RE: Final Acceptance Letter
AstraZeneca — Parking Expansion
Dear Marco Santamaria
December 16, 2020
Representatives of the City of Coppell have confirmed a final inspection of paving and
utilities for the referenced project. The two-year maintenance bonds have been received.
Maturity on the bonds will be two years from the date of this letter. Maturity on the
Erosion Control Bond LC if necessary will also be two years from the date of this letter.
You may notify MS4 (City of Coppell) at any time during the two-year maintenance
period if stabilization of the site per the SWPPP permit can be demonstrated. If so,
complete and submit a Notice of Termination (NOT) to discontinue coverage under the
SWPPP permit.
A follow up inspection of the facilities will be conducted prior to the lapse of the two-
year bond period. If any punch list items are noted at that time, you will be contacted to
make repairs.
Sincerely,
woe
Marcus D. Marion
Construction Inspector II
(469) 576-7707
mmarion@coppelltx.gov
cc:
Kent Collins, P.E., Director of Public Works
Michael Garza, P.E., Assistant Director of Public Works
Suzanne Arnold, Chief Building Official
Tim Oates, Deputy Fire Chief
Jennifer Miller, Finance Director