ST1501A-CS181108 Daily Field Report - Nov 8, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:04:30 PM Equipment:Drill RigTraveled mi. Types of Tests/Observations Performed: Concrete, Other, Pier Observation Documents Referenced: Sheet # B - 23 Detail # 1 Observations/Remarks: Kleinfelder arrived on jobsite for pier observation of N.B. Freeport Pkwy. Bent # 2. Kleinfelder observed workers drill three 36diameter piers and penetrated into dark gray unweathered shale. All piers were drilled in general accordance with the project drawings. Details were documented on straight drilled shaft report. Kleinfelder sampled from 9 yd.concrete load. Kleinfelder performed test consisting of ambient temperature, concrete mix temperature, slump, and one set of four 6x12concrete cylinder mold samples. Test results were recorded on report. Workers placed concrete from trucks through chutes into trimme pipe center of pier rebar steel cages. Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name Reviewed by: Cody Solvin on 11/12/2018 4:07:26 AM CT Page 1 of 2 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 8, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Plans and Markups Fig. A: Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name Reviewed by: Cody Solvin on 11/12/2018 4:07:26 AM CT Page 2 of 2 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 9, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:Jimmy Reed w/ TSCTime Start:04:30 PM Equipment:Drill Rig, CraneTraveled mi. Types of Tests/Observations Performed: Concrete, Other, Pier observation Documents Referenced: Sheet # B-2 Detail # 1 Observations/Remarks: Kleinfelder arrived on jobsite for pier observation of N.B. Abutment Bent # 4 at Freeport Pkwy. Kleinfelder observed workers drill two 36diameter piers and penetrated into dark gray bearing stratum for N.B. Abutment Bent # 4 of Freeport Pkwy. Workers drilled piers in general accordance with the project drawings. Details were documented on straight drilled shaft report. Kleinfelder sampled from middle batch of 7 yd.concrete load. Kleinfelder performed test consisting of ambient temperature, concrete mix temperature, slump, and one set of four 6x12concrete cylinder mold samples. Test results were recorded on report. Workers placed concrete from trucks through chutes into trimme pipe at center of pier rebar steel cages. Kleinfelder picked up one set of cylinders that were performed on 11-8-18 by Mike Perez w/ Kleinfelder. Marcus w/ City of Coppell was notified of pier observation by Kleinfelder. Acknowledged By SignatureKleinfelder Representative Signature Jimmy Reed w/ TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name Reviewed by: Cody Solvin on 11/12/2018 4:07:26 AM CT Page 1 of 2 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 9, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Plans and Markups Fig. A: Acknowledged By SignatureKleinfelder Representative Signature Jimmy Reed w/ TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name Reviewed by: Cody Solvin on 11/12/2018 4:07:26 AM CT Page 2 of 2 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 10, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:07:00 AM Traveled mi. Types of Tests/Observations Performed: Sample Pick Up Compression Tests Documents Referenced: Observations/Remarks: Kleinfelder arrived on jobsite for cylinder pickup of one set of cylinders that were performed on 11-9-18 by Mike Perez w/ Kleinfelder. Kleinfelder picked up set of cylinders and departed jobsite. Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name Reviewed by: Cody Solvin on 11/12/2018 4:07:26 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 21, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:03:30 PM Equipment:CraneTraveled mi. Types of Tests/Observations Performed: Concrete Documents Referenced: Observations/Remarks: Kleinfelder arrived on jobsite for concrete placement of bottom walls at N.B. Freeport Pkwy. Abutment # 4. Concrete arrived on jobsite at 2:15 pm. Kleinfelder sampled from 10 yd.concrete load. Kleinfelder performed test consisting of ambient temperature, concrete mix temperature, air content %, slump, and one set of five 4x8concrete cylinder mold samples. Test results were recorded on report. Workers placed concrete from trucks through chutes into bucket. Concrete was placed from bucket into forms of bottom walls. Concrete was consolidated with a mechanical vibrator. Marcus w/ City of Coppell was notified of concrete test results by Kleinfelder. Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name 75563 Reviewed by: Joel Peters on 11/27/2018 1:39:11 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 DFR #: 20183887.001A181119 CK Daily Field Report - Nov 19, 2018 DFR KLF Project #: 20183887.001A byColton KrumCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:11:30 PM Types of Tests/Observations Performed: Concrete Documents Referenced: Observations/Remarks: I was dispatch to perform concrete sampling and testing. I spoke Jimmy with TSC about specifications and concrete locations. TSC was placing concrete for a pier. Concrete temperature was 55 degrees. Concrete was placed with bucket. I performed slump, air, and temperature testing. I created one set of 5(4x8) cylinders for compressing testing for one 7 day, three 28 days, and one hold. All results were given to Jimmy. Acknowledged By SignatureKleinfelder Representative Signature TSCColton Krum Representing Company Company NameKleinfelder Representative Print Name 74492 Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 17, 2018 KLF Project #: 20183887.001A byPatrick MartinCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:?Time Start:11:00 AM Traveled mi. Types of Tests/Observations Performed: Sample Pick Up Compression Tests Documents Referenced: Observations/Remarks: I arrived on project site located off of Freeport Road in Coppell, Texas. I picked up 1 set of 5(4x8) cylinders cast by MP on 11-16-18. Acknowledged By SignatureKleinfelder Representative Signature ?Patrick Martin Representing Company Company NameKleinfelder Representative Print Name 74018 Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 16, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:01:30 PM Equipment:CraneTraveled mi. Types of Tests/Observations Performed: Concrete Documents Referenced: Observations/Remarks: Kleinfelder arrived on jobsite for concrete placement of columns at N.B. Freeport Pkwy. Bent # 3. Kleinfelder sampled from middle batch of 10 yd.concrete load. Kleinfelder performed test consisting of ambient temperature, concrete mix temperature, air content %, slump, and one set of five 4x8concrete cylinder mold samples. Test results were recorded on report. Workers placed concrete from trucks through chutes into bucket. Concrete was placed from bucket into forms of columns. Concrete was consolidated with a mechanical vibrator. Marcus w/ City of Coppell was notified of all test results by Kleinfelder. Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name 73790 Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 15, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:09:30 AM Traveled mi. Types of Tests/Observations Performed: Sample Pick Up Compression Tests Documents Referenced: Observations/Remarks: Kleinfelder arrived on jobsite for cylinder pickup of one set of cylinders that were performed on 11-14-18 by Mike Perez w/ Kleinfelder. Kleinfelder picked up set of cylinders and departed jobsite. Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name 73406 Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 14, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:04:00 PM Equipment:Drill RigTraveled mi. Types of Tests/Observations Performed: Concrete, Other, Pier observation Documents Referenced: Sheet # B-23 Detail # 1 Observations/Remarks: Kleinfelder arrived on jobsite for pier observation of N.B. Freeport Pkwy. Abutments # 1 and # 4. Kleinfelder observed workers drill four piers of 36and18diameter. Workers penetrated into dark gray bearing stratum of piers. All piers were drilled in general accordance with the project drawings. Details were documented on straight drilled shaft report. Kleinfelder sampled from 9 yd.concrete load. Kleinfelder performed test consisting of ambient temperature, concrete mix temperature, slump, and one set of five 4x8concrete cylinder mold samples. Test results were recorded on report. Workers placed concrete from trucks through chutes into center of pier rebar steel cages. Kleinfelder picked up one set of cylinders that were performed on 11-13-18 by Mike Perez w/ Kleinfelder. Marcus w/ City of Coppell was notified of pier observation by Kleinfelder. Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name 72998 Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT Page 1 of 3 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 14, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Plans and Markups Fig. A: Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name 72998 Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT Page 2 of 3 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 14, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Plans and Markups Fig. B: Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name 72998 Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT Page 3 of 3 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 13, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:03:30 PM Equipment:Drill RigTraveled mi. Types of Tests/Observations Performed: Concrete, Other, Pier Obersavation Documents Referenced: Sheet # B-23 Detail # 1 Observations/Remarks: Kleinfelder arrived on jobsite for pier observation of N.B. Freeport Pkwy. Abutment # 3. Kleinfelder observed workers drill three 36piers and penetrated into dark gray bearing stratum for N.B. Freeport Pkwy. Abutment # 3. All piers were drilled in general accordance with the project drawings. Details were documented on straight drilled shaft report. Kleinfelder sampled from 9 yd.concrete load. Kleinfelder performed test consisting of ambient temperature, concrete mix temperature, slump, and one set of five 4x8concrete cylinder mold samples. Test results were recorded on report. Workers placed concrete from trucks through chutes into trimme pipe center of pier rebar steel cages. Marcus w/ City of Coppell was notified of pier observation by Kleinfelder. Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name 72599 Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT Page 1 of 2 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 13, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Plans and Markups Fig. A: Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name 72599 Reviewed by: Cody Solvin on 11/20/2018 4:34:41 AM CT Page 2 of 2 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 20, 2018 KLF Project #: 20183887.001A byMike PerezCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:07:30 PM Traveled mi. Types of Tests/Observations Performed: Sample Pick Up Compression Tests Documents Referenced: Observations/Remarks: Kleinfelder arrived on jobsite for cylinder pickup of one set of cylinders that were performed on 11-19-18 by Colton Krum w/ Kleinfelder. Kleinfelder picked up set of cylinders and departed jobsite. Acknowledged By SignatureKleinfelder Representative Signature TSCMike Perez Representing Company Company NameKleinfelder Representative Print Name 75131 Reviewed by: Cody Solvin on 11/28/2018 3:55:15 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 27, 2018 KLF Project #: 20183887.001A byTim PickensCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:03:00 PM Equipment:Crane Types of Tests/Observations Performed: Concrete Documents Referenced: Observations/Remarks: I arrived onsite to perform concrete services for back wall on Bridge abutment # 4. I cast 1 set of 5 (4x8) cylinders. Acknowledged By SignatureKleinfelder Representative Signature TSCTim Pickens Representing Company Company NameKleinfelder Representative Print Name 76550 Reviewed by: Cody Solvin on 11/28/2018 3:55:15 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Nov 28, 2018 KLF Project #: 20183887.001A byLuis V RiveraCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:Time Start:04:00 PM Traveled mi. Types of Tests/Observations Performed: Sample Pick Up Compression Tests Documents Referenced: Observations/Remarks: I was dispatched to the site to pick up concrete cylinder samples for curing and compression testing. Kleinfelder Representative Signature Luis V Rivera Kleinfelder Representative Print Name 77607 Reviewed by: Cody Solvin on 12/4/2018 3:17:26 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Dec 11, 2018 KLF Project #: 20183887.001A byPatrick MartinCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:04:30 PM Types of Tests/Observations Performed: Concrete Documents Referenced: Observations/Remarks: I arrived at project site located on Freeport Parkway in Coppell, Texas. I was onsite to perform concrete testing and sampling. I got with Jimmy (TSC) to discuss the project. The mix design being used was Argos #4674CB, with a 3600 PSI. The slump specification was 5-7, with air at 0-3. He wanted break days of 7, 28, 28, 28, H. The concrete did not show up until 3:15. After the driver was tested he backed the truck up to the desired location. He poured the concrete into a bucket that was taken to the location with a crane. They poured a Abutment #1 that contained around 25 yards of concrete. I casted 1 set of 5(4x8) cylinders for lab compression testing. Kleinfelder Representative Signature Patrick Martin Kleinfelder Representative Print Name 81372 Reviewed by: Cody Solvin on 12/18/2018 12:48:53 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Dec 11, 2018 KLF Project #: 20183887.001A byTim PickensCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:TSCTime Start:11:00 AM Equipment:Crane Types of Tests/Observations Performed: Concrete Documents Referenced: Job Specifications Observations/Remarks: I arrived onsite to perform concrete services on Bridge Cap # 2. I cast 1 set of 5 (4x8) cylinders on cap # 2. Also performed Slump,air content & temperature and report test results to Jimmy Reed with TSC. Kleinfelder Representative Signature Tim Pickens Kleinfelder Representative Print Name 81186 Reviewed by: Cody Solvin on 12/18/2018 12:48:53 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063 Daily Field Report - Dec 12, 2018 KLF Project #: 20183887.001A byDavid LancasterCoCoppell: Freeport Pkwy Reconstruction Client:City of Coppell, TX Contractor:Time Start:09:55 AM Equipment:F28Traveled mi. Types of Tests/Observations Performed: Sample Pick Up Compression Tests Documents Referenced: Observations/Remarks: I reported to Freeport Parkway Reconstruction project in Coppell to pick up 2 sets of 5 (4x8) cylinders cast on 12-11 by Tim P. & Patrick M. The cylinders were transported to the laboratory where they were identified and placed in the curing room. Kleinfelder Representative Signature David Lancaster Kleinfelder Representative Print Name 81762 Reviewed by: Cody Solvin on 12/18/2018 12:48:53 AM CT Page 1 of 1 Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063