ST9801-CS000113Project: Date: Time: Ill. CITY OF COPPELL, TEXAS PROGRESS MEETING AGENDA Coppell Road Paving, Drainage and Water Line Installation January 13, 2000 9:00 AM PROJECT ISSUES A. Utility Conflicts/Relocations (TXU Electric/TXU C_ms/Paragon CabledGTE) B. Storm Drain Construction C. Waterline Construction D. Paving Issues E. Communications with Property Owners/Residents F. Submittals G. Box Culvert Construction H. Time Charged SCHEDULE ISSUES A. Work Expected in Next Month? UPCOMING CALENDAR EVENTS A. Next Progress Meeting (Tentative): January 27, 9:00 am B. Holidays: January 17, 1999 Sent. by: FREESE & NICHOLS 2149202565 01/17/00 9:05AM Job 818 Page 2/3 Fi~EESE - NICHOLS Meetinn Minutes PI'Oj CC t: ,Sul~.icct: I~.ecordcd by: Datc: Locaticm: Allendoes: Coppoll Road hnprovemcnts Construction Meeting Keyin Young January 13, Coppoll City Hall ~tn~ Davis, Kent Collins, Mike M~ulin, Robert Wet~r, Ga~ Pryor, Ahm Greet. Ken Griffin, Keyin Young The.[ollowing is our understanding of the subject tnatter covered during the subjet:t meeting. If this differs from your understanding, please not(fy us within .five working days. % ,,.,. .. ,, ,,, ,, a~,' ',Z~,'~m~ ~i / de nr~,'~ ~ re ~a r~.rd.~ ~e rid ~ ~ ' I. *Closing the road m const.met the box culvei~ is not acceptable Lo the City Engineering I~panment. and will bc ~,,~dd~¢d a d~ad isle. A one-way detour to construct the box culvert is also I'lol rcconm~ended by the Cky. The two-way traffic contn.>l and phasing plan submitted to the City on 12-6-99 is an acceptable option. llowever, the change order for $239,740 is not acceptable to the CZ'i ty. Thcrct~orc, it is recommended that the two-way detour option be pursued, and a new change onler request be prepared. Compensation tk'>r additional bid items shall be considered based on items in the original bid. Any request i~r bid cost increase must t~ of adequate detail for the City to vcril}' correctncss m calculations of added quantities and costs. There is a conflict: in thc field between somc stom~ dn~ns and a GTE duct bank. No field chm~ges have occurred to this point. Jay Simms, with GTE, is currently investigating the situation. They have been asked to pothole the duct bank from 121 to the box culvert to verify depths. GTE was surprised that there were conflicts. An initial contact with GTE requesting approximate line locations and informing them of the job occurred in October 1998, and a formal pl:ms .'rod specifications submittal to GTE occurred in February 1999. FREESE ANI) NICIt(')LS · 1701 N. MARKE'F STREE'F, SUITE 5(1t) · DAI..I..AS, TEXA.% 7521}2-2001 'I'F'.I.!:.P|/f.}NE: 214-920-2500 · FAX: 2 Id-92(}-2565 · FORM DA'IIi: I ltl 1/99 Sent FREESE & NICHOLS 2149202565 01 I17/00 9:06AM Job 818 Page 3/3 Meeting Minutes Coppoll Road Reconstruction January 13, 2000 Page 2 3. In regards to storm drain construction, protection around inlets in progress is needed. The 12" waterline is in place, except for tie-in at the south end by I O'- 12 ', as inilially planned. The line has been pressure tested and is currently being flushed. Samples will be taken after flushing. Tic-ins will occur next form the Mansions to the south. The City water department should be inw>lved in valve operation,al ~h3 Manelion3 vault. Shut down notifications must occur in all siluations. One tie per day i.s anticipated by Ed Bell. = It is requested by the City that 'all fire hydrants tenrain operable throughout construction. Ed Bell has complied and a.~isurcs that they are all usable. Contact with the fire department should be made bcl'orc bagging fire hydrants. 6. Waterline densities are all in check with the exception of some retakes. 7. Paving operations on the east/west portion arc on hold until the (;'FIE'; conflicts are resolved. 8. There are no known property owner issues at this time. 9. *A new traffic control and phasing package is anticipated by the City in order to initiate box culvert construction. 10. Work expected in the next 2-3 weeks includes storm drain lines B- 1 and B-2, with the exception FREE:,SE ANI;) NIC:Itl)I.~q · 1701 N. MARKEl' S'FREE'r, surrE 5(1t) · I).,MA.AS. 'rEXAS 752(12-.2(j01 'I"EI.EPI,{ONE'. 2 t4-920-2500 · FAX: 2 I-i-920-2565 · FORM DATE: I I11 I/~) Sent by: FREESE & NICHOLS 2149202565 01/21/00 10:36AM Job 983 Page 2/3 Nichols. FREESE - NICHOLS Meeting Minutes project: Coppell Road hnprovcments Constructmn Meeting Subject: ' Recorded by: Kevin Young/~5':~ [)ate: Janum3' 13, 2000 Location: Coppeil City Hall Attendees: I..,arry Davis, Kent Collins, Mike Martin, Robert Weber, Gary Pryor. Alan Greet, Ken Griffin, Kevin Young The.fo/lowing is our understanding of the subject tnatter covered during the subject ~neeting. If this differs from your understanding, please notify us within Jive working days. 1. 4' lo.%mg thc road to construct the box culvert is not acceptable to the City Engil)ecring Department. A one-way detour to construct the box culvert is also no! recommended by the City. The two-way traffic control and phasing plan submitted to the £....~ty ( n 12-6-99 is an acceptable option. However, thc. change order for $239,740 is not acceptable to thc City. Thcrel"orc, it is recommended that the two-way detour option be pursued, and a new change ( ~ der request be. prepared. Compensation for addition,d bid items shtdl be considered based on items in the original bid. Any request for bid cost increase must be of adequate detail for Ihe City to verify correcmcss in calculalions of added quantities and costs. '2. Trench safety has been included in the origimd bid to construct the box culvert parallel lo C()ppell Road. Any discussion on additional items will be restricted ti) thai section crossing the road. 3. There is a conflict in the field between some storm drai ns :md a GTI':',2 duct bank. No field changes have occurred to this point. Jay Simms, with GTE, is currently investigating thc. situation. They have been asked to pothole the duct bank from 121 to the box culve]l to verify depths. GTE was surprised that there were conflicts. An initial contact with GTE requcsting approximate line locations anti informing them of the job occurred in October 1998, and a formal plans and specifications submittal to GTE occurred in February 1999. }.:REESE AND NICI I(,)LS · [ 701 N. MAP, KET STRI~ET, SI )lTl'.' 500 * D,,\I,LAS. TF~XA S 75202 TI:LI:?.PHONE: 21 ,:1-92(}-2500 ® FAX: ~ 14- ),()-,~.~( 5 · FORM DA'I'll: I I / I l Sent by: FREESE & NICHOLS 2149202565 01/21/00 10:36AM Job 983 Page 3/3 Meeting Minutes Coppell Road Reconstruction .lanuary 13, 2000 Page 2 4. In regards to storm drain construction, protcction around inlets in progress is needed. 5. The 12" waterline is in place, except for tie-in at the south end by l 0'- 12', as initially planned. The linc has been pressure tested and is currently being flushed. Samples will be taken after Ilushing. Tie-ins will occur next form the Mansions to the south, The City water department should be involved in valve operations. Shut down notifications must occur in all situations. One tic per day is anticipated by Ed Bell. 6. It is re;quested by tile City that all fire hydrants remain operable throughout constrt.~ction. Ed Bell has complied and assures that they are alt usable. Contact wifl~ the tire depzu'tmc.nt should 1~ made before bagging fire hydrants. 7. Waterline densities are all in check with thc exception of some retakes. 8. Paving operations on the east/west portion are on hold until tile GTE conflicts are resolve, cl. 9. There are no known property owner issues at this time. 10. *A new trall~ic control and phasing package is zmticipatcd by the City in order lo initiate box culvcl~ conslruction. I 1. Ed Bell shall use the indicated section item in contract ['or backfi It, compaction, and material usc for 12" water main and ReP installation. 12. Work expected in the next 2-3 weeks includes storm drain linen B- 1 and B-2, with tile exception of laterMs. The waterline will be completed. The GTE conflict and the box culvert issues must be resolved to progress further. *Action Item - END - FREES[-'. AND NIC'ItOI~q * 17{,}t N. MAP, KET STRF. ET. SD I']"E 500 · I)AI.I ..&wi. TEXAS 75202-2OOI TEI,EP[ION[;,: 214.-t,'20-2500 · FAX: 214,920-2565 · FC)RM DATE: I