As per your request, staff has reviewed the debris on the north side of Deforest on Mr. McInnis'
property. It appears to be a combination of trees, lumber, and other construction debris. The
following is the proposed estimate:
100 Manhours @ $20.00 per manhour $2,000.00
2 Dump Trucks(2 days)@ $150.00 per day 600.00
1 Backhoe/Loader(2 days)@ 250.00 per day 500.00
2 Chain saws (2 days) @ 25.00 per day I00.00
$3,200.00
This is just an estimate. Staff isn't sure of what all is in the pile of debris that may require
special disposal or additional time to remove.