Hunterwood-CS181121 November 21, 2018 Joel Brown & Co., LLC Joel Brown 500 E. Arapaho Rd. ste 603 Richardson, Texas 75081 RE: Hunterwood Park Bank Stabilization/Trail Project NOTICE TO PROCEED WITH CONSTRUCTION Dear Mr. Brown: This letter will serve as your official notice to begin work on the referenced project on November 26, 2018. Eighty-nine (89) calendar days were bid on this project for the completion of work. Therefore, if work begins on November 26, 2018, then the calendar days on the project will expire on February 23, 2018. Your construction time will officially begin the day of commencement or November 26th, whichever comes first. If you have any questions or need any additional information, please feel free to contact Derrick Thomas, Construction Inspector, at (469-576-5999). Sincerely, Mike Garza Assistant Director of Public Works-Operations Office 972/304-3681 Mgarza@coppelltx.gov