ST9601-CN 981203 MEMORANDUM FROM THE DEPARTMENT OF ENGINEERING To: Jim Witt, City Manager From: Mike Martin, P.E., Asst. City Engineer ~ RE: Modification to the Scope of Services to Wrangler Drive Reconstruction Project ST96-01 Consulting Engineer's Contract Date: December 8, 1998 Attached for your approval is modifications to the Scope of Services for Teague, Nail and Perkins relating to the referenced project. The original Scope of Services had a provision in the design contract which allowed the City to request separate sets of plans for the extension of the water line to Freeport Parkway. Initially when this contract was signed there was some uncertainty if the City would construct Wrangler Drive from Belt Line Road to Enterprise Drive or from Belt Line Road to Freeport Parkway. If the City had chosen to build Wrangler Drive from Belt Line Road to Enterprise Drive then the consulting engineer would have had to prepare a separate set of construction plans and documents for the section of Wrangler Drive from Enterprise Drive to Freeport Pkwy. The City constructed the entire section so it freed up approximately $5,000.00. I am proposing that this money be used to allow the consultant Engineer to prepare a set of water line plans to lower approximately 900 feet of an existing 12" water line. The 12" water line needs to be lowered because during the street construction at Coppell Middle School West it was determined that the location and the shallow depth of the water line was undesirable and could over a period of time become a maintenance issue. Attached are cost estimates for the relocation of the 12" water line. Funds are available to do the work and once the plans have been prepared and approved, then an agenda item for an amendment to the contractor's contract can be presented to Council for approval. "CITY OF COPPELL ENGINEERING - EXCELLENCE BY DESIGN" TEAGUE NALL AND PERKINS ENGINEERS I SURVEYORS ~ MUNICIPAL CONSUL TANTS December 03, 1998 Mr. Michael Martin, P.E. Engineering Department City of Coppell 255 Parkway Blvd. P.O. Box 478 Coppell, Texas 75019 Re: Wrangler Road Reconstruction Consulting Engineer's Contract Modification to the Scope of Services Dear Mike: The enclosed Modification to the Scope of Services for the referenced Contract has been prepared, per your request, in accordance with the applicable provisions of the Engineering Services Contract for the Wrangler Drive Reconstruction Project dated August 13, 1996. This modified scope of services deletes the proposed work under Special Services Item No. 3 on Attachment "B" of the contract and adds in lieu of that work the design of approximately 900 linear feet of 12-inch water line relocation and other related improvements along Wrangler Drive, adjacent to the Coppell Middle School West. A preliminary opinion of probable construction cost for these additional improvements is also enclosed for your information. The subject Modification of the Scope of Services is based upon the following understanding: 1. The alignment forthe proposed water line relocation/adjustment will be along the south side of Wrangler Drive, from approximately Sta. 8+25 to Sta. 18+00, save and except a portion of the existing water approximately 30 feet either side of the two (2) water meter vaults to the school. 2. The City will provide plans for the existing water, sanitary sewer, paving and drainage improvements within and/or adjacent to the project area. 3. The proposed improvements will be incorporated into the current construction contract with Tiseo Paving by Change Order and will not require the preparation of a separate set of bid documents, specifications or contract documents. 915 FLOt?ENC~ S~E_FT F~i'r WORFH, rEXAS 76102 (817) J,.~-577J FAX ('817) JJd-281J Mr. Michael Martin, P.E. - City of Coppell December 03, 1998 Page 2 Should you have any questions regarding the proposed Modifications to the Scope of Services, please give me a call. Sincerely, TEAGUE NALL AND PERKINS, INC. Michael A. Jones, P.E. Enclosures Q:~proj-r14~cp196164\docs\corres~contract,modification.water line adjusUetter.(revised).wpd 'I-eSAGUE NALL AND PERKINS, INC. -- IENGINEER'S PRELIMINARY OPINION OF PROBABLE COST December 02, 1998 City of Coppell, Texas Project Name: 12-Inch Water Line Relocation on Wrangler Drive Proj. No. CPL 96164 (Adjacent to Coppell Middle School West) ITEM DESCRIPTION OF ITEM UNIT TOTAL UNIT COST NO. QUANTITY PRICE Proposed W. L. Improvements 1 6-Inch Water Line LF 20 29.00 580.00 2 8-Inch Water Line LF 10 31.50 315.00 3 12-Inch Water Line LF 895 27.00 24,165.00 4 6-Inch Gate Valve Each 2 975.00 1,950.00 5 8-Inch Gate Valve Each I 1,125.00 1,125.00 6 12-Inch Gate Valve Each 2 1,600.00 3,200.00 7 Fittings Tons 0.75 5,250.00 3,937.50 8 Fire Hydrant Each 2 1,800.00 3,600.00 9 Connect to Existing System Each 5 895.00 4,475.00 10 Abandon Existing Water Line LS I 1,500.00 1,500.00 11 Remove/Replace Concrete Driveway SY 100 31.00 3,100.00 12 Protect/Repair Existing Irrigation System LS I 1,500.00 1,500,00 13 Trench Safety for W.L. LF 925 1.10 1,017.50 PREPARED BY: SUBTOTAL $50,465.00 CONTINGENCY (+5%) $2,535.00 REVIEWED & APPROVED BY: TOTAL $53,000.00 p:V;D196164\engrd~l~\12-inch.w~c. osty/l:~. Page 1 of 1 CITY OF COPPELL Consulting Engineer's Contract Modification to the Scope of Services (ATTACHMENT "B" - SPECIAL SERVICES) I. DELETED SCOPE OF SERVICES Delete work under Special Services Item No. 3 related to separation of construction project into two (2) sets of plans. II. ADDITIONAL SCOPE OF SERVICES Design of approximately 900 linear feet of 12-inch water line relocation and other related improvements along Wrangler Drive, adjacent to the Coppell Middle School West. Information from the previous design surveys for Wrangler Drive will be used as the base for the proposed design, therefore no additional design surveys will be performed. III. PROJECT SCHEDULE The additional design will be completed within 20 working days from receipt of written approval/authorization for the Modification to the Scope of Services from the City. IV. COMPENSATION The Engineer shall be paid the same fee for the above described Additional Scope of Services as originally provided for Special Services Item No. 3 in an amount not to exceed the lump sum of Five Thousand and no/100 Dollars ($5,000.00). This amount includes nothing for design surveys and $5,000 for special services. APPROVED: AGREED/ACCEPTED: Dt /~~