ST9801-CS000403 (2)FAX (214) 352-3201 TELEPHONE (214) 358-6581
ED BELL CONSTRUCTION COMPANY
POST OFFICE BOX 540787 10605 HARRY HINES
DALLAS, TEXAS 75354-0787 DALLAS, TEXAS 75220
April 3, 2000
Mr. Kevin C. Young, E.I.T.
Freese and Nichols, Inc.
1701 N. Market, Suite 500, LB 51
Dallas. Texas 75201
Re:
Coppell Road Reconstruction
SH 121 to Sandy Lake Road
Coppell Project #: ST 98-01
Dear Mr. Young:
The following prices are for the various subgrade stabilization/paving options for the SH 121 to Parkway Boulevard
portion of the referenced project that were discussed at the March 30, 2000 progress meeting:
Option 1: Cement Stabilization (dry application)
Cement Stabilization 13,436 SY
Cement 390 TNS
$3.91 per SY $52,495.66
$100.00 per SY $39,000.00
$91,495.66
Option 2: Cement Stabilization (slurry application)
EBCC currently doesn't have the equipment necessary to apply slurried cement.
Option 3: Extra 1" of concrete pavement on lime treated subgrade
Unclassified Excavation 422 CY $5.00 per CY
Extra 1" of Concrete Pavement 12,803 SY $3.71 per SY
$2,110.00
$47,499.13
$49,609.13
Option 4: Extra V2 sack of cement for pavement on lime treated subgrade
Cement (Extra ¼ sack) 3,275 CY $2.44 per CY
$7,991.00
If you have any questions regarding this information, don't hesitate to contact our office.
Si, n~rely,
kl,~.l~l~o struct~! Company
Robert D. Weber
Project Engineer
xc:
Mr. Kent Collins, P.E., Engineering and Public Works, City of Coppell
255 Parkway Blvd., Coppell, Texas 75019-4409