ST1501A-CS181218
Daily Field Report - Dec 18, 2018 KLF Project #: 20183887.001A
byPatrick MartinCoCoppell: Freeport Pkwy Reconstruction
Client:City of Coppell, TX
Contractor:TSCTime Start:12:15 PM
Types of Tests/Observations Performed:
Concrete
Documents Referenced:
Observations/Remarks:
I arrived on project site located off of Freeport Parkway in Coppell, Texas. I was onsite to perform concrete
testing and sampling. The mix design being used was Argos #4674CB, with a 3600 PSI. The slump
specification was 5-7, with air at 0-3. Jimmy wanted break days of 7, 28, 28, 28, H. When I showed up to the
job site, the concrete truck was already dumping his load. They poured the concrete into a bucket that was
transported to the desired location with a crane. They poured a Abutment 1 Backwall & Wing Wall containing
10 yards of concrete. I casted 1 set of 5(4x8) cylinders for lab compression testing.
Kleinfelder Representative Signature
Patrick Martin
Kleinfelder Representative Print Name
83820
Reviewed by: Cody Solvin on 12/21/2018 3:44:36 AM CT
Page 1 of 1
Kleinfelder Dallas 7805 Mesquite Bend Irving, TX 75063