Documents Referenced:
Observations/Remarks:
I was dispatched to the site to pick up concrete cylinder samples for curing and compression testing.
Kleinfelder Representative Signature
Luis V Rivera
Kleinfelder Representative Print Name
77607
Reviewed by: Cody Solvin on 12/4/2018 3:17:26 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Dec 11, 2018 KLF Project #: 20183887.001A
byPatrick MartinCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:04:30 PM
Types of Tests/Observations Performed:
Concrete
Documents Referenced:
Observations/Remarks:
I arrived at project site located on Freeport Parkway in Coppell, Texas. I was onsite to perform concrete testing
and sampling. I got with Jimmy (TSC) to discuss the project. The mix design being used was Argos #4674CB,
with a 3600 PSI. The slump specification was 5-7, with air at 0-3. He wanted break days of 7, 28, 28, 28, H.
The concrete did not show up until 3:15. After the driver was tested he backed the truck up to the desired
location. He poured the concrete into a bucket that was taken to the location with a crane. They poured a
Abutment #1 that contained around 25 yards of concrete. I casted 1 set of 5(4x8) cylinders for lab compression
testing.
Kleinfelder Representative Signature
Patrick Martin
Kleinfelder Representative Print Name
81372
Reviewed by: Cody Solvin on 12/18/2018 12:48:53 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Dec 11, 2018 KLF Project #: 20183887.001A
byTim PickensCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:11:00 AM
Equipment:Crane
Types of Tests/Observations Performed:
Concrete
Documents Referenced:
Job Specifications
Observations/Remarks:
I arrived onsite to perform concrete services on Bridge Cap # 2. I cast 1 set of 5 (4x8) cylinders on cap # 2.
Also performed Slump,air content & temperature and report test results to Jimmy Reed with TSC.
Kleinfelder Representative Signature
Tim Pickens
Kleinfelder Representative Print Name
81186
Reviewed by: Cody Solvin on 12/18/2018 12:48:53 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063
Daily Field Report - Dec 12, 2018 KLF Project #: 20183887.001A
byDavid LancasterCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:Time Start:09:55 AM
Equipment:F28Traveled mi.
Types of Tests/Observations Performed:
Sample Pick Up Compression Tests
Documents Referenced:
Observations/Remarks:
I reported to Freeport Parkway Reconstruction project in Coppell to pick up 2 sets of 5 (4x8) cylinders cast on
12-11 by Tim P. & Patrick M. The cylinders were transported to the laboratory where they were identified and
placed in the curing room.
Kleinfelder Representative Signature
David Lancaster
Kleinfelder Representative Print Name
81762
Reviewed by: Cody Solvin on 12/18/2018 12:48:53 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063