ST9601-CS 960910 SCHEDULE OF (PROFESSIONAL ENGINEERING) SERVICES
'
WRANGLER DRIV RECONSTRUCTION
(Freeport Parkway to Belt Line Road)
cITY oF CoPPELL, TEXAS
Engineer: TEAGUE NALL AND PERKINS, INC.
Contract Budget: $132,000
Notice To Proceed: 08/19/96
Project Task Schedule
A. SCHEMATIC DESIGN - PHASE I
Pre-Design Conference With City Staff August 19, 1996
Design Field Surveys August 19 - September 13, 1996
Initial Coordination With Utility Companies September 1, 1996
Preliminary Drainage Evaluation/Design September 16 - 20, 1996
Schematic Roadway Design September 23 - 27, 1996
Preliminary Assessment of
Right-of-Way/Easement Needs September 16 - 27, 1996
Schematic Design Report September 30 - October 4, 1996
Submittal of Schematic Design to City October 7,, 1996
City Review of Schematic Design October 7 - 18, 1996
Meeting with City to Discuss Schematic Design October 21, 1996
Schematic Design to Utility Companies October 25, 1996
[Schematic Design Phase Represents 25 % of Contract Budget]
B. PRELIMINARY DESIGN - PHASE II
Second Coordination With Utility Companies November 4, 1996
Detailed Drainage Layout/Design/Calculations October 28 - November 8, 1996
Detailed Roadway Layout/Design/Calculations November 11 - 22, 1996
Detailed Water Line Layout/Design November 25 - December 6, 1996
Preliminary Traffic Control Concept Plan November 25 - December 6, 1996
Preliminary Street Lighting Layout November 25 - December 6, 1996
Finalize Right-of-way/Easement Documents December 9, 1996
Preliminary Quantity Take-Off and
Opinion of Probable Cost December 9 - 13, 1996
Submittal of Preliminary Plans to City December 16, 1996
City Review of Preliminary Hans December 16 - January 3, 1997
Meeting with City to Discuss Preliminary Plans January 6, 1997
Preliminary Plans to Utility Companies January 10, 1997
[Preliminary Design Phase Represents 35 % of Contract Budget]
Schedule of Services - Wrangler Drive Reconstruction
Page 2
C. FINAL PLANS, SPECIFICATIONS & ESTIMATE (PS & E) - PHASE HI
Final Coordination With Utility Companies January 20, 1997
Finalize Paving, Drainage and Water Line Design January 13 - 31, 1997
Finalize Traffic Control Plan January 20 - 31, 1997
Finalize Street Lighting Layout January 27 - 31, 1997
Contract Documents January 13 - 31, 1997
Final Quantity Take-Off and
Opinion of Probable Cost February 3 - 7, 1997
Submittal of Final PS & E to City February 10, 1997
City Review of Final PS & E February 10 - 21, 1997
Meeting with City to Discuss Final PS & E February 24, 1997
Revisions to Final Plans Per City Review February 24 - 28, 1997
Final Plans to Utility Companies March 3, 1997
Contract Documents and Bid Plans to City March 3, 1997
[Final PS & E Represents 30 % of Contract Budget]
D. CONSTRUCTION ADMINISTRATION - PHASE IV
[Construction Administration Phase Represents 10 % of Contract Budget]
Prepared: September 10, 1996