Loading...
ST9904-CS010406 TxDOT SH 121 TASK FORCE REPORT Note: Section numbers in narrative below correspond to numbers on drawings. April 6, 2001 I. SH 121 CAPACITY IMPROVEMENTS (STAGE I) A. Completed Sections Section From To Description Date Completed 1 Tarrant CL Denton CR 4-lane ML w/2-lane FR Jul 1992 2 Denton CR Itt 35E 4/6 lane divided highway Nov 1993 3 IH 35E FM 1171 6-lane divided highway Jun 1991 4 FM 1171 Elm Fork 6-lane divided highway Jul 1988 5 Elm Fork BNRR 4-lane divided highway Feb 1994 5B Crider Road FM 423 Eliminate intersection Sep 1995 6 BNRR Legacy 4-lane divided highway Mar 1994 7 Legacy SH 289 4-lane divided highway May 1995 B. Section 8: SH 289 to US 75 (3-lane frontage roads)(CSJ 0364-04-022) 1. The Commission approved funding for this project at their 11-18-99 meet- ing as part of a supplement to the 2000 UTP. This project now has Priori- ty 1 status for FY 2003 with funding from Category 4C - STP-MM ($12 million) and Category 12 - Commission Strategic Priority ($28 million). 2. The current construction cost estimate is $46,320,000 (including the Custer Road Mainlane Overpass to be funded by Collin County). 3. Additional cost to add mainlane overpasses at cross-streets (allowing through traffic to bypass intersections): CROSS-STREET ADDITIONAL COST Rasor ! Hilcrest Road $6,203,933 Colt Road $4,560,874 Independence Parkway $4,473,293 Rowlett Road $4,925,420 Stacy Road $4,153,717 Lake Forest Road $4,016,494 Watters Road $4,416,029 TOTAL $32,749,760 4. Design Status: 32% complete. Anticipated Letting Date: October 2002. Anticipated Plans Adequate Date: August 31,2001. Page I of 4 Updated: 04/06/01 8:55 AM II. SH 121 LEWISVILLE BYPASS (STAGE I) A. Completed Sections Section From To Description Date Completed 9 Denton CR Denton Tap Road 3-lane frontage roads Oct 1998 10 Denton Tap Road Lake Vista 3-lane frontage roads Jul 1988 11 Lake Vista IH 35E 3-lane frontage roads Jun 1996 12 IH 35E FM 544 3-lane frontage roads Oct 1999 III. SH 121 FREEWAY IMPROVEMENTS (STAGE II) A. Section 13: Tarrant County Line to North of Denton Creek (conversion to freeway)(CSJ 0364-02-017 & 0364-03-064) 1. This project is currently listed as a Long Range Project (LRP). 2. Candidate for Category 3A -- National Highway System Mobility. 3. Estimated Construction Costs: CSJ COUNTY FROM TO Length COST 2002 UTP PRELIM RANKINGS 0364-02-017 Dallas Tan'ant CL Denton CL 1.728 $51,000,000 LRP (65 of 121) 0364-03-064 Denton Dallas CL Denton Crk 0.300 $ 9,100,000 LRP (59 of 121) Total $60,100,000 4. TxDOT's Fort Worth District is including this section of the SH 121 Free- way in an ongoing MIS, Schematic, and EA consultant contract they have in the area. The Fort Worth District is working closely with the City of Grapevine to develop the transportation needs in the area. The following are estimated milestone dates: DESCRIPTION ESTIMATED DATE MIS Complete Public Meeting: Preliminary Schematic and EA findings presented. Summer 2001 Public Hearing: Final Schematic and Final EA presented. Winter 2~1/2002 5. The Public Meeting and Hearing dates have been pushed back to allow the consultant to address Grapevine and Coppell ramp location concerns. updated traffic counts have been received from Austin~ Page 2 of 4 Updated: 04/06/01 8:55 AM B. Section 14: Existing SH 121 Near Denton Creek to Existing SH 121 Near FM 544 (Lewisville Bypass)(Mainlanes)(CSJ 3547-03-003, 3547-02-004, 3547-01-005, 3547-01-008, & 3547-01-009) 1. The District recently received additional discretionary programming authority for project development. Combined with the partnership from COG (STP-MM) and local funding, theses projects have been moved to Priority 2 status. 2. Candidate for Category 3A -- National Highway System Mobility. 3. Estimated Construction Costs: CSJ Designer County FROM TO Length COST 3547-03-003 Denton Co - Halff Denton SH 121 Dallas CL 0.500 $ 5,500,000 3547-02-004 Denton Co - Halff Dallas Denton CL Denton CL 1.800 $12,600,000 3547-01-005 Denton Co - Halff Denton Dallas CL Lake Vista 1.085 $ 7,800,000 3547-01-008 Dent°nco~H~ff Denton Lake Vista IH35E 0.730 $40,500,000* 3547-01-009 Denton Co - C&B Denton Hebron FM 544 3.432 $22,400,000 Total $88,800,000 * Includes $18,119,000 for cost of direct connections. C. Section 15: FM 544 to US 75 (CSJ 0364-04-023, 0364-04-024, 0364-03-066, 0364-03-067, 0364-03-086, & 0364-03-087) 1. Frontage Road Estimated Construction Costs (6-lane frontage roads): CSJ County FROM TO Length COST 2002 UTP PRELIM RANKINGS 0364-03-066 Denton FM 544 FM 423 1.917 $ 7,695,917 P2 (12 of 57) 0364-03-067 Denton FM 423 Collin CL 3.030 $12,164,126 P2 (14 of 57) 0364-04-038 Collin Denton CL DNT 0.982 $ 3,942,301 P2 (20 of 57) 0364-04-023 Collin DNT SH 289 1.515 $28,000,000 P1 0364-04-DNT # Collin DNT Interchange See Section 8 Collin SH 289 US 75 PI Total # NTTA project with joint funding: NTTA = $23.84M; T~OT= $10L2M. Note: The Minute Order allowing the NTrA to cOnstruct the DM Interchange Was executed by the Texas Tr~Sportation CO~ssion at its March meeting. Page 3 of 4 Updated: 04/06/01 8:55 AM 2. Mainlane Estimated Construction Costs (Add 6-lane mainlanes to 6-lane frontage roads): CSJ County FROM TO Length COST 2002 UTP PRELIM RANKINGS 0364-03-086 Denton FM 544 FM 423 1.917 $11,920,993 LRP (46 of 121) 0364-03-087 Denton FM 423 Collin CL 3.030 $18,654,120 LRP (41 of 121) 0364-04-039 Collin Denton CL DNT 0.982 $ 6,106,633 P2 (6 of 57) 0364-04-037 Collin DNT SH 289 1.515 $12,400,000 P2 (41 of 57) 0364-04-024 Collin SH 289 US 75 9.059 $57,530,000 LRP (73 of 121) Total $106,611,746 3. Denton County's consultant, Bridgefarmer, is designing mainlanes and frontage roads from FM 544 to the DNT (CSJ's 0364-03-066, 0364-03- 067, 0364-04-038, 0364-03-086, 0364-03-087, 0364-04-039). Page 4 of 4 Updated: 04/06/01 8:55 AM