ST9801-CS000317P.O. Box 478
Coppell, Texas 75019
972'-462-0022
March 17, 2000
RE: Coppell Road Project #ST98-01 (Sandy Lake Road to SH121)
Dear Coppell Citizen:
The Coppell Road reconstruction project' has progressed over the past. few months with. the
focus being on completion of the water line and progress on storm drain work. The contractor
for the project has notified the city that Phase One of the paving construction will begin on
March 29th. Phase One will include paving and drainage improvements to the east-west
portion of Coppell Road and will entail closure of the road from the SH121 frontage road to
the main entrance of The Mansions Apartments (see map on back of this letter). Again,
Coppell Road from SH 121 to the main entrance of The Mansions will be closed to all
traffic beginning March 29, 2000. The estimated time of the phase one construction is eight
weeks. Advanced signing will be used to wam motorists of the closure and direct traffic to
other routes; particularly Canyon Drive, Coppell Road and SH121 Frontage Road. Please
plan on using these altemate routes for the duration of.Phase One.
Details on the later phases of paving construction are still under consideration, but the City
will work to maintain traffic flow as much as possible. Any long-term lane closures will
require approval from Staff and City Council.
If you have any questions regarding this project or any information provided in this letter,
please contact Larry Davis, Inspector, or me at (972)304-3679, or Gary Pryor with Ed Bell
Construction at (214)358-6581.
Respectfully Yours,
Kent Collins, P.E.
Civil Engineer